AXIS YOG VILLAS
by ARUSH INFRA PROMOTERS PRIVATE LIMITED · Yog City, Sindhudurg
Possession date of AXIS YOG VILLAS: 30 September 2027, moved from 31 July 2024 (34 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52900021552, and currently active. Its completion date has moved from July 2024 to September 2027: 34 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about AXIS YOG VILLAS?
How the possession date of AXIS YOG VILLAS has moved
31 July 2024
Completion date given when the project was registered
31 May 2027
Extended at the builder's request (MahaRERA application EXT52900027375)
Reason the builder gave MahaRERA:
“As you are aware, the COVID-19 pandemic began shortly after our project's launch in 2019 and persisted for nearly two years, significantly impacting our construction schedule. Additionally, our project is located in the Konkan region, which…” Read the full reason
“As you are aware, the COVID-19 pandemic began shortly after our project's launch in 2019 and persisted for nearly two years, significantly impacting our construction schedule. Additionally, our project is located in the Konkan region, which is known for heavy rainfall. The years 2022 and 2023 experienced exceptionally heavy rains, further hampering our construction activities.”30 September 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: AXIS YOG VILLAS’s extension records on MahaRERA (P52900021552), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AXIS YOG VILLAS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52900021552
- Status
- Registered and active
- Builder
- ARUSH INFRA PROMOTERS PRIVATE LIMITED
- Location
- Yog City, Sindhudurg · 416512
- Project type
- Residential / Group Housing
- Registered on
- 8 Jul 2019
- Completion date at registration
- July 2024
- Latest completion date
- September 2027
- Delay so far
- 34 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 18
- Towers
- 6
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of AXIS YOG VILLAS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 1 | 0% | 0% | 0% | 0% |
| 2 | 0% | 0% | 0% | 0% |
| 3 | 0% | 0% | 0% | 0% |
| 4 | 0% | 0% | 0% | 0% |
| 5 | 0% | 0% | 0% | 0% |
| 6 | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AXIS YOG VILLAS every month.
AXIS YOG VILLAS: buildings, flats and land, as filed on MahaRERA
- Buildings: 1 (2 floors) · 2 (2 floors) · 3 (2 floors) · 4 (2 floors) · 5 (2 floors) · 6 (2 floors)
- Land: 2,989 sq m (about 0.7 acres) · sanctioned built-up 1,539 sq m
The builder’s record and reviews
Eejak Holdings (a group of 2 linked companies) has 4 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 11 months late); 1 lapsed. 54 complaints on MahaRERA across 2 projects.
Read Google reviews of AXIS YOG VILLAS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AXIS YOG VILLAS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AXIS YOG VILLAS
What is the possession date of AXIS YOG VILLAS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AXIS YOG VILLAS in Yog City, Sindhudurg is 30 September 2027 — 34 months later than 31 July 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for AXIS YOG VILLAS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AXIS YOG VILLAS's builder has filed on MahaRERA, the official one, is 30 September 2027, already 34 months later than the 31 July 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AXIS YOG VILLAS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), AXIS YOG VILLAS's builder applied to MahaRERA to extend the completion date once: to 31 May 2027, giving the reason "As you are aware, the COVID-19 pandemic began shortly after our project's launch in 2019 and persisted for nearly two years, significantly impacting our construction schedule. Additionally, our project is located in the Konkan region, which is known for heavy rainfall. The years 2022 and 2023 experienced exceptionally heavy rains, further hampering our construction activities.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of AXIS YOG VILLAS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AXIS YOG VILLAS in Yog City, Sindhudurg is P52900021552.
Is AXIS YOG VILLAS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AXIS YOG VILLAS is registered as P52900021552 and its status is "Registered and active".
What is the construction status of AXIS YOG VILLAS?
According to GharKundli's check of MahaRERA records (updated October 2026), AXIS YOG VILLAS's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 6 towers. GharKundli's full report compares construction progress with the deadline.
Does AXIS YOG VILLAS have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is AXIS YOG VILLAS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), AXIS YOG VILLAS is registered on MahaRERA as P52900021552, its completion date has moved 34 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AXIS YOG VILLAS's possession date changes?
The latest dates are on AXIS YOG VILLAS's MahaRERA page (P52900021552). GharKundli's Kundli Watch sends a free WhatsApp update on AXIS YOG VILLAS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AXIS YOG VILLAS have?
According to GharKundli's check of MahaRERA records (updated October 2026), AXIS YOG VILLAS has 6 buildings filed: 1 with 2 floors; 2 with 2 floors; 3 with 2 floors; 4 with 2 floors; 5 with 2 floors; 6 with 2 floors.
How big is the land of AXIS YOG VILLAS?
According to GharKundli's check of MahaRERA records (updated October 2026), AXIS YOG VILLAS stands on 2,989 sq m of land (about 0.7 acres), with 1,539 sq m of sanctioned built-up area.
What is the track record of AXIS YOG VILLAS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Eejak Holdings (a group of 2 linked companies) has 4 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 11 months late); 1 lapsed. 54 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of AXIS YOG VILLAS?
Google Maps has reviews of AXIS YOG VILLAS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AXIS YOG VILLAS?
AXIS YOG VILLAS by ARUSH INFRA PROMOTERS PRIVATE LIMITED is in Yog City, Sindhudurg (pincode 416512), Maharashtra, and is registered on MahaRERA as P52900021552, per GharKundli's check of MahaRERA records.
How many homes are in AXIS YOG VILLAS?
According to GharKundli's check of MahaRERA records (updated October 2026), AXIS YOG VILLAS has 18 homes in 6 towers registered on MahaRERA.
When was AXIS YOG VILLAS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AXIS YOG VILLAS was registered on MahaRERA on 8 July 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on AXIS YOG VILLAS?
No court cases are listed for AXIS YOG VILLAS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AXIS YOG VILLAS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARUSH INFRA PROMOTERS PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of AXIS YOG VILLAS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Sindhudurg →
Other projects in Dodamarg
All 19 projects in Dodamarg (416512) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.