Nakshtra Varad Venkatesh
by NAKSHTRA INFRA · Chinmay Park Area, Sangli 416416Also near Budhgaon, MadhavnagarRegistered on MahaRERA as “VARAD VENKATESH”
What’s in the report? →Possession: Nakshtra Varad Venkatesh (MahaRERA P53100025887) is marked completed on MahaRERA. It has 22 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P53100025887. Status: Completed.
Source: MahaRERA website — records for P53100025887, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Nakshtra Varad Venkatesh?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Nakshtra Varad Venkatesh
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53100025887
- Status
- Completed
- Builder
- NAKSHTRA INFRA
- Location
- Chinmay Park Area, Sangli · 416416
- Project type
- Others
- Registered on
- 27 Jul 2020
- Completion date at registration
- January 2023
- Latest completion date
- January 2023
- Homes
- 22
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Nakshtra Varad Venkatesh, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VARAD VENTAESH | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nakshtra Varad Venkatesh every 1–2 months.
Nakshtra Varad Venkatesh: buildings, flats and land, as filed on MahaRERA
- Buildings: VARAD VENTAESH (5 floors)
- Land: 470 sq m (about 0.1 acres) · sanctioned built-up 667 sq m
- Land, as filed: 1301/50
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Nakshtra Infra has 4 projects on MahaRERA since 2019, this one included. Of the 4 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 6 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Nakshtra Varad Venkatesh →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Nakshtra Varad Venkatesh: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Nakshtra Varad Venkatesh
What is the possession date of Nakshtra Varad Venkatesh?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Nakshtra Varad Venkatesh in Chinmay Park Area, Sangli is 30 January 2023.
Is the builder's possession date different from the MahaRERA date for Nakshtra Varad Venkatesh?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Nakshtra Varad Venkatesh's builder has filed on MahaRERA, the official one, is 30 January 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Nakshtra Varad Venkatesh?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Nakshtra Varad Venkatesh in Chinmay Park Area, Sangli is P53100025887.
Is Nakshtra Varad Venkatesh registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakshtra Varad Venkatesh is registered as P53100025887 and its status is "Completed".
What is the current construction status of Nakshtra Varad Venkatesh? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakshtra Varad Venkatesh's status on MahaRERA is "Completed". As filed by the builder, slab work on VARAD VENTAESH is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Nakshtra Varad Venkatesh have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Nakshtra Varad Venkatesh safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakshtra Varad Venkatesh is registered on MahaRERA as P53100025887, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Nakshtra Varad Venkatesh?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakshtra Varad Venkatesh is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Nakshtra Varad Venkatesh?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Nakshtra Varad Venkatesh: gharkundli.com/tools/property-cost-calculator
Has Nakshtra Varad Venkatesh received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakshtra Varad Venkatesh is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Nakshtra Varad Venkatesh completed?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakshtra Varad Venkatesh is marked completed on MahaRERA, and the completion date filed there is 30 January 2023. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Has Nakshtra Varad Venkatesh uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Nakshtra Varad Venkatesh was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Nakshtra Varad Venkatesh's possession date changes?
The latest dates are on Nakshtra Varad Venkatesh's MahaRERA page (P53100025887). GharKundli's Kundli Watch sends a free WhatsApp update on Nakshtra Varad Venkatesh every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Nakshtra Varad Venkatesh have?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakshtra Varad Venkatesh has one building filed: VARAD VENTAESH with 5 floors.
How big is the land of Nakshtra Varad Venkatesh?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakshtra Varad Venkatesh stands on 470 sq m of land (about 0.1 acres), with 667 sq m of sanctioned built-up area.
What is the track record of Nakshtra Varad Venkatesh's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakshtra Infra has 4 projects on MahaRERA since 2019, this one included. Of the 4 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 6 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Nakshtra Varad Venkatesh?
Google Maps has reviews of Nakshtra Varad Venkatesh written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Nakshtra Varad Venkatesh?
Nakshtra Varad Venkatesh by NAKSHTRA INFRA is in Chinmay Park Area, Sangli, pincode 416416 (near Budhgaon, Madhavnagar), Maharashtra, and is registered on MahaRERA as P53100025887, per GharKundli's check of MahaRERA records. Its land is filed as 1301/50. GharKundli lists all 368 MahaRERA projects in Sangli (416416).
How many flats are in Nakshtra Varad Venkatesh?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakshtra Varad Venkatesh has 22 homes in 1 tower registered on MahaRERA.
When was Nakshtra Varad Venkatesh registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakshtra Varad Venkatesh was registered on MahaRERA on 27 July 2020. GharKundli did not find a title report on the land on file there.
Does Nakshtra Varad Venkatesh have any legal issues or court cases?
No court cases are listed for Nakshtra Varad Venkatesh on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Nakshtra Varad Venkatesh?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NAKSHTRA INFRA, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Nakshtra Varad Venkatesh
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Miraj
- Vishnu Hari Regency
- Nakshtra
- Platinum Plaza
- Aranya
- Irish Orison
- Elite Prime
- Sriram Vasant
- Shivnandini Complex
Other projects by NAKSHTRA INFRA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.