Possession date of ASHTVINAYAK GAURAV SANKUL: 31 December 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1280002601995, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ASHTVINAYAK GAURAV SANKUL?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on ASHTVINAYAK GAURAV SANKUL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1280002601995
Status
Registered and active
Builder
DHANASHRI DEVELOPERS
Location
Malnaka, Ratnagiri · 415612
Project type
Residential / Group Housing
Registered on
22 Sep 2026
Completion date at registration
December 2029
Homes
46
Sold or booked
0%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of ASHTVINAYAK GAURAV SANKUL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ASHTVINAYAK GAURAV SANKUL / WING A0%0%0%0%
ASHTVINAYAK GAURAV SANKUL / WING B0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • ASHTVINAYAK GAURAV SANKUL: covers 9 floors
  • ASHTVINAYAK GAURAV SANKUL: covers 7 floors

Latest CC order on MahaRERA: dated 19/12/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ASHTVINAYAK GAURAV SANKUL every month.

ASHTVINAYAK GAURAV SANKUL: buildings, flats and land, as filed on MahaRERA

  • Buildings: ASHTVINAYAK GAURAV SANKUL (9 floors, 28 units) · ASHTVINAYAK GAURAV SANKUL (7 floors, 18 units)
  • Car parking: 12 covered
  • Land: 1,238 sq m (about 0.3 acres) · sanctioned built-up 2,771 sq m

The builder’s record and reviews

Dhanashri Developers has 2 projects on MahaRERA since 2025, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of ASHTVINAYAK GAURAV SANKUL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ASHTVINAYAK GAURAV SANKUL: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ASHTVINAYAK GAURAV SANKUL

What is the possession date of ASHTVINAYAK GAURAV SANKUL?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ASHTVINAYAK GAURAV SANKUL in Malnaka, Ratnagiri is 31 December 2029.

Is the builder's possession date different from the MahaRERA date for ASHTVINAYAK GAURAV SANKUL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ASHTVINAYAK GAURAV SANKUL's builder has filed on MahaRERA, the official one, is 31 December 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of ASHTVINAYAK GAURAV SANKUL?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ASHTVINAYAK GAURAV SANKUL in Malnaka, Ratnagiri is PR1280002601995.

Is ASHTVINAYAK GAURAV SANKUL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHTVINAYAK GAURAV SANKUL is registered as PR1280002601995 and its status is "Registered and active".

What is the construction status of ASHTVINAYAK GAURAV SANKUL?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHTVINAYAK GAURAV SANKUL's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does ASHTVINAYAK GAURAV SANKUL have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is ASHTVINAYAK GAURAV SANKUL safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHTVINAYAK GAURAV SANKUL is registered on MahaRERA as PR1280002601995, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ASHTVINAYAK GAURAV SANKUL's possession date changes?

The latest dates are on ASHTVINAYAK GAURAV SANKUL's MahaRERA page (PR1280002601995). GharKundli's Kundli Watch sends a free WhatsApp update on ASHTVINAYAK GAURAV SANKUL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ASHTVINAYAK GAURAV SANKUL have?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHTVINAYAK GAURAV SANKUL has 2 buildings filed: ASHTVINAYAK GAURAV SANKUL with 9 floors and 28 units; ASHTVINAYAK GAURAV SANKUL with 7 floors and 18 units.

How much parking does ASHTVINAYAK GAURAV SANKUL have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 covered car parking spaces for ASHTVINAYAK GAURAV SANKUL.

How big is the land of ASHTVINAYAK GAURAV SANKUL?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHTVINAYAK GAURAV SANKUL stands on 1,238 sq m of land (about 0.3 acres), with 2,771 sq m of sanctioned built-up area.

What is the track record of ASHTVINAYAK GAURAV SANKUL's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Dhanashri Developers has 2 projects on MahaRERA since 2025, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ASHTVINAYAK GAURAV SANKUL?

Google Maps has reviews of ASHTVINAYAK GAURAV SANKUL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ASHTVINAYAK GAURAV SANKUL?

ASHTVINAYAK GAURAV SANKUL by DHANASHRI DEVELOPERS is in Malnaka, Ratnagiri (pincode 415612), Maharashtra, and is registered on MahaRERA as PR1280002601995, per GharKundli's check of MahaRERA records.

How many homes are in ASHTVINAYAK GAURAV SANKUL?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHTVINAYAK GAURAV SANKUL has 46 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.

When was ASHTVINAYAK GAURAV SANKUL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHTVINAYAK GAURAV SANKUL was registered on MahaRERA on 22 September 2026. GharKundli did not find a title report on the land on file there.

Are there court cases on ASHTVINAYAK GAURAV SANKUL?

No court cases are listed for ASHTVINAYAK GAURAV SANKUL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of ASHTVINAYAK GAURAV SANKUL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DHANASHRI DEVELOPERS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2029 in Ratnagiri →

Other projects in Ratnagiri

All 63 projects in Ratnagiri (415612) →

Other projects by DHANASHRI DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.