Skip to content
GharKundli

Morya Apartment

by YUVRAJ JAYSINGRAO PATIL · Rajarmpuri, Sangli 416416Also near Vishrambag, Hasara chowk, Dattanagar

What’s in the report? →

Possession: Morya Apartment (MahaRERA P53100005998) is marked completed on MahaRERA. It has 13 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P53100005998. Status: Completed.

Source: MahaRERA website — records for P53100005998, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Morya Apartment?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Morya Apartment

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2018 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53100005998
Status
Completed
Builder
YUVRAJ JAYSINGRAO PATIL
Location
Rajarmpuri, Sangli · 416416
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
April 2018
Homes
13
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Morya Apartment, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MORAYA APARTMENT100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Morya Apartment every 1–2 months.

Morya Apartment: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Yuvaraj Jaysingrao Patil has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 25 months late). No complaints on MahaRERA.

Read Google reviews of Morya Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Morya Apartment: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Morya Apartment

What is the possession date of Morya Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Morya Apartment in Rajarmpuri, Sangli is 20 April 2018.

Is the builder's possession date different from the MahaRERA date for Morya Apartment?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Morya Apartment's builder has filed on MahaRERA, the official one, is 20 April 2018, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Morya Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Morya Apartment in Rajarmpuri, Sangli is P53100005998.

Is Morya Apartment registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Morya Apartment is registered as P53100005998 and its status is "Completed".

What is the current construction status of Morya Apartment? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Morya Apartment's status on MahaRERA is "Completed". As filed by the builder, slab work on MORAYA APARTMENT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Morya Apartment have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Morya Apartment safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Morya Apartment is registered on MahaRERA as P53100005998, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Morya Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Morya Apartment is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Morya Apartment?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Morya Apartment: gharkundli.com/tools/property-cost-calculator

Has Morya Apartment received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Morya Apartment is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Morya Apartment completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Morya Apartment is marked completed on MahaRERA, and the completion date filed there is 20 April 2018. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Morya Apartment uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Morya Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Morya Apartment's possession date changes?

The latest dates are on Morya Apartment's MahaRERA page (P53100005998). GharKundli's Kundli Watch sends a free WhatsApp update on Morya Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Morya Apartment have?

According to GharKundli's check of MahaRERA records (updated November 2026), Morya Apartment has one building filed: MORAYA APARTMENT with 6 floors.

How big is the land of Morya Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Morya Apartment stands on 550 sq m of land (about 0.1 acres), with 549 sq m of sanctioned built-up area.

What is the track record of Morya Apartment's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Yuvaraj Jaysingrao Patil has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 25 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Morya Apartment?

Google Maps has reviews of Morya Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Morya Apartment?

Morya Apartment by YUVRAJ JAYSINGRAO PATIL is in Rajarmpuri, Sangli, pincode 416416 (near Vishrambag, Hasara chowk, Dattanagar), Maharashtra, and is registered on MahaRERA as P53100005998, per GharKundli's check of MahaRERA records. Its boundaries filed there include MUNICIPAL ROAD. Its land is filed as C S NO 2516. GharKundli lists all 368 MahaRERA projects in Sangli (416416).

How many flats are in Morya Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Morya Apartment has 13 homes in 1 tower registered on MahaRERA.

When was Morya Apartment registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Morya Apartment was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Does Morya Apartment have any legal issues or court cases?

No court cases are listed for Morya Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Morya Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is YUVRAJ JAYSINGRAO PATIL, which has 1 other project registered on MahaRERA.

Other projects in Miraj

All 368 projects in Sangli (416416) →

Other projects by YUVRAJ JAYSINGRAO PATIL

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.