Nirmaan Bhavan
by NIRMAN BUILDERS AND DEVELOPERS · Old Shiroda Naka, Sindhudurg 416510Also near Sawantwadi, Salaiwada, Sabniswada
What’s in the report? →Possession date of Nirmaan Bhavan (MahaRERA P52900007056): 31 October 2019, moved from 31 October 2018 (12 months later), and it has already passed. It has 33 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52900007056. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52900007056, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2019) has passed.
What do you want to know about Nirmaan Bhavan?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Nirmaan Bhavan has moved
31 October 2018
Completion date given when the project was registered
31 October 2019
Extended at the builder's request (MahaRERA application EXT52900000716)
Reason the builder gave MahaRERA:
“THERE BEING MAJOR FAMILY HEALTH ISSUES WITH ONE OF THE PARTNER cum CONSULTANT AND THEN SUDDEN DEATH OF HIS WIFE DURING THE PROJECT PERIOD. ALSO DUE TO RECESSION IN CONSTRUCTION INDUSTRY RESPONSE FROM THE CUSTOMER WAS MUCH LESS THAN EXPECTED…” Read the full reason
“THERE BEING MAJOR FAMILY HEALTH ISSUES WITH ONE OF THE PARTNER cum CONSULTANT AND THEN SUDDEN DEATH OF HIS WIFE DURING THE PROJECT PERIOD. ALSO DUE TO RECESSION IN CONSTRUCTION INDUSTRY RESPONSE FROM THE CUSTOMER WAS MUCH LESS THAN EXPECTED WHICH IMPACTED ON OUR FUNDS.CONSIDERING ALL ABOVE ISSUES PLEASE ALLOW US THE EXPECTED EXTENSION.”
Source: Nirmaan Bhavan’s extension records on MahaRERA (P52900007056), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Nirmaan Bhavan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52900007056
- Status
- Lapsed (registration period ended)
- Builder
- NIRMAN BUILDERS AND DEVELOPERS
- Location
- Old Shiroda Naka, Sindhudurg · 416510
- Project type
- Others
- Registered on
- 17 Aug 2017
- Completion date at registration
- October 2018
- Latest completion date
- October 2019
- Delay so far
- 12 months
- Homes
- 33
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Nirmaan Bhavan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NIRMAAN BHAVAN | 100% | 100% | 35% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nirmaan Bhavan every 1–2 months.
Nirmaan Bhavan: buildings, flats and land, as filed on MahaRERA
- Buildings: NIRMAAN BHAVAN (6 floors)
- Land: 1,300 sq m (about 0.3 acres) · sanctioned built-up 1,303 sq m
- Boundaries filed include: MILAGRIS HIGH SCHOOL
- Land, as filed: CTS NO. 4878 4879 4880 4881, SURVEY NO. 50B/3
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Nirmaan Bhavan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Nirmaan Bhavan: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Nirmaan Bhavan
What is the possession date of Nirmaan Bhavan?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Nirmaan Bhavan in Old Shiroda Naka, Sindhudurg is 31 October 2019 — 12 months later than 31 October 2018, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Nirmaan Bhavan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Nirmaan Bhavan's builder has filed on MahaRERA, the official one, is 31 October 2019, already 12 months later than the 31 October 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Nirmaan Bhavan extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmaan Bhavan's builder applied to MahaRERA to extend the completion date once: to 31 October 2019, giving the reason "THERE BEING MAJOR FAMILY HEALTH ISSUES WITH ONE OF THE PARTNER cum CONSULTANT AND THEN SUDDEN DEATH OF HIS WIFE DURING THE PROJECT PERIOD. ALSO DUE TO RECESSION IN CONSTRUCTION INDUSTRY RESPONSE FROM THE CUSTOMER WAS MUCH LESS THAN EXPECTED WHICH IMPACTED ON OUR FUNDS.CONSIDERING ALL ABOVE ISSUES PLEASE ALLOW US THE EXPECTED EXTENSION.".
What is the RERA number of Nirmaan Bhavan?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Nirmaan Bhavan in Old Shiroda Naka, Sindhudurg is P52900007056.
Is Nirmaan Bhavan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmaan Bhavan is registered as P52900007056 and its status is "Lapsed (registration period ended)".
What is the current construction status of Nirmaan Bhavan? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmaan Bhavan's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NIRMAAN BHAVAN is 100% done and internal work 35%. GharKundli's full report compares construction progress with the deadline.
Does Nirmaan Bhavan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Nirmaan Bhavan safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmaan Bhavan is registered on MahaRERA as P52900007056, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Nirmaan Bhavan?
Nirmaan Bhavan isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Nirmaan Bhavan?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Nirmaan Bhavan: gharkundli.com/tools/property-cost-calculator
Has Nirmaan Bhavan received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Nirmaan Bhavan isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 October 2019 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Nirmaan Bhavan?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmaan Bhavan's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 October 2019) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Nirmaan Bhavan uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Nirmaan Bhavan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Nirmaan Bhavan's possession date changes?
The latest dates are on Nirmaan Bhavan's MahaRERA page (P52900007056). GharKundli's Kundli Watch sends a free WhatsApp update on Nirmaan Bhavan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Nirmaan Bhavan have?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmaan Bhavan has one building filed: NIRMAAN BHAVAN with 6 floors.
How big is the land of Nirmaan Bhavan?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmaan Bhavan stands on 1,300 sq m of land (about 0.3 acres), with 1,303 sq m of sanctioned built-up area.
What are the reviews of Nirmaan Bhavan?
Google Maps has reviews of Nirmaan Bhavan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Nirmaan Bhavan?
Nirmaan Bhavan by NIRMAN BUILDERS AND DEVELOPERS is in Old Shiroda Naka, Sindhudurg, pincode 416510 (near Sawantwadi, Salaiwada, Sabniswada), Maharashtra, and is registered on MahaRERA as P52900007056, per GharKundli's check of MahaRERA records. Its boundaries filed there include MILAGRIS HIGH SCHOOL. Its land is filed as CTS NO. 4878 4879 4880 4881, SURVEY NO. 50B/3. GharKundli lists all 100 MahaRERA projects in Sawantwadi (416510).
How many flats are in Nirmaan Bhavan?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmaan Bhavan has 33 homes in 1 tower registered on MahaRERA.
When was Nirmaan Bhavan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmaan Bhavan was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Does Nirmaan Bhavan have any legal issues or court cases?
No court cases are listed for Nirmaan Bhavan on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Nirmaan Bhavan?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NIRMAN BUILDERS AND DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Nirmaan Bhavan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Sawantwadi
- Unnati Heights
- Marlin Plots
- Future Reality Builders and Developers
- Heritage Homes
- Anaadih Shri Datta
- Perto De Goa Phase 4
- Vrukshavalli B-4
- HNS Valley
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.