AXIS BLUES

by EEJAK HOLDINGS PRIVATE LIMITED · Yog City, Sindhudurg

Possession date of AXIS BLUES: 30 April 2026, moved from 30 October 2024 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52900024380. Status: Lapsed (registration period ended). 52 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (April 2026) has passed.

What do you want to know about AXIS BLUES?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AXIS BLUES has moved

  1. 30 October 2024

    Completion date given when the project was registered

  2. 30 October 2025

    Extended at the builder's request (MahaRERA application EXT52900019833)

    Reason the builder gave MahaRERA: “COVID started immediately after our project launched and Heavy rain fall in the region hence require an extension u/s 6”
  3. 30 April 2026

    Extended at the builder's request (MahaRERA application EXT52900027776)

    Reason the builder gave MahaRERA:
    “The delay in the project is primarily due to the COVID-I9 pandemic, which affected development activities for two continuous years after its commencement in 2019. Additionally, the rising prices of steel and overall costs further impacted p…” Read the full reason“The delay in the project is primarily due to the COVID-I9 pandemic, which affected development activities for two continuous years after its commencement in 2019. Additionally, the rising prices of steel and overall costs further impacted progress. Since Sindhudurg is a coastal region, it experiences continuous rainfall for nearly six months each year, further slowing down construction activities. These factors collectively contributed to the project's prolonged timeline, making it challenging to maintain the expected pace. Despite these setbacks, efforts are being made to overcome these ob…”

Source: AXIS BLUES’s extension records on MahaRERA (P52900024380), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AXIS BLUES

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 52 complaints, and how it ended
  • Construction pace against the April 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52900024380
Status
Lapsed (registration period ended)
Builder
EEJAK HOLDINGS PRIVATE LIMITED
Location
Yog City, Sindhudurg · 416512
Project type
Commercial
Registered on
10 Feb 2020
Completion date at registration
October 2024
Latest completion date
April 2026
Delay so far
18 months
Homes
165
Sold or booked
78%
Towers
4
Complaints on MahaRERA
52
Court cases listed
0
Appeals at the tribunal
2
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of AXIS BLUES, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING C100%100%95%10%
BUILDING NO F100%100%85%10%
BUILDING NO I100%100%45%10%
BUILDING NO J100%90%15%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AXIS BLUES every month.

AXIS BLUES: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING C (5 floors, 40 units) · BUILDING NO F (4 floors, 44 units) · BUILDING NO I (4 floors, 44 units) · BUILDING NO J (4 floors, 44 units)
  • Car parking: 1 covered, 12 open
  • Land: 3,995 sq m (about 1.0 acres) · sanctioned built-up 5,009 sq m

The builder’s record and reviews

Eejak Holdings (a group of 2 linked companies) has 4 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 11 months late); 1 lapsed. 54 complaints on MahaRERA across 2 projects.

Read Google reviews of AXIS BLUES →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AXIS BLUES: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AXIS BLUES

What is the possession date of AXIS BLUES?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AXIS BLUES in Yog City, Sindhudurg is 30 April 2026 — 18 months later than 30 October 2024, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for AXIS BLUES?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AXIS BLUES's builder has filed on MahaRERA, the official one, is 30 April 2026, already 18 months later than the 30 October 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AXIS BLUES extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AXIS BLUES's builder applied to MahaRERA to extend the completion date 2 times: to 30 October 2025, giving the reason "COVID started immediately after our project launched and Heavy rain fall in the region hence require an extension u/s 6"; to 30 April 2026, giving the reason "The delay in the project is primarily due to the COVID-I9 pandemic, which affected development activities for two continuous years after its commencement in 2019. Additionally, the rising prices of steel and overall costs further impacted progress. Since Sindhudurg is a coastal region, it experiences continuous rainfall for nearly six months each year, further slowing down construction activities. These factors collectively contributed to the project's prolonged timeline, making it challenging to maintain the expected pace. Despite these setbacks, efforts are being made to overcome these ob…".

What is the RERA number of AXIS BLUES?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AXIS BLUES in Yog City, Sindhudurg is P52900024380.

Is AXIS BLUES registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AXIS BLUES is registered as P52900024380 and its status is "Lapsed (registration period ended)".

What is the construction status of AXIS BLUES?

According to GharKundli's check of MahaRERA records (updated October 2026), AXIS BLUES's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 90% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does AXIS BLUES have complaints on MahaRERA?

52 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AXIS BLUES safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AXIS BLUES is registered on MahaRERA as P52900024380, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and 52 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AXIS BLUES's possession date changes?

The latest dates are on AXIS BLUES's MahaRERA page (P52900024380). GharKundli's Kundli Watch sends a free WhatsApp update on AXIS BLUES every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AXIS BLUES have?

According to GharKundli's check of MahaRERA records (updated October 2026), AXIS BLUES has 4 buildings filed: BUILDING C with 5 floors and 40 units; BUILDING NO F with 4 floors and 44 units; BUILDING NO I with 4 floors and 44 units; BUILDING NO J with 4 floors and 44 units.

How much parking does AXIS BLUES have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 12 open car parking spaces for AXIS BLUES.

How big is the land of AXIS BLUES?

According to GharKundli's check of MahaRERA records (updated October 2026), AXIS BLUES stands on 3,995 sq m of land (about 1.0 acres), with 5,009 sq m of sanctioned built-up area.

What is the track record of AXIS BLUES's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Eejak Holdings (a group of 2 linked companies) has 4 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 11 months late); 1 lapsed. 54 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of AXIS BLUES?

Google Maps has reviews of AXIS BLUES written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 52 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AXIS BLUES?

AXIS BLUES by EEJAK HOLDINGS PRIVATE LIMITED is in Yog City, Sindhudurg (pincode 416512), Maharashtra, and is registered on MahaRERA as P52900024380, per GharKundli's check of MahaRERA records.

How many homes are in AXIS BLUES?

According to GharKundli's check of MahaRERA records (updated October 2026), AXIS BLUES has 165 homes in 4 towers registered on MahaRERA, and 78% of them are sold or booked.

When was AXIS BLUES registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AXIS BLUES was registered on MahaRERA on 10 February 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on AXIS BLUES?

No court cases are listed for AXIS BLUES on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of AXIS BLUES?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is EEJAK HOLDINGS PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Sindhudurg →

Other projects in Dodamarg

All 19 projects in Dodamarg (416512) →

Other projects by EEJAK HOLDINGS PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.