KRISHNA RESIDENCY
by Nilesh Madanlal Gundecha · Nachane, Ratnagiri
Possession date of KRISHNA RESIDENCY: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52800050437. Status: In abeyance (on hold by MahaRERA). Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about KRISHNA RESIDENCY?
How the possession date of KRISHNA RESIDENCY has moved
30 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: KRISHNA RESIDENCY’s extension records on MahaRERA (P52800050437), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KRISHNA RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800050437
- Status
- In abeyance (on hold by MahaRERA)
- Builder
- Nilesh Madanlal Gundecha
- Location
- Nachane, Ratnagiri · 415639
- Project type
- Others
- Registered on
- 12 Apr 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 44
- Sold or booked
- 27%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of KRISHNA RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PHASE - I B and C - Wing | 100% | 85% | 75% | 0% |
| PHASE - II A-Wing | 100% | 0% | 3% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- PHASE - I B and C - Wing: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KRISHNA RESIDENCY every month.
KRISHNA RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: PHASE - I B and C - Wing (5 floors, 32 units) · PHASE - II A-Wing (3 floors, 20 units)
- Car parking: 4 covered, 80 open
- Land: 1,725 sq m (about 0.4 acres) · sanctioned built-up 1,866 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of KRISHNA RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KRISHNA RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KRISHNA RESIDENCY
What is the possession date of KRISHNA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KRISHNA RESIDENCY in Nachane, Ratnagiri is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for KRISHNA RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KRISHNA RESIDENCY's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of KRISHNA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KRISHNA RESIDENCY in Nachane, Ratnagiri is P52800050437.
Is KRISHNA RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA RESIDENCY is registered as P52800050437 and its status is "In abeyance (on hold by MahaRERA)".
What is the construction status of KRISHNA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA RESIDENCY's status on MahaRERA is "In abeyance (on hold by MahaRERA)". As filed by the builder, slab work ranges from 0% to 85% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does KRISHNA RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is KRISHNA RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA RESIDENCY is registered on MahaRERA as P52800050437, its MahaRERA status is "In abeyance (on hold by MahaRERA)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KRISHNA RESIDENCY's possession date changes?
The latest dates are on KRISHNA RESIDENCY's MahaRERA page (P52800050437). GharKundli's Kundli Watch sends a free WhatsApp update on KRISHNA RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KRISHNA RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA RESIDENCY has 2 buildings filed: PHASE - I B and C - Wing with 5 floors and 32 units; PHASE - II A-Wing with 3 floors and 20 units.
How much parking does KRISHNA RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 4 covered and 80 open car parking spaces for KRISHNA RESIDENCY.
How big is the land of KRISHNA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA RESIDENCY stands on 1,725 sq m of land (about 0.4 acres), with 1,866 sq m of sanctioned built-up area.
Where can I read reviews of KRISHNA RESIDENCY?
Google Maps has reviews of KRISHNA RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KRISHNA RESIDENCY?
KRISHNA RESIDENCY by Nilesh Madanlal Gundecha is in Nachane, Ratnagiri (pincode 415639), Maharashtra, and is registered on MahaRERA as P52800050437, per GharKundli's check of MahaRERA records.
How many homes are in KRISHNA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA RESIDENCY has 44 homes in 2 towers registered on MahaRERA, and 27% of them are sold or booked.
When was KRISHNA RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA RESIDENCY was registered on MahaRERA on 12 April 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on KRISHNA RESIDENCY?
No court cases are listed for KRISHNA RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of KRISHNA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Nilesh Madanlal Gundecha.
Check it yourself on MahaRERA
- How to check the possession date of KRISHNA RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Ratnagiri →
Other projects in pincode 415639
- VIJAYSHREE
- AJWA ESTATE PHASE II
- MAHALAKSHMI RESIDENCY
- MAHESHWAR
- SAI SANGAM RESIDENCY
- SHUBHANKAR PRARAMBH
- ORCHID PLATINO PHASE - I
- VISHWATEJ
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.