Mango Heritage
by SAMIR SHRINIVAS KALE · Guhagar, Ratnagiri 415703
What’s in the report? →Possession: Mango Heritage (MahaRERA P52800006761) is marked completed on MahaRERA. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52800006761. Status: Completed.
Source: MahaRERA website — records for P52800006761, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Mango Heritage?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Mango Heritage has moved
31 March 2018
Completion date given when the project was registered
31 March 2019
Extended at the builder's request (MahaRERA application EXT52800000370)
Reason the builder gave MahaRERA:
“Respected Sir/Madam, We have already completed the following tasks relating to the Plotting Project as Guhagar 1. The independent 7/12 extracts of all plots as per the approved layout have been issued by the local Talathi office 2. The per…” Read the full reason
“Respected Sir/Madam, We have already completed the following tasks relating to the Plotting Project as Guhagar 1. The independent 7/12 extracts of all plots as per the approved layout have been issued by the local Talathi office 2. The per the sale deed signed and registered with the land owners, the respective plots have been handover over the owners and the developer. Their respective name have been muted in the records of the local Tahsil office and have appeared on the separate 7/12 extracts. 3. The roads and gutters have been constructed The reasons for the delay are as follows: 1. The…”
Source: Mango Heritage’s extension records on MahaRERA (P52800006761), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mango Heritage
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800006761
- Status
- Completed
- Builder
- SAMIR SHRINIVAS KALE
- Location
- Guhagar, Ratnagiri · 415703
- Project type
- Plotted
- Registered on
- 16 Aug 2017
- Completion date at registration
- March 2018
- Latest completion date
- March 2019
- Delay so far
- 12 months
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 37
Mango Heritage: buildings, flats and land, as filed on MahaRERA
- Land: 12,297 sq m (about 3.0 acres) · recreational space 2,618 sq m
- Boundaries filed include: Old Road, Guhagar Chiplun Road
- Land, as filed: Survey No 128/3
- Map: Get directions
The builder’s record and reviews
Samir Shrinivas Kale has 38 projects on MahaRERA since 2017, this one included. Of the 36 GharKundli has checked: 33 finished, 31 within the promised date and 2 needed more time (typically 12 months); 3 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Mango Heritage →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mango Heritage: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Mango Heritage
What is the possession date of Mango Heritage?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mango Heritage in Guhagar, Ratnagiri is 31 March 2019 — 12 months later than 31 March 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Mango Heritage?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mango Heritage's builder has filed on MahaRERA, the official one, is 31 March 2019, already 12 months later than the 31 March 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Mango Heritage extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Mango Heritage's builder applied to MahaRERA to extend the completion date once: to 31 March 2019, giving the reason "Respected Sir/Madam, We have already completed the following tasks relating to the Plotting Project as Guhagar 1. The independent 7/12 extracts of all plots as per the approved layout have been issued by the local Talathi office 2. The per the sale deed signed and registered with the land owners, the respective plots have been handover over the owners and the developer. Their respective name have been muted in the records of the local Tahsil office and have appeared on the separate 7/12 extracts. 3. The roads and gutters have been constructed The reasons for the delay are as follows: 1. The…".
What is the RERA number of Mango Heritage?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mango Heritage in Guhagar, Ratnagiri is P52800006761.
Is Mango Heritage registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mango Heritage is registered as P52800006761 and its status is "Completed".
What is the current construction status of Mango Heritage? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Mango Heritage's status on MahaRERA is "Completed". GharKundli's full report compares construction progress with the deadline.
Does Mango Heritage have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Mango Heritage safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Mango Heritage is registered on MahaRERA as P52800006761, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Mango Heritage?
According to GharKundli's check of MahaRERA records (updated November 2026), Mango Heritage is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Mango Heritage?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Mango Heritage: gharkundli.com/tools/property-cost-calculator
Has Mango Heritage received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated November 2026), Mango Heritage is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Mango Heritage completed?
According to GharKundli's check of MahaRERA records (updated November 2026), Mango Heritage is marked completed on MahaRERA, and the completion date filed there is 31 March 2019. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Has Mango Heritage uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Mango Heritage was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Mango Heritage's possession date changes?
The latest dates are on Mango Heritage's MahaRERA page (P52800006761). GharKundli's Kundli Watch sends a free WhatsApp update on Mango Heritage every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of Mango Heritage?
According to GharKundli's check of MahaRERA records (updated November 2026), Mango Heritage stands on 12,297 sq m of land (about 3.0 acres) and 2,618 sq m of recreational open space.
What is the track record of Mango Heritage's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Samir Shrinivas Kale has 38 projects on MahaRERA since 2017, this one included. Of the 36 GharKundli has checked: 33 finished, 31 within the promised date and 2 needed more time (typically 12 months); 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Mango Heritage?
Google Maps has reviews of Mango Heritage written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Mango Heritage?
Mango Heritage by SAMIR SHRINIVAS KALE is in Guhagar, Ratnagiri, pincode 415703, Maharashtra, and is registered on MahaRERA as P52800006761, per GharKundli's check of MahaRERA records. Its boundaries filed there include Old Road, Guhagar Chiplun Road. Its land is filed as Survey No 128/3. GharKundli lists all 47 MahaRERA projects in Kirtanwadi (415703).
When was Mango Heritage registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mango Heritage was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.
Does Mango Heritage have any legal issues or court cases?
No court cases are listed for Mango Heritage on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Mango Heritage?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAMIR SHRINIVAS KALE, which has 37 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Mango Heritage
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kirtanwadi (415703)
- Pashchima
- Samarth Residency
- Shree Mahakal Heights
- Mandke Lighthouse
- MHVG Bungalow No 91
- MHVG Bungalow No 86
- Mango Lakefront Paradise Guhagar
- Konkan Bliss Residences
Other projects by SAMIR SHRINIVAS KALE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.