Searock Residency

by Bedrock Enterprises · Anand Nagar, Ratnagiri

Possession date of Searock Residency: 31 December 2027, moved from 31 December 2025 (20 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800077638, and currently active. Its completion date has moved from December 2025 to December 2027: 20 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Searock Residency?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Searock Residency has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 August 2027

    Extended at the builder's request (MahaRERA application EA19082622236)

    Reason the builder gave MahaRERA:
    “1) We would like to inform to this authority that, we have updated all the project details time to time. There is delay caused for almost 6 months in the construction due to some paperwork related to the project such as revised commencement…” Read the full reason“1) We would like to inform to this authority that, we have updated all the project details time to time. There is delay caused for almost 6 months in the construction due to some paperwork related to the project such as revised commencement certificate and revised sanction plan. 2) Also, we would like to inform this authority that there is a delay in the construction of the building due to lack of labour, availability of construction materials and rainy season”
  3. 31 December 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Searock Residency’s extension records on MahaRERA (P52800077638), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Searock Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800077638
Status
Registered and active
Builder
Bedrock Enterprises
Location
Anand Nagar, Ratnagiri · 415612
Project type
Residential / Group Housing
Registered on
17 Oct 2024
Completion date at registration
December 2025
Latest completion date
December 2027
Delay so far
20 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
18
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Searock Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Searock Residency100%100%50%30%

Commencement certificate (CC), as filed on MahaRERA

  • Searock Residency: covers Gr Parking+Stilt Parking+5

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Searock Residency every month.

Searock Residency: buildings, flats and land, as filed on MahaRERA

  • Buildings: Searock Residency (5 floors, 19 units)
  • Car parking: 7 covered
  • Land: 517 sq m (about 0.1 acres) · sanctioned built-up 1,047 sq m
  • Boundaries filed include: Anand Nagar Road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Searock Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Searock Residency: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Searock Residency

What is the possession date of Searock Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Searock Residency in Anand Nagar, Ratnagiri is 31 December 2027 — 20 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Searock Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Searock Residency's builder has filed on MahaRERA, the official one, is 31 December 2027, already 20 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Searock Residency extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residency's builder applied to MahaRERA to extend the completion date once: to 31 August 2027, giving the reason "1) We would like to inform to this authority that, we have updated all the project details time to time. There is delay caused for almost 6 months in the construction due to some paperwork related to the project such as revised commencement certificate and revised sanction plan. 2) Also, we would like to inform this authority that there is a delay in the construction of the building due to lack of labour, availability of construction materials and rainy season". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Searock Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Searock Residency in Anand Nagar, Ratnagiri is P52800077638.

Is Searock Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residency is registered as P52800077638 and its status is "Registered and active".

What is the construction status of Searock Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Searock Residency is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does Searock Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Searock Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residency is registered on MahaRERA as P52800077638, its completion date has moved 20 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Searock Residency's possession date changes?

The latest dates are on Searock Residency's MahaRERA page (P52800077638). GharKundli's Kundli Watch sends a free WhatsApp update on Searock Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Searock Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residency has one building filed: Searock Residency with 5 floors and 19 units.

How much parking does Searock Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 7 covered car parking spaces for Searock Residency.

How big is the land of Searock Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residency stands on 517 sq m of land (about 0.1 acres), with 1,047 sq m of sanctioned built-up area.

Where can I read reviews of Searock Residency?

Google Maps has reviews of Searock Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Searock Residency?

Searock Residency by Bedrock Enterprises is in Anand Nagar, Ratnagiri (pincode 415612), Maharashtra, and is registered on MahaRERA as P52800077638, per GharKundli's check of MahaRERA records. Its boundaries filed there include Anand Nagar Road.

How many homes are in Searock Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residency has 18 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Searock Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residency was registered on MahaRERA on 17 October 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on Searock Residency?

No court cases are listed for Searock Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Searock Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Bedrock Enterprises.

All projects with possession due in 2027 in Ratnagiri →

Other projects in Ratnagiri

All 63 projects in Ratnagiri (415612) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.