LAXMI KEHSAV NAGAR PHASE II
by DEEPAK YASHWANT SALVI · Ganesh Nagar, Ratnagiri
Possession date of LAXMI KEHSAV NAGAR PHASE II: 31 March 2027, moved from 30 December 2024 (27 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52800017021, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about LAXMI KEHSAV NAGAR PHASE II?
How the possession date of LAXMI KEHSAV NAGAR PHASE II has moved
30 December 2024
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA05092622467)
Reason the builder gave MahaRERA:
“The promoter has filed present extension application only to regularize and facilitate completion of the pending procedural requirements and does not raise on account of any delay in the actual completion of the project. Since the FULL OC H…” Read the full reason
“The promoter has filed present extension application only to regularize and facilitate completion of the pending procedural requirements and does not raise on account of any delay in the actual completion of the project. Since the FULL OC HAS ALREADY BEEN OBTAINED ON 09/08/2024. We look forward to your favorable consideration of our request.”
Source: LAXMI KEHSAV NAGAR PHASE II’s extension records on MahaRERA (P52800017021), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on LAXMI KEHSAV NAGAR PHASE II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800017021
- Status
- Registered and active
- Builder
- DEEPAK YASHWANT SALVI
- Location
- Ganesh Nagar, Ratnagiri · 415612
- Project type
- Residential / Group Housing
- Registered on
- 4 Jul 2018
- Completion date at registration
- December 2024
- Latest completion date
- March 2027
- Delay so far
- 27 months
- Homes
- 143
- Sold or booked
- 86%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of LAXMI KEHSAV NAGAR PHASE II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A BUILDING | 100% | 100% | 100% | 100% |
| D BUILDING | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- A BUILDING: covers 8 floors
- D BUILDING: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on LAXMI KEHSAV NAGAR PHASE II every month.
LAXMI KEHSAV NAGAR PHASE II: buildings, flats and land, as filed on MahaRERA
- Buildings: A BUILDING (9 floors, 97 units) · D BUILDING (9 floors, 46 units)
- Car parking: 19 covered, 27 open
- Land: 4,665 sq m (about 1.2 acres) · sanctioned built-up 8,252 sq m
- Boundaries filed include: RAILWAY TRACK
The builder’s record and reviews
Deepak Yashwant Salvi has 7 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 3 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA.
Read Google reviews of LAXMI KEHSAV NAGAR PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
LAXMI KEHSAV NAGAR PHASE II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about LAXMI KEHSAV NAGAR PHASE II
What is the possession date of LAXMI KEHSAV NAGAR PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for LAXMI KEHSAV NAGAR PHASE II in Ganesh Nagar, Ratnagiri is 31 March 2027 — 27 months later than 30 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for LAXMI KEHSAV NAGAR PHASE II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date LAXMI KEHSAV NAGAR PHASE II's builder has filed on MahaRERA, the official one, is 31 March 2027, already 27 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of LAXMI KEHSAV NAGAR PHASE II extended?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI KEHSAV NAGAR PHASE II's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The promoter has filed present extension application only to regularize and facilitate completion of the pending procedural requirements and does not raise on account of any delay in the actual completion of the project. Since the FULL OC HAS ALREADY BEEN OBTAINED ON 09/08/2024. We look forward to your favorable consideration of our request.".
What is the RERA number of LAXMI KEHSAV NAGAR PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of LAXMI KEHSAV NAGAR PHASE II in Ganesh Nagar, Ratnagiri is P52800017021.
Is LAXMI KEHSAV NAGAR PHASE II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI KEHSAV NAGAR PHASE II is registered as P52800017021 and its status is "Registered and active".
What is the construction status of LAXMI KEHSAV NAGAR PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI KEHSAV NAGAR PHASE II's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does LAXMI KEHSAV NAGAR PHASE II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is LAXMI KEHSAV NAGAR PHASE II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI KEHSAV NAGAR PHASE II is registered on MahaRERA as P52800017021, its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if LAXMI KEHSAV NAGAR PHASE II's possession date changes?
The latest dates are on LAXMI KEHSAV NAGAR PHASE II's MahaRERA page (P52800017021). GharKundli's Kundli Watch sends a free WhatsApp update on LAXMI KEHSAV NAGAR PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does LAXMI KEHSAV NAGAR PHASE II have?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI KEHSAV NAGAR PHASE II has 2 buildings filed: A BUILDING with 9 floors and 97 units; D BUILDING with 9 floors and 46 units.
How much parking does LAXMI KEHSAV NAGAR PHASE II have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 19 covered and 27 open car parking spaces for LAXMI KEHSAV NAGAR PHASE II.
How big is the land of LAXMI KEHSAV NAGAR PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI KEHSAV NAGAR PHASE II stands on 4,665 sq m of land (about 1.2 acres), with 8,252 sq m of sanctioned built-up area.
What is the track record of LAXMI KEHSAV NAGAR PHASE II's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Deepak Yashwant Salvi has 7 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 3 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of LAXMI KEHSAV NAGAR PHASE II?
Google Maps has reviews of LAXMI KEHSAV NAGAR PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is LAXMI KEHSAV NAGAR PHASE II?
LAXMI KEHSAV NAGAR PHASE II by DEEPAK YASHWANT SALVI is in Ganesh Nagar, Ratnagiri (pincode 415612), Maharashtra, and is registered on MahaRERA as P52800017021, per GharKundli's check of MahaRERA records. Its boundaries filed there include RAILWAY TRACK.
How many homes are in LAXMI KEHSAV NAGAR PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI KEHSAV NAGAR PHASE II has 143 homes in 2 towers registered on MahaRERA, and 86% of them are sold or booked.
When was LAXMI KEHSAV NAGAR PHASE II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LAXMI KEHSAV NAGAR PHASE II was registered on MahaRERA on 4 July 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on LAXMI KEHSAV NAGAR PHASE II?
No court cases are listed for LAXMI KEHSAV NAGAR PHASE II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of LAXMI KEHSAV NAGAR PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DEEPAK YASHWANT SALVI, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of LAXMI KEHSAV NAGAR PHASE II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Ratnagiri →
Other projects in Ganesh Nagar
- OM ASHISH CHS
- AUDUMBAR PARK
- VINAYAK SQUARE
- SAHAJANAND CO. OP. HSG.SOC. LTD.
- SHREE PURNANAND APARTMENT
- SAI SHARADA CHS LTD
- BAJIRAO PARK
- RAVIRAJ APARTMENT
Other projects by DEEPAK YASHWANT SALVI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.