Aarcon-suyog
by Pradeep Janardan Aaras · Hanuman Peth, Ratnagiri 415709
What’s in the report? →Possession date of Aarcon-suyog (MahaRERA P52800024739): 30 October 2021, moved from 30 November 2020 (11 months later), and it has already passed. It has 1 home. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52800024739. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52800024739, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2021) has passed.
What do you want to know about Aarcon-suyog?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Aarcon-suyog has moved
30 November 2020
Completion date given when the project was registered
30 April 2021
Extended at the builder's request (MahaRERA application EXT52800008561)
Reason the builder gave MahaRERA: “Labourers and raw materials are not available due to (COVID-19)Corona pandemic crisis lock down. The construction of the project is in Konkan division which is affected by heavy monsoon.”
30 October 2021
Revised completion date on MahaRERA
Source: Aarcon-suyog’s extension records on MahaRERA (P52800024739), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aarcon-suyog
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800024739
- Status
- Lapsed (registration period ended)
- Builder
- Pradeep Janardan Aaras
- Location
- Hanuman Peth, Ratnagiri · 415709
- Project type
- Commercial
- Registered on
- 2 Mar 2020
- Completion date at registration
- November 2020
- Latest completion date
- October 2021
- Delay so far
- 11 months
- Homes
- 1
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Aarcon-suyog, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Aarcon Suyog | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aarcon-suyog every 1–2 months.
Aarcon-suyog: buildings, flats and land, as filed on MahaRERA
- Buildings: Aarcon Suyog (6 floors)
- Land: 299 sq m (about 0.1 acres) · sanctioned built-up 299 sq m · recreational space 158 sq m
- Land, as filed: 1554,1555
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Aarcon-suyog →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aarcon-suyog: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Aarcon-suyog
What is the possession date of Aarcon-suyog?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aarcon-suyog in Hanuman Peth, Ratnagiri is 30 October 2021 — 11 months later than 30 November 2020, the date given at registration. That date has already passed.
The date has already moved 11 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Aarcon-suyog?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aarcon-suyog's builder has filed on MahaRERA, the official one, is 30 October 2021, already 11 months later than the 30 November 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Aarcon-suyog extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Aarcon-suyog's builder applied to MahaRERA to extend the completion date once: to 30 April 2021, giving the reason "Labourers and raw materials are not available due to (COVID-19)Corona pandemic crisis lock down. The construction of the project is in Konkan division which is affected by heavy monsoon.".
What is the RERA number of Aarcon-suyog?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aarcon-suyog in Hanuman Peth, Ratnagiri is P52800024739.
Is Aarcon-suyog registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Aarcon-suyog is registered as P52800024739 and its status is "Lapsed (registration period ended)".
What is the current construction status of Aarcon-suyog? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Aarcon-suyog's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Aarcon Suyog is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Aarcon-suyog have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Aarcon-suyog safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Aarcon-suyog is registered on MahaRERA as P52800024739, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 11 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Aarcon-suyog?
Aarcon-suyog isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Aarcon-suyog?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Aarcon-suyog: gharkundli.com/tools/property-cost-calculator
Has Aarcon-suyog received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Aarcon-suyog isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 October 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Aarcon-suyog?
According to GharKundli's check of MahaRERA records (updated November 2026), Aarcon-suyog's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 October 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Aarcon-suyog uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Aarcon-suyog was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Aarcon-suyog's possession date changes?
The latest dates are on Aarcon-suyog's MahaRERA page (P52800024739). GharKundli's Kundli Watch sends a free WhatsApp update on Aarcon-suyog every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aarcon-suyog have?
According to GharKundli's check of MahaRERA records (updated November 2026), Aarcon-suyog has one building filed: Aarcon Suyog with 6 floors.
How big is the land of Aarcon-suyog?
According to GharKundli's check of MahaRERA records (updated November 2026), Aarcon-suyog stands on 299 sq m of land (about 0.1 acres), with 299 sq m of sanctioned built-up area and 158 sq m of recreational open space.
What are the reviews of Aarcon-suyog?
Google Maps has reviews of Aarcon-suyog written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Aarcon-suyog?
Aarcon-suyog by Pradeep Janardan Aaras is in Hanuman Peth, Ratnagiri, pincode 415709, Maharashtra, and is registered on MahaRERA as P52800024739, per GharKundli's check of MahaRERA records. Its land is filed as 1554,1555. GharKundli lists all 98 MahaRERA projects in Khed (415709).
How many flats are in Aarcon-suyog?
According to GharKundli's check of MahaRERA records (updated November 2026), Aarcon-suyog has 1 home in 1 tower registered on MahaRERA.
When was Aarcon-suyog registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Aarcon-suyog was registered on MahaRERA on 2 March 2020. GharKundli did not find a title report on the land on file there.
Does Aarcon-suyog have any legal issues or court cases?
No court cases are listed for Aarcon-suyog on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Aarcon-suyog?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Pradeep Janardan Aaras.
Check it yourself on MahaRERA
- How to check the possession date of Aarcon-suyog
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Khed
- Siddheshwar Anant Residency
- Shree Samarth Krupa Sankalp
- Dream Horizon
- Shree Complex
- The Butala Avenue
- Vedant Residency
- Arkan Heritage
- Hiray's Wisteria
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.