SAMARTH SAI PRASAD APARTMENT-4

by SAI PRASAD BUILDERS & DEVELOPERS · Near Apana Bazar Shringartali, Ratnagiri

Possession date of SAMARTH SAI PRASAD APARTMENT-4: 31 July 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800053584, and currently active. Its completion date is now July 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SAMARTH SAI PRASAD APARTMENT-4?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAMARTH SAI PRASAD APARTMENT-4 has moved

  1. 31 March 2028

    Completion date given when the project was registered

  2. 31 July 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SAMARTH SAI PRASAD APARTMENT-4’s extension records on MahaRERA (P52800053584), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAMARTH SAI PRASAD APARTMENT-4

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52800053584
Status
Registered and active
Builder
SAI PRASAD BUILDERS & DEVELOPERS
Location
Near Apana Bazar Shringartali, Ratnagiri · 415724
Project type
Others
Registered on
10 Nov 2023
Completion date at registration
March 2028
Latest completion date
July 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
27
Sold or booked
71%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SAMARTH SAI PRASAD APARTMENT-4, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAMARTH SAI PRASAD APARTMENT-4100%100%100%90%

Commencement certificate (CC), as filed on MahaRERA

  • SAMARTH SAI PRASAD APARTMENT-4: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAMARTH SAI PRASAD APARTMENT-4 every month.

SAMARTH SAI PRASAD APARTMENT-4: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAMARTH SAI PRASAD APARTMENT-4 (6 floors, 49 units)
  • Car parking: 11 covered
  • Land: 1,475 sq m (about 0.4 acres) · sanctioned built-up 1,912 sq m

The builder’s record and reviews

SAI Prasad Builders & Developers has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of SAMARTH SAI PRASAD APARTMENT-4 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAMARTH SAI PRASAD APARTMENT-4: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAMARTH SAI PRASAD APARTMENT-4

What is the possession date of SAMARTH SAI PRASAD APARTMENT-4?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAMARTH SAI PRASAD APARTMENT-4 in Near Apana Bazar Shringartali, Ratnagiri is 31 July 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SAMARTH SAI PRASAD APARTMENT-4?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAMARTH SAI PRASAD APARTMENT-4's builder has filed on MahaRERA, the official one, is 31 July 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SAMARTH SAI PRASAD APARTMENT-4?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAMARTH SAI PRASAD APARTMENT-4 in Near Apana Bazar Shringartali, Ratnagiri is P52800053584.

Is SAMARTH SAI PRASAD APARTMENT-4 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH SAI PRASAD APARTMENT-4 is registered as P52800053584 and its status is "Registered and active".

What is the construction status of SAMARTH SAI PRASAD APARTMENT-4?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH SAI PRASAD APARTMENT-4's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAMARTH SAI PRASAD APARTMENT-4 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SAMARTH SAI PRASAD APARTMENT-4 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SAMARTH SAI PRASAD APARTMENT-4 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH SAI PRASAD APARTMENT-4 is registered on MahaRERA as P52800053584, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does SAMARTH SAI PRASAD APARTMENT-4 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SAMARTH SAI PRASAD APARTMENT-4 BUILDING NO 2 (PR1280002502742, possession 30 Mar 2031). Check that your agreement names the registration of your own wing.

How can I get updates if SAMARTH SAI PRASAD APARTMENT-4's possession date changes?

The latest dates are on SAMARTH SAI PRASAD APARTMENT-4's MahaRERA page (P52800053584). GharKundli's Kundli Watch sends a free WhatsApp update on SAMARTH SAI PRASAD APARTMENT-4 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAMARTH SAI PRASAD APARTMENT-4 have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH SAI PRASAD APARTMENT-4 has one building filed: SAMARTH SAI PRASAD APARTMENT-4 with 6 floors and 49 units.

How much parking does SAMARTH SAI PRASAD APARTMENT-4 have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 11 covered car parking spaces for SAMARTH SAI PRASAD APARTMENT-4.

How big is the land of SAMARTH SAI PRASAD APARTMENT-4?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH SAI PRASAD APARTMENT-4 stands on 1,475 sq m of land (about 0.4 acres), with 1,912 sq m of sanctioned built-up area.

What is the track record of SAMARTH SAI PRASAD APARTMENT-4's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI Prasad Builders & Developers has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAMARTH SAI PRASAD APARTMENT-4?

Google Maps has reviews of SAMARTH SAI PRASAD APARTMENT-4 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAMARTH SAI PRASAD APARTMENT-4?

SAMARTH SAI PRASAD APARTMENT-4 by SAI PRASAD BUILDERS & DEVELOPERS is in Near Apana Bazar Shringartali, Ratnagiri (pincode 415724), Maharashtra, and is registered on MahaRERA as P52800053584, per GharKundli's check of MahaRERA records.

How many homes are in SAMARTH SAI PRASAD APARTMENT-4?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH SAI PRASAD APARTMENT-4 has 27 homes in 1 tower registered on MahaRERA, and 71% of them are sold or booked.

When was SAMARTH SAI PRASAD APARTMENT-4 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH SAI PRASAD APARTMENT-4 was registered on MahaRERA on 10 November 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on SAMARTH SAI PRASAD APARTMENT-4?

No court cases are listed for SAMARTH SAI PRASAD APARTMENT-4 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAMARTH SAI PRASAD APARTMENT-4?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAI PRASAD BUILDERS & DEVELOPERS, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2028 in Ratnagiri →

Other projects in pincode 415724

All 10 projects in Shringartali (415724) →

Other projects by SAI PRASAD BUILDERS & DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.