VIJAYSHREE
by Shailesh Pandurang Pednekar · Opp Vishwanagar, Ratnagiri
Possession date of VIJAYSHREE: 31 January 2027, moved from 30 December 2023 (37 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52800019041, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VIJAYSHREE?
How the possession date of VIJAYSHREE has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT52800018076)
Reason the builder gave MahaRERA: “Project is almost on the verge of Completion”
30 June 2025
Extended at the builder's request (MahaRERA application EXT52800025609)
Reason the builder gave MahaRERA: “Project is almost on the verge of Completion.”
31 March 2026
Extended at the builder's request (MahaRERA application EA04102518015)
Reason the builder gave MahaRERA: “Project is Completed and OC Received”
31 July 2026
Extended at the builder's request
31 January 2027
Extended at the builder's request (MahaRERA application EA30092639009)
Reason the builder gave MahaRERA: “Project is Completed, OC Received But Correction window was not open in the mean time Project due date was over and hence now apply for extention.”
Source: VIJAYSHREE’s extension records on MahaRERA (P52800019041), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VIJAYSHREE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800019041
- Status
- Registered and active
- Builder
- Shailesh Pandurang Pednekar
- Location
- Opp Vishwanagar, Ratnagiri · 415639
- Project type
- Residential / Group Housing
- Registered on
- 28 Dec 2018
- Completion date at registration
- December 2023
- Latest completion date
- January 2027
- Delay so far
- 37 months
- Homes
- 32
- Sold or booked
- 63%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of VIJAYSHREE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VIJAYSHREE | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- VIJAYSHREE: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VIJAYSHREE every month.
VIJAYSHREE: buildings, flats and land, as filed on MahaRERA
- Buildings: VIJAYSHREE (9 floors, 33 units)
- Car parking: 17 covered
- Land: 1,297 sq m (about 0.3 acres) · sanctioned built-up 990 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VIJAYSHREE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VIJAYSHREE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VIJAYSHREE
What is the possession date of VIJAYSHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VIJAYSHREE in Opp Vishwanagar, Ratnagiri is 31 January 2027 — 37 months later than 30 December 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for VIJAYSHREE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VIJAYSHREE's builder has filed on MahaRERA, the official one, is 31 January 2027, already 37 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VIJAYSHREE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), VIJAYSHREE's builder applied to MahaRERA to extend the completion date 5 times: to 29 December 2024, giving the reason "Project is almost on the verge of Completion"; to 30 June 2025, giving the reason "Project is almost on the verge of Completion."; to 31 March 2026, giving the reason "Project is Completed and OC Received"; to 31 July 2026; to 31 January 2027, giving the reason "Project is Completed, OC Received But Correction window was not open in the mean time Project due date was over and hence now apply for extention.".
What is the RERA number of VIJAYSHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VIJAYSHREE in Opp Vishwanagar, Ratnagiri is P52800019041.
Is VIJAYSHREE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VIJAYSHREE is registered as P52800019041 and its status is "Registered and active".
What is the construction status of VIJAYSHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), VIJAYSHREE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VIJAYSHREE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does VIJAYSHREE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is VIJAYSHREE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VIJAYSHREE is registered on MahaRERA as P52800019041, its completion date has moved 37 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VIJAYSHREE's possession date changes?
The latest dates are on VIJAYSHREE's MahaRERA page (P52800019041). GharKundli's Kundli Watch sends a free WhatsApp update on VIJAYSHREE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VIJAYSHREE have?
According to GharKundli's check of MahaRERA records (updated October 2026), VIJAYSHREE has one building filed: VIJAYSHREE with 9 floors and 33 units.
How much parking does VIJAYSHREE have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 17 covered car parking spaces for VIJAYSHREE.
How big is the land of VIJAYSHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), VIJAYSHREE stands on 1,297 sq m of land (about 0.3 acres), with 990 sq m of sanctioned built-up area.
Where can I read reviews of VIJAYSHREE?
Google Maps has reviews of VIJAYSHREE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VIJAYSHREE?
VIJAYSHREE by Shailesh Pandurang Pednekar is in Opp Vishwanagar, Ratnagiri (pincode 415639), Maharashtra, and is registered on MahaRERA as P52800019041, per GharKundli's check of MahaRERA records.
How many homes are in VIJAYSHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), VIJAYSHREE has 32 homes in 1 tower registered on MahaRERA, and 63% of them are sold or booked.
When was VIJAYSHREE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VIJAYSHREE was registered on MahaRERA on 28 December 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on VIJAYSHREE?
No court cases are listed for VIJAYSHREE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VIJAYSHREE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shailesh Pandurang Pednekar.
Check it yourself on MahaRERA
- How to check the possession date of VIJAYSHREE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Ratnagiri →
Other projects in Ratnagiri
- LAXMI KEHSAV NAGAR PHASE II
- ASHTVINAYAK GAURAV SANKUL
- RAM VIJAY
- SHUBHANKAR PRARAMBH
- SAI SANGAM RESIDENCY
- KOHINOOR CHAITANYA
- Searock Residency
- OCEAN INFINITY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.