Possession date of Kala Exuberance: 30 April 2027, moved from 30 June 2023 (42 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800017129, and currently active. Its completion date has moved from June 2023 to April 2027: 42 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Kala Exuberance?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Kala Exuberance has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT52800016496)

    Reason the builder gave MahaRERA:
    “1. During Covid and lockdown, The material supply and workers were not available regularly. 2. Because of Covid, People interest of buying commercial property is reduced.So resulting into less booking response. 3. We have sold 2 apartments…” Read the full reason“1. During Covid and lockdown, The material supply and workers were not available regularly. 2. Because of Covid, People interest of buying commercial property is reduced.So resulting into less booking response. 3. We have sold 2 apartments from this project and the occupancy certificate is received from Ratnagiri Municipal Council for respected apartments. 4. 2 apartments are sold from this project and The possession is also given to the respected owners. 5. Now as we have received less booking response , we need more time to complete this project.”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Kala Exuberance’s extension records on MahaRERA (P52800017129), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kala Exuberance

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800017129
Status
Registered and active
Builder
Prafulla Pandurang Magar
Location
Shivajinagar, Ratnagiri · 415639
Project type
Others
Registered on
16 Jul 2018
Completion date at registration
June 2023
Latest completion date
April 2027
Delay so far
42 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
19
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of Kala Exuberance, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Kala Exuberance100%3%50%65%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kala Exuberance every month.

Kala Exuberance: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Kala Exuberance →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kala Exuberance: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Kala Exuberance

What is the possession date of Kala Exuberance?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Kala Exuberance in Shivajinagar, Ratnagiri is 30 April 2027 — 42 months later than 30 June 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Kala Exuberance?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kala Exuberance's builder has filed on MahaRERA, the official one, is 30 April 2027, already 42 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Kala Exuberance extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Kala Exuberance's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "1. During Covid and lockdown, The material supply and workers were not available regularly. 2. Because of Covid, People interest of buying commercial property is reduced.So resulting into less booking response. 3. We have sold 2 apartments from this project and the occupancy certificate is received from Ratnagiri Municipal Council for respected apartments. 4. 2 apartments are sold from this project and The possession is also given to the respected owners. 5. Now as we have received less booking response , we need more time to complete this project.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Kala Exuberance?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Kala Exuberance in Shivajinagar, Ratnagiri is P52800017129.

Is Kala Exuberance registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Kala Exuberance is registered as P52800017129 and its status is "Registered and active".

What is the construction status of Kala Exuberance?

According to GharKundli's check of MahaRERA records (updated November 2026), Kala Exuberance's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Kala Exuberance is 3% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does Kala Exuberance have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Kala Exuberance safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Kala Exuberance is registered on MahaRERA as P52800017129, its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Kala Exuberance's possession date changes?

The latest dates are on Kala Exuberance's MahaRERA page (P52800017129). GharKundli's Kundli Watch sends a free WhatsApp update on Kala Exuberance every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kala Exuberance have?

According to GharKundli's check of MahaRERA records (updated November 2026), Kala Exuberance has one building filed: Kala Exuberance with 5 floors.

How big is the land of Kala Exuberance?

According to GharKundli's check of MahaRERA records (updated November 2026), Kala Exuberance stands on 1,220 sq m of land (about 0.3 acres), with 1,279 sq m of sanctioned built-up area.

Where can I read reviews of Kala Exuberance?

Google Maps has reviews of Kala Exuberance written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Kala Exuberance?

Kala Exuberance by Prafulla Pandurang Magar is in Shivajinagar, Ratnagiri (pincode 415639), Maharashtra, and is registered on MahaRERA as P52800017129, per GharKundli's check of MahaRERA records.

How many homes are in Kala Exuberance?

According to GharKundli's check of MahaRERA records (updated November 2026), Kala Exuberance has 19 homes in 1 tower registered on MahaRERA.

When was Kala Exuberance registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Kala Exuberance was registered on MahaRERA on 16 July 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Kala Exuberance?

1 court case is listed for Kala Exuberance on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Kala Exuberance?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Prafulla Pandurang Magar.

All projects with possession due in 2027 in Ratnagiri →

Other projects in Shivajinagar

All 53 projects in RTG (415639) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.