What’s in the report? →Possession date of Kanade Residency (MahaRERA P52800024011): 30 September 2023, and it has already passed. It has 11 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52800024011. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52800024011, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (September 2023) has passed.
What do you want to know about Kanade Residency?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Kanade Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800024011
- Status
- Lapsed (registration period ended)
- Builder
- Jagdish Vithoba Kanade
- Location
- Khed, Ratnagiri · 415709
- Project type
- Residential / Group Housing
- Registered on
- 14 Jan 2020
- Completion date at registration
- September 2023
- Latest completion date
- September 2023
- Homes
- 11
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Kanade Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Kanade Residency | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kanade Residency every 1–2 months.
Kanade Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: Kanade Residency (5 floors)
- Land: 468 sq m (about 0.1 acres) · sanctioned built-up 586 sq m
- Land, as filed: 1337 2 3
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Kanade Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kanade Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Kanade Residency
What is the possession date of Kanade Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Kanade Residency in Khed, Ratnagiri is 30 September 2023. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Kanade Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kanade Residency's builder has filed on MahaRERA, the official one, is 30 September 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Kanade Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Kanade Residency in Khed, Ratnagiri is P52800024011.
Is Kanade Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Kanade Residency is registered as P52800024011 and its status is "Lapsed (registration period ended)".
What is the current construction status of Kanade Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Kanade Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Kanade Residency is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Kanade Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Kanade Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Kanade Residency is registered on MahaRERA as P52800024011, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Kanade Residency?
Kanade Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Kanade Residency?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Kanade Residency: gharkundli.com/tools/property-cost-calculator
Has Kanade Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Kanade Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Kanade Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Kanade Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Kanade Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Kanade Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Kanade Residency's possession date changes?
The latest dates are on Kanade Residency's MahaRERA page (P52800024011). GharKundli's Kundli Watch sends a free WhatsApp update on Kanade Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kanade Residency have?
According to GharKundli's check of MahaRERA records (updated November 2026), Kanade Residency has one building filed: Kanade Residency with 5 floors.
How big is the land of Kanade Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Kanade Residency stands on 468 sq m of land (about 0.1 acres), with 586 sq m of sanctioned built-up area.
What are the reviews of Kanade Residency?
Google Maps has reviews of Kanade Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Kanade Residency?
Kanade Residency by Jagdish Vithoba Kanade is in Khed, Ratnagiri, pincode 415709, Maharashtra, and is registered on MahaRERA as P52800024011, per GharKundli's check of MahaRERA records. Its land is filed as 1337 2 3. GharKundli lists all 98 MahaRERA projects in Khed (415709).
How many flats are in Kanade Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Kanade Residency has 11 homes in 1 tower registered on MahaRERA.
When was Kanade Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Kanade Residency was registered on MahaRERA on 14 January 2020. GharKundli did not find a title report on the land on file there.
Does Kanade Residency have any legal issues or court cases?
No court cases are listed for Kanade Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Kanade Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Jagdish Vithoba Kanade.
Check it yourself on MahaRERA
- How to check the possession date of Kanade Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Khed (415709)
- Arkan Heritage
- Dream Horizon
- Tathastu Suncity Phase-II
- Icon Tower
- Kokan Valley Phase - II Building No. 01
- Shree Complex
- Hiray's Wisteria
- The Butala Avenue
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.