BAJIRAO PARK
by VAISHNAVI DEVELOPERS · Ganesh Nagar, Pune
Possession date of BAJIRAO PARK: 30 September 2023, moved from 30 March 2023 (6 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100023669. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (September 2023) has passed.
What do you want to know about BAJIRAO PARK?
How the possession date of BAJIRAO PARK has moved
30 March 2023
Completion date given when the project was registered
30 September 2023
Extended at the builder's request (MahaRERA application EXT52100015108)
Reason the builder gave MahaRERA: “PANDEMIC DELAY,”
Source: BAJIRAO PARK’s extension records on MahaRERA (P52100023669), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BAJIRAO PARK
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100023669
- Status
- Lapsed (registration period ended)
- Builder
- VAISHNAVI DEVELOPERS
- Location
- Ganesh Nagar, Pune · 412101
- Project type
- Residential / Group Housing
- Registered on
- 2 Jan 2020
- Completion date at registration
- March 2023
- Latest completion date
- September 2023
- Delay so far
- 6 months
- Homes
- 74
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 9
Construction progress of BAJIRAO PARK, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BAJIRAO PARK | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BAJIRAO PARK every month.
BAJIRAO PARK: buildings, flats and land, as filed on MahaRERA
- Buildings: BAJIRAO PARK (12 floors)
- Land: 2,489 sq m (about 0.6 acres) · sanctioned built-up 3,454 sq m · recreational space 249 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of BAJIRAO PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BAJIRAO PARK: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BAJIRAO PARK
What is the possession date of BAJIRAO PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BAJIRAO PARK in Ganesh Nagar, Pune is 30 September 2023 — 6 months later than 30 March 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for BAJIRAO PARK?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BAJIRAO PARK's builder has filed on MahaRERA, the official one, is 30 September 2023, already 6 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of BAJIRAO PARK extended?
According to GharKundli's check of MahaRERA records (updated November 2026), BAJIRAO PARK's builder applied to MahaRERA to extend the completion date once: to 30 September 2023, giving the reason "PANDEMIC DELAY,".
What is the RERA number of BAJIRAO PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BAJIRAO PARK in Ganesh Nagar, Pune is P52100023669.
Is BAJIRAO PARK registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), BAJIRAO PARK is registered as P52100023669 and its status is "Lapsed (registration period ended)".
What is the construction status of BAJIRAO PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), BAJIRAO PARK's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on BAJIRAO PARK is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does BAJIRAO PARK have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is BAJIRAO PARK safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), BAJIRAO PARK is registered on MahaRERA as P52100023669, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if BAJIRAO PARK's possession date changes?
The latest dates are on BAJIRAO PARK's MahaRERA page (P52100023669). GharKundli's Kundli Watch sends a free WhatsApp update on BAJIRAO PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BAJIRAO PARK have?
According to GharKundli's check of MahaRERA records (updated November 2026), BAJIRAO PARK has one building filed: BAJIRAO PARK with 12 floors.
How big is the land of BAJIRAO PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), BAJIRAO PARK stands on 2,489 sq m of land (about 0.6 acres), with 3,454 sq m of sanctioned built-up area and 249 sq m of recreational open space.
Where can I read reviews of BAJIRAO PARK?
Google Maps has reviews of BAJIRAO PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is BAJIRAO PARK?
BAJIRAO PARK by VAISHNAVI DEVELOPERS is in Ganesh Nagar, Pune (pincode 412101), Maharashtra, and is registered on MahaRERA as P52100023669, per GharKundli's check of MahaRERA records.
How many homes are in BAJIRAO PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), BAJIRAO PARK has 74 homes in 1 tower registered on MahaRERA.
When was BAJIRAO PARK registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), BAJIRAO PARK was registered on MahaRERA on 2 January 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on BAJIRAO PARK?
No court cases are listed for BAJIRAO PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of BAJIRAO PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VAISHNAVI DEVELOPERS, which has 9 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of BAJIRAO PARK
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ganesh Nagar
- LAXMI KEHSAV NAGAR PHASE II
- OM ASHISH CHS
- AUDUMBAR PARK
- VINAYAK SQUARE
- SAHAJANAND CO. OP. HSG.SOC. LTD.
- SHREE PURNANAND APARTMENT
- SAI SHARADA CHS LTD
- RAVIRAJ APARTMENT
Other projects by VAISHNAVI DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.