Skip to content
GharKundli

OMKAR COMPLEX - PHASE 1

by Shree Omkar developers · Shriram Gogate High School, SindhudurgAlso near Jamsande

Possession: OMKAR COMPLEX - PHASE 1 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52900018151. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about OMKAR COMPLEX - PHASE 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of OMKAR COMPLEX - PHASE 1 has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT52900010199)

    Reason the builder gave MahaRERA: “FILE SUBMITTED IN TOWNPLANNING FOR REVISED APPROVAL AS PER UDCPR”
  3. 30 December 2023

    Revised completion date on MahaRERA

Source: OMKAR COMPLEX - PHASE 1’s extension records on MahaRERA (P52900018151), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on OMKAR COMPLEX - PHASE 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52900018151
Status
Completed
Builder
Shree Omkar developers
Location
Shriram Gogate High School, Sindhudurg · 416612
Project type
Residential / Group Housing
Registered on
11 Oct 2018
Completion date at registration
June 2021
Latest completion date
December 2023
Delay so far
30 months
Homes
36
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of OMKAR COMPLEX - PHASE 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
HERAMB100%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on OMKAR COMPLEX - PHASE 1 every month.

OMKAR COMPLEX - PHASE 1: buildings, flats and land, as filed on MahaRERA

  • Buildings: HERAMB (4 floors)
  • Land: 7,064 sq m (about 1.7 acres) · sanctioned built-up 4,446 sq m · recreational space 635 sq m
  • Boundaries filed include: DEVGAD NIPANI ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of OMKAR COMPLEX - PHASE 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

OMKAR COMPLEX - PHASE 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about OMKAR COMPLEX - PHASE 1

What is the possession date of OMKAR COMPLEX - PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for OMKAR COMPLEX - PHASE 1 in Shriram Gogate High School, Sindhudurg is 30 December 2023 — 30 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for OMKAR COMPLEX - PHASE 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date OMKAR COMPLEX - PHASE 1's builder has filed on MahaRERA, the official one, is 30 December 2023, already 30 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of OMKAR COMPLEX - PHASE 1 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), OMKAR COMPLEX - PHASE 1's builder applied to MahaRERA to extend the completion date once: to 30 June 2023, giving the reason "FILE SUBMITTED IN TOWNPLANNING FOR REVISED APPROVAL AS PER UDCPR".

What is the RERA number of OMKAR COMPLEX - PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of OMKAR COMPLEX - PHASE 1 in Shriram Gogate High School, Sindhudurg is P52900018151.

Is OMKAR COMPLEX - PHASE 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), OMKAR COMPLEX - PHASE 1 is registered as P52900018151 and its status is "Completed".

What is the construction status of OMKAR COMPLEX - PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), OMKAR COMPLEX - PHASE 1's status on MahaRERA is "Completed". As filed by the builder, slab work on HERAMB is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does OMKAR COMPLEX - PHASE 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is OMKAR COMPLEX - PHASE 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), OMKAR COMPLEX - PHASE 1 is registered on MahaRERA as P52900018151, its MahaRERA status is "Completed", its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does OMKAR COMPLEX - PHASE 1 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Omkar Complex Phase 2 (PM1311012601640, possession 31 Mar 2030). Check that your agreement names the registration of your own wing.

How can I get updates if OMKAR COMPLEX - PHASE 1's possession date changes?

The latest dates are on OMKAR COMPLEX - PHASE 1's MahaRERA page (P52900018151). GharKundli's Kundli Watch sends a free WhatsApp update on OMKAR COMPLEX - PHASE 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does OMKAR COMPLEX - PHASE 1 have?

According to GharKundli's check of MahaRERA records (updated November 2026), OMKAR COMPLEX - PHASE 1 has one building filed: HERAMB with 4 floors.

How big is the land of OMKAR COMPLEX - PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), OMKAR COMPLEX - PHASE 1 stands on 7,064 sq m of land (about 1.7 acres), with 4,446 sq m of sanctioned built-up area and 635 sq m of recreational open space.

Where can I read reviews of OMKAR COMPLEX - PHASE 1?

Google Maps has reviews of OMKAR COMPLEX - PHASE 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is OMKAR COMPLEX - PHASE 1?

OMKAR COMPLEX - PHASE 1 by Shree Omkar developers is in Shriram Gogate High School, Sindhudurg (pincode 416612), near Jamsande, Maharashtra, and is registered on MahaRERA as P52900018151, per GharKundli's check of MahaRERA records. Its boundaries filed there include DEVGAD NIPANI ROAD.

How many homes are in OMKAR COMPLEX - PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), OMKAR COMPLEX - PHASE 1 has 36 homes in 1 tower registered on MahaRERA.

When was OMKAR COMPLEX - PHASE 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), OMKAR COMPLEX - PHASE 1 was registered on MahaRERA on 11 October 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on OMKAR COMPLEX - PHASE 1?

No court cases are listed for OMKAR COMPLEX - PHASE 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of OMKAR COMPLEX - PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shree Omkar developers, which has 1 other project registered on MahaRERA.

Other projects in Devgad

All 13 projects in Jamsande (416612) →

Other projects by Shree Omkar developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.