DHRUV RESIDENCY
by NIKESH GURUMUKH GIDWANI · Dhamani Road, SangliAlso near Vishrambag, Hasara chowk, Willingdon College Sangli
Possession: DHRUV RESIDENCY is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P53100026031. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about DHRUV RESIDENCY?
How the possession date of DHRUV RESIDENCY has moved
30 December 2021
Completion date given when the project was registered
30 August 2022
Extended at the builder's request (MahaRERA application EXT53100010797)
Reason the builder gave MahaRERA: “Due to corona and flood we are unable to complete the project in mentioned time line.”
28 February 2023
Revised completion date on MahaRERA
Source: DHRUV RESIDENCY’s extension records on MahaRERA (P53100026031), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DHRUV RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the February 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53100026031
- Status
- Completed
- Builder
- NIKESH GURUMUKH GIDWANI
- Location
- Dhamani Road, Sangli · 416416
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2020
- Completion date at registration
- December 2021
- Latest completion date
- February 2023
- Delay so far
- 14 months
- Homes
- 15
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of DHRUV RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DHRUV RESIDENCY | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DHRUV RESIDENCY every month.
DHRUV RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: DHRUV RESIDENCY (6 floors)
- Land: 657 sq m (about 0.2 acres) · sanctioned built-up 940 sq m
- Boundaries filed include: ROAD AND RESIDENCE OF BHALERAO
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of DHRUV RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DHRUV RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DHRUV RESIDENCY
What is the possession date of DHRUV RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for DHRUV RESIDENCY in Dhamani Road, Sangli is 28 February 2023 — 14 months later than 30 December 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for DHRUV RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DHRUV RESIDENCY's builder has filed on MahaRERA, the official one, is 28 February 2023, already 14 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of DHRUV RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated November 2026), DHRUV RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 30 August 2022, giving the reason "Due to corona and flood we are unable to complete the project in mentioned time line.".
What is the RERA number of DHRUV RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of DHRUV RESIDENCY in Dhamani Road, Sangli is P53100026031.
Is DHRUV RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), DHRUV RESIDENCY is registered as P53100026031 and its status is "Completed".
What is the construction status of DHRUV RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), DHRUV RESIDENCY's status on MahaRERA is "Completed". As filed by the builder, slab work on DHRUV RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does DHRUV RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is DHRUV RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), DHRUV RESIDENCY is registered on MahaRERA as P53100026031, its MahaRERA status is "Completed", its completion date has moved 14 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DHRUV RESIDENCY's possession date changes?
The latest dates are on DHRUV RESIDENCY's MahaRERA page (P53100026031). GharKundli's Kundli Watch sends a free WhatsApp update on DHRUV RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DHRUV RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), DHRUV RESIDENCY has one building filed: DHRUV RESIDENCY with 6 floors.
How big is the land of DHRUV RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), DHRUV RESIDENCY stands on 657 sq m of land (about 0.2 acres), with 940 sq m of sanctioned built-up area.
Where can I read reviews of DHRUV RESIDENCY?
Google Maps has reviews of DHRUV RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DHRUV RESIDENCY?
DHRUV RESIDENCY by NIKESH GURUMUKH GIDWANI is in Dhamani Road, Sangli (pincode 416416), near Vishrambag, Hasara chowk, Willingdon College Sangli, Maharashtra, and is registered on MahaRERA as P53100026031, per GharKundli's check of MahaRERA records. Its boundaries filed there include ROAD AND RESIDENCE OF BHALERAO.
How many homes are in DHRUV RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), DHRUV RESIDENCY has 15 homes in 1 tower registered on MahaRERA.
When was DHRUV RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), DHRUV RESIDENCY was registered on MahaRERA on 11 August 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on DHRUV RESIDENCY?
No court cases are listed for DHRUV RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of DHRUV RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NIKESH GURUMUKH GIDWANI.
Check it yourself on MahaRERA
- How to check the possession date of DHRUV RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Miraj
- VISHNU HARI REGENCY
- NAKSHTRA
- PLATINUM PLAZA
- ARANYA
- ELITE PRIME
- IRISH ORISON
- SRIRAM VASANT
- SHIVNANDINI COMPLEX
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.