GODGRESS A
by GODGRESS · Jamsande, Sindhudurg
Possession: GODGRESS A is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52900017282. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about GODGRESS A?
How the possession date of GODGRESS A has moved
25 December 2019
Completion date given when the project was registered
30 December 2021
Extended at the builder's request (MahaRERA application EXT52900006144)
Reason the builder gave MahaRERA: “Due to heave rain fall in our area and availability of material like natural sand was not possible due to government restriction now we are use crush sand to complete the project”
31 December 2024
Extended at the builder's request (MahaRERA application EXT52900017273)
Reason the builder gave MahaRERA: “The project is delayed due to the various reasons lack of funds, delay in material covid time, Covid 19 . we have faced many difficulties, the project is near to the completion hence we required extension till 31st December 2024.”
Source: GODGRESS A’s extension records on MahaRERA (P52900017282), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GODGRESS A
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52900017282
- Status
- Completed
- Builder
- GODGRESS
- Location
- Jamsande, Sindhudurg · 416612
- Project type
- Residential / Group Housing
- Registered on
- 27 Jul 2018
- Completion date at registration
- December 2019
- Latest completion date
- December 2024
- Delay so far
- 60 months
- Homes
- 17
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of GODGRESS A, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GODGRESS A | 100% | 100% | 70% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GODGRESS A every month.
GODGRESS A: buildings, flats and land, as filed on MahaRERA
- Buildings: GODGRESS A (3 floors)
- Land: 2,500 sq m (about 0.6 acres) · sanctioned built-up 1,513 sq m · recreational space 400 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of GODGRESS A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GODGRESS A: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GODGRESS A
What is the possession date of GODGRESS A?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GODGRESS A in Jamsande, Sindhudurg is 31 December 2024 — 60 months later than 25 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for GODGRESS A?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GODGRESS A's builder has filed on MahaRERA, the official one, is 31 December 2024, already 60 months later than the 25 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GODGRESS A extended?
According to GharKundli's check of MahaRERA records (updated November 2026), GODGRESS A's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2021, giving the reason "Due to heave rain fall in our area and availability of material like natural sand was not possible due to government restriction now we are use crush sand to complete the project"; to 31 December 2024, giving the reason "The project is delayed due to the various reasons lack of funds, delay in material covid time, Covid 19 . we have faced many difficulties, the project is near to the completion hence we required extension till 31st December 2024.".
What is the RERA number of GODGRESS A?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GODGRESS A in Jamsande, Sindhudurg is P52900017282.
Is GODGRESS A registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), GODGRESS A is registered as P52900017282 and its status is "Completed".
What is the construction status of GODGRESS A?
According to GharKundli's check of MahaRERA records (updated November 2026), GODGRESS A's status on MahaRERA is "Completed". As filed by the builder, slab work on GODGRESS A is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does GODGRESS A have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is GODGRESS A safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), GODGRESS A is registered on MahaRERA as P52900017282, its MahaRERA status is "Completed", its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GODGRESS A's possession date changes?
The latest dates are on GODGRESS A's MahaRERA page (P52900017282). GharKundli's Kundli Watch sends a free WhatsApp update on GODGRESS A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GODGRESS A have?
According to GharKundli's check of MahaRERA records (updated November 2026), GODGRESS A has one building filed: GODGRESS A with 3 floors.
How big is the land of GODGRESS A?
According to GharKundli's check of MahaRERA records (updated November 2026), GODGRESS A stands on 2,500 sq m of land (about 0.6 acres), with 1,513 sq m of sanctioned built-up area and 400 sq m of recreational open space.
Where can I read reviews of GODGRESS A?
Google Maps has reviews of GODGRESS A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GODGRESS A?
GODGRESS A by GODGRESS is in Jamsande, Sindhudurg (pincode 416612), Maharashtra, and is registered on MahaRERA as P52900017282, per GharKundli's check of MahaRERA records.
How many homes are in GODGRESS A?
According to GharKundli's check of MahaRERA records (updated November 2026), GODGRESS A has 17 homes in 1 tower registered on MahaRERA.
When was GODGRESS A registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), GODGRESS A was registered on MahaRERA on 27 July 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on GODGRESS A?
No court cases are listed for GODGRESS A on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of GODGRESS A?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GODGRESS.
Check it yourself on MahaRERA
- How to check the possession date of GODGRESS A
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 416612
- MANGALSIDDHI ARCADE
- ATHARVA PARADISE
- SWARUPANAND ARCADE
- MUKUND ARCADE
- SHREE SAI RESIDENCY
- KRUSHNKUNJ APARTMENT
- Omkar Complex Phase 2
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.