Possession date of RADHAKRISHNA ENCLAVE: 28 February 2023, moved from 30 September 2022 (5 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52800026002. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (February 2023) has passed.
What do you want to know about RADHAKRISHNA ENCLAVE?
How the possession date of RADHAKRISHNA ENCLAVE has moved
30 September 2022
Completion date given when the project was registered
28 February 2023
Extended at the builder's request (MahaRERA application EXT52800012581)
Reason the builder gave MahaRERA: “Work is 95% Completed and will be completed earlier”
Source: RADHAKRISHNA ENCLAVE’s extension records on MahaRERA (P52800026002), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RADHAKRISHNA ENCLAVE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the February 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800026002
- Status
- Lapsed (registration period ended)
- Builder
- Nisar Hassan Wagle
- Location
- Nachane, Ratnagiri · 415612
- Project type
- Others
- Registered on
- 7 Aug 2020
- Completion date at registration
- September 2022
- Latest completion date
- February 2023
- Delay so far
- 5 months
- Homes
- 18
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of RADHAKRISHNA ENCLAVE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RADHAKRISHNA ENCLAVE | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RADHAKRISHNA ENCLAVE every month.
RADHAKRISHNA ENCLAVE: buildings, flats and land, as filed on MahaRERA
- Buildings: RADHAKRISHNA ENCLAVE (6 floors)
- Land: 480 sq m (about 0.1 acres) · sanctioned built-up 618 sq m
- Boundaries filed include: Service Road
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of RADHAKRISHNA ENCLAVE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RADHAKRISHNA ENCLAVE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RADHAKRISHNA ENCLAVE
What is the possession date of RADHAKRISHNA ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RADHAKRISHNA ENCLAVE in Nachane, Ratnagiri is 28 February 2023 — 5 months later than 30 September 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for RADHAKRISHNA ENCLAVE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RADHAKRISHNA ENCLAVE's builder has filed on MahaRERA, the official one, is 28 February 2023, already 5 months later than the 30 September 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RADHAKRISHNA ENCLAVE extended?
According to GharKundli's check of MahaRERA records (updated November 2026), RADHAKRISHNA ENCLAVE's builder applied to MahaRERA to extend the completion date once: to 28 February 2023, giving the reason "Work is 95% Completed and will be completed earlier".
What is the RERA number of RADHAKRISHNA ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RADHAKRISHNA ENCLAVE in Nachane, Ratnagiri is P52800026002.
Is RADHAKRISHNA ENCLAVE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RADHAKRISHNA ENCLAVE is registered as P52800026002 and its status is "Lapsed (registration period ended)".
What is the construction status of RADHAKRISHNA ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), RADHAKRISHNA ENCLAVE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on RADHAKRISHNA ENCLAVE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does RADHAKRISHNA ENCLAVE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is RADHAKRISHNA ENCLAVE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), RADHAKRISHNA ENCLAVE is registered on MahaRERA as P52800026002, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 5 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RADHAKRISHNA ENCLAVE's possession date changes?
The latest dates are on RADHAKRISHNA ENCLAVE's MahaRERA page (P52800026002). GharKundli's Kundli Watch sends a free WhatsApp update on RADHAKRISHNA ENCLAVE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RADHAKRISHNA ENCLAVE have?
According to GharKundli's check of MahaRERA records (updated November 2026), RADHAKRISHNA ENCLAVE has one building filed: RADHAKRISHNA ENCLAVE with 6 floors.
How big is the land of RADHAKRISHNA ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), RADHAKRISHNA ENCLAVE stands on 480 sq m of land (about 0.1 acres), with 618 sq m of sanctioned built-up area.
Where can I read reviews of RADHAKRISHNA ENCLAVE?
Google Maps has reviews of RADHAKRISHNA ENCLAVE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RADHAKRISHNA ENCLAVE?
RADHAKRISHNA ENCLAVE by Nisar Hassan Wagle is in Nachane, Ratnagiri (pincode 415612), Maharashtra, and is registered on MahaRERA as P52800026002, per GharKundli's check of MahaRERA records. Its boundaries filed there include Service Road.
How many homes are in RADHAKRISHNA ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), RADHAKRISHNA ENCLAVE has 18 homes in 1 tower registered on MahaRERA.
When was RADHAKRISHNA ENCLAVE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RADHAKRISHNA ENCLAVE was registered on MahaRERA on 7 August 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on RADHAKRISHNA ENCLAVE?
No court cases are listed for RADHAKRISHNA ENCLAVE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of RADHAKRISHNA ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Nisar Hassan Wagle, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of RADHAKRISHNA ENCLAVE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nachane
Other projects by Nisar Hassan Wagle
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.