RAGHUVEER
by VAZE BUILDER PROP. MUKAAYSH VAZE · sahyadri nagar, SangliAlso near Vishrambag, Kupwad, Government Colony
Possession: RAGHUVEER is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P53100012164. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about RAGHUVEER?
How the possession date of RAGHUVEER has moved
31 July 2019
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT53100017772)
Reason the builder gave MahaRERA:
“I, Mr. Mukaaysh vaze (Prop. Vaze builder) 155, Sai pushp Apartment, opp.kanti shah hospital,Vakharbhag,Sangli 416416 hereby declare that I have purchased the semi constructed project and the land situated at CTS.No.6669B,Mangalwar bazaar ch…” Read the full reason
“I, Mr. Mukaaysh vaze (Prop. Vaze builder) 155, Sai pushp Apartment, opp.kanti shah hospital,Vakharbhag,Sangli 416416 hereby declare that I have purchased the semi constructed project and the land situated at CTS.No.6669B,Mangalwar bazaar chowk ,near Ratna hotel,Sahyadri nagar,Sangli 416416 bearing Rera registration no. P53100012164 from Malhar associates vide. Registered sale-deed no. 7321 dated 10/10/2022 .The same is reflected on the city survey records. From August 2017 upto October 2022 there was no development in the construction of project and the project was in stand still condition.…”
Source: RAGHUVEER’s extension records on MahaRERA (P53100012164), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RAGHUVEER
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53100012164
- Status
- Completed
- Builder
- VAZE BUILDER PROP. MUKAAYSH VAZE
- Location
- sahyadri nagar, Sangli · 416416
- Project type
- Others
- Registered on
- 1 Sep 2017
- Completion date at registration
- July 2019
- Latest completion date
- December 2026
- Delay so far
- 89 months
- Homes
- 34
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of RAGHUVEER, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MALHAR ANNEX | 100% | 80% | 30% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RAGHUVEER every month.
RAGHUVEER: buildings, flats and land, as filed on MahaRERA
- Buildings: MALHAR ANNEX (6 floors)
- Land: 741 sq m (about 0.2 acres) · sanctioned built-up 1,773 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of RAGHUVEER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RAGHUVEER: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RAGHUVEER
What is the possession date of RAGHUVEER?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RAGHUVEER in sahyadri nagar, Sangli is 31 December 2026 — 89 months later than 31 July 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for RAGHUVEER?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RAGHUVEER's builder has filed on MahaRERA, the official one, is 31 December 2026, already 89 months later than the 31 July 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RAGHUVEER extended?
According to GharKundli's check of MahaRERA records (updated November 2026), RAGHUVEER's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "I, Mr. Mukaaysh vaze (Prop. Vaze builder) 155, Sai pushp Apartment, opp.kanti shah hospital,Vakharbhag,Sangli 416416 hereby declare that I have purchased the semi constructed project and the land situated at CTS.No.6669B,Mangalwar bazaar chowk ,near Ratna hotel,Sahyadri nagar,Sangli 416416 bearing Rera registration no. P53100012164 from Malhar associates vide. Registered sale-deed no. 7321 dated 10/10/2022 .The same is reflected on the city survey records. From August 2017 upto October 2022 there was no development in the construction of project and the project was in stand still condition.…".
What is the RERA number of RAGHUVEER?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RAGHUVEER in sahyadri nagar, Sangli is P53100012164.
Is RAGHUVEER registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAGHUVEER is registered as P53100012164 and its status is "Completed".
What is the construction status of RAGHUVEER?
According to GharKundli's check of MahaRERA records (updated November 2026), RAGHUVEER's status on MahaRERA is "Completed". As filed by the builder, slab work on MALHAR ANNEX is 80% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.
Does RAGHUVEER have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is RAGHUVEER safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), RAGHUVEER is registered on MahaRERA as P53100012164, its MahaRERA status is "Completed", its completion date has moved 89 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RAGHUVEER's possession date changes?
The latest dates are on RAGHUVEER's MahaRERA page (P53100012164). GharKundli's Kundli Watch sends a free WhatsApp update on RAGHUVEER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RAGHUVEER have?
According to GharKundli's check of MahaRERA records (updated November 2026), RAGHUVEER has one building filed: MALHAR ANNEX with 6 floors.
How big is the land of RAGHUVEER?
According to GharKundli's check of MahaRERA records (updated November 2026), RAGHUVEER stands on 741 sq m of land (about 0.2 acres), with 1,773 sq m of sanctioned built-up area.
Where can I read reviews of RAGHUVEER?
Google Maps has reviews of RAGHUVEER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RAGHUVEER?
RAGHUVEER by VAZE BUILDER PROP. MUKAAYSH VAZE is in sahyadri nagar, Sangli (pincode 416416), near Vishrambag, Kupwad, Government Colony, Maharashtra, and is registered on MahaRERA as P53100012164, per GharKundli's check of MahaRERA records.
How many homes are in RAGHUVEER?
According to GharKundli's check of MahaRERA records (updated November 2026), RAGHUVEER has 34 homes in 1 tower registered on MahaRERA.
When was RAGHUVEER registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAGHUVEER was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on RAGHUVEER?
No court cases are listed for RAGHUVEER on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of RAGHUVEER?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VAZE BUILDER PROP. MUKAAYSH VAZE.
Check it yourself on MahaRERA
- How to check the possession date of RAGHUVEER
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Miraj
All 103 projects in Sangli (416416) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.