Skip to content
GharKundli

PRITESH CHAMBERS

by PRALHAD LADU ARONDEKAR · Kumbharli Malgaon, Sindhudurg

Possession: PRITESH CHAMBERS is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52900011467. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about PRITESH CHAMBERS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PRITESH CHAMBERS has moved

  1. 31 March 2019

    Completion date given when the project was registered

  2. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT52900013380)

    Reason the builder gave MahaRERA: “covid-19 pandamic situation work could not be completed.”

Source: PRITESH CHAMBERS’s extension records on MahaRERA (P52900011467), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PRITESH CHAMBERS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52900011467
Status
Completed
Builder
PRALHAD LADU ARONDEKAR
Location
Kumbharli Malgaon, Sindhudurg · 416510
Project type
Others
Registered on
31 Aug 2017
Completion date at registration
March 2019
Latest completion date
December 2024
Delay so far
69 months
Homes
139
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of PRITESH CHAMBERS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PRITESH CHAMBERS100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PRITESH CHAMBERS every month.

PRITESH CHAMBERS: buildings, flats and land, as filed on MahaRERA

  • Buildings: PRITESH CHAMBERS (6 floors)
  • Land: 5,810 sq m (about 1.4 acres) · sanctioned built-up 4,474 sq m
  • Boundaries filed include: SAWANTWADI ROAD RAILWAY STATION

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PRITESH CHAMBERS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PRITESH CHAMBERS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PRITESH CHAMBERS

What is the possession date of PRITESH CHAMBERS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PRITESH CHAMBERS in Kumbharli Malgaon, Sindhudurg is 31 December 2024 — 69 months later than 31 March 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for PRITESH CHAMBERS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PRITESH CHAMBERS's builder has filed on MahaRERA, the official one, is 31 December 2024, already 69 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PRITESH CHAMBERS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), PRITESH CHAMBERS's builder applied to MahaRERA to extend the completion date once: to 31 December 2024, giving the reason "covid-19 pandamic situation work could not be completed.".

What is the RERA number of PRITESH CHAMBERS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PRITESH CHAMBERS in Kumbharli Malgaon, Sindhudurg is P52900011467.

Is PRITESH CHAMBERS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PRITESH CHAMBERS is registered as P52900011467 and its status is "Completed".

What is the construction status of PRITESH CHAMBERS?

According to GharKundli's check of MahaRERA records (updated November 2026), PRITESH CHAMBERS's status on MahaRERA is "Completed". As filed by the builder, slab work on PRITESH CHAMBERS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does PRITESH CHAMBERS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is PRITESH CHAMBERS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), PRITESH CHAMBERS is registered on MahaRERA as P52900011467, its MahaRERA status is "Completed", its completion date has moved 69 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PRITESH CHAMBERS's possession date changes?

The latest dates are on PRITESH CHAMBERS's MahaRERA page (P52900011467). GharKundli's Kundli Watch sends a free WhatsApp update on PRITESH CHAMBERS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PRITESH CHAMBERS have?

According to GharKundli's check of MahaRERA records (updated November 2026), PRITESH CHAMBERS has one building filed: PRITESH CHAMBERS with 6 floors.

How big is the land of PRITESH CHAMBERS?

According to GharKundli's check of MahaRERA records (updated November 2026), PRITESH CHAMBERS stands on 5,810 sq m of land (about 1.4 acres), with 4,474 sq m of sanctioned built-up area.

Where can I read reviews of PRITESH CHAMBERS?

Google Maps has reviews of PRITESH CHAMBERS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PRITESH CHAMBERS?

PRITESH CHAMBERS by PRALHAD LADU ARONDEKAR is in Kumbharli Malgaon, Sindhudurg (pincode 416510), Maharashtra, and is registered on MahaRERA as P52900011467, per GharKundli's check of MahaRERA records. Its boundaries filed there include SAWANTWADI ROAD RAILWAY STATION.

How many homes are in PRITESH CHAMBERS?

According to GharKundli's check of MahaRERA records (updated November 2026), PRITESH CHAMBERS has 139 homes in 1 tower registered on MahaRERA.

When was PRITESH CHAMBERS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PRITESH CHAMBERS was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on PRITESH CHAMBERS?

No court cases are listed for PRITESH CHAMBERS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of PRITESH CHAMBERS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PRALHAD LADU ARONDEKAR.

Other projects in Sawantwadi

All 49 projects in Sawantwadi (416510) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.