Aditya Tower

by ADITYA CONSTRUCTIONS · MIDC Area, Sangli 416415

What’s in the report? →

Possession date of Aditya Tower (MahaRERA P53100021574): 21 April 2023, and it has already passed. It has 32 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P53100021574. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P53100021574, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (April 2023) has passed.

What do you want to know about Aditya Tower?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Aditya Tower

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53100021574
Status
Lapsed (registration period ended)
Builder
ADITYA CONSTRUCTIONS
Location
MIDC Area, Sangli · 416415
Project type
Others
Registered on
9 Jul 2019
Completion date at registration
April 2023
Latest completion date
April 2023
Homes
32
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Aditya Tower, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ADITYA TOWER0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aditya Tower every 1–2 months.

Aditya Tower: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Aditya Constructions has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 lapsed. No complaints on MahaRERA.

Read Google reviews of Aditya Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aditya Tower: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aditya Tower

What is the possession date of Aditya Tower?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aditya Tower in MIDC Area, Sangli is 21 April 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Aditya Tower?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aditya Tower's builder has filed on MahaRERA, the official one, is 21 April 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Aditya Tower?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aditya Tower in MIDC Area, Sangli is P53100021574.

Is Aditya Tower registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Tower is registered as P53100021574 and its status is "Lapsed (registration period ended)".

What is the current construction status of Aditya Tower? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Tower's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ADITYA TOWER is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Aditya Tower have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Aditya Tower safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Tower is registered on MahaRERA as P53100021574, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aditya Tower?

Aditya Tower isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Aditya Tower?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Aditya Tower: gharkundli.com/tools/property-cost-calculator

Has Aditya Tower received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Tower isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 21 April 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Aditya Tower?

According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Tower's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (21 April 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Aditya Tower uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Aditya Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Aditya Tower's possession date changes?

The latest dates are on Aditya Tower's MahaRERA page (P53100021574). GharKundli's Kundli Watch sends a free WhatsApp update on Aditya Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aditya Tower have?

According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Tower has one building filed: ADITYA TOWER with 5 floors.

How big is the land of Aditya Tower?

According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Tower stands on 1,135 sq m of land (about 0.3 acres), with 1,540 sq m of sanctioned built-up area.

What is the track record of Aditya Tower's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Constructions has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Aditya Tower?

Google Maps has reviews of Aditya Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aditya Tower?

Aditya Tower by ADITYA CONSTRUCTIONS is in MIDC Area, Sangli, pincode 416415, Maharashtra, and is registered on MahaRERA as P53100021574, per GharKundli's check of MahaRERA records. Its land is filed as S NO 937 P NO 2 ND 3. GharKundli lists all 95 MahaRERA projects in Willingdon College Sangli (416415).

How many flats are in Aditya Tower?

According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Tower has 32 homes in 1 tower registered on MahaRERA.

When was Aditya Tower registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Tower was registered on MahaRERA on 9 July 2019. GharKundli did not find a title report on the land on file there.

Does Aditya Tower have any legal issues or court cases?

No court cases are listed for Aditya Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Aditya Tower?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ADITYA CONSTRUCTIONS, which has 1 other project registered on MahaRERA.

Other projects in Miraj

All 95 projects in Willingdon College Sangli (416415) →

Other projects by ADITYA CONSTRUCTIONS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.