Casa Bella
by VIKRAM PUNDALIK GADADE · Pragati Coloy, Sangli 416416Also near Vishrambag, Dattanagar, South Shivaji Nagar
What’s in the report? →Possession: Casa Bella (MahaRERA P53100029466) is marked completed on MahaRERA. It has 10 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P53100029466. Status: Completed.
Source: MahaRERA website — records for P53100029466, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Casa Bella?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Casa Bella
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53100029466
- Status
- Completed
- Builder
- VIKRAM PUNDALIK GADADE
- Location
- Pragati Coloy, Sangli · 416416
- Project type
- Residential / Group Housing
- Registered on
- 29 May 2021
- Completion date at registration
- December 2022
- Homes
- 10
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Casa Bella, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CASA BELLA | 100% | 95% | 50% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Casa Bella every 1–2 months.
Casa Bella: buildings, flats and land, as filed on MahaRERA
- Buildings: CASA BELLA (7 floors)
- Land: 341 sq m (about 0.1 acres) · sanctioned built-up 679 sq m
- Land, as filed: S NO 72 1 PLOT NO 20
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Vikram Pundalik Gadade has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, all within the promised date. No complaints on MahaRERA.
Read Google reviews of Casa Bella →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Casa Bella: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Casa Bella
What is the possession date of Casa Bella?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Casa Bella in Pragati Coloy, Sangli is 31 December 2022.
Is the builder's possession date different from the MahaRERA date for Casa Bella?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Casa Bella's builder has filed on MahaRERA, the official one, is 31 December 2022, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Casa Bella?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Casa Bella in Pragati Coloy, Sangli is P53100029466.
Is Casa Bella registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Casa Bella is registered as P53100029466 and its status is "Completed".
What is the current construction status of Casa Bella? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Casa Bella's status on MahaRERA is "Completed". As filed by the builder, slab work on CASA BELLA is 95% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does Casa Bella have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Casa Bella safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Casa Bella is registered on MahaRERA as P53100029466, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Casa Bella?
According to GharKundli's check of MahaRERA records (updated November 2026), Casa Bella is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Casa Bella?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Casa Bella: gharkundli.com/tools/property-cost-calculator
Has Casa Bella received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated November 2026), Casa Bella is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Casa Bella completed?
According to GharKundli's check of MahaRERA records (updated November 2026), Casa Bella is marked completed on MahaRERA, and the completion date filed there is 31 December 2022. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Has Casa Bella uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Casa Bella was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Casa Bella's possession date changes?
The latest dates are on Casa Bella's MahaRERA page (P53100029466). GharKundli's Kundli Watch sends a free WhatsApp update on Casa Bella every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Casa Bella have?
According to GharKundli's check of MahaRERA records (updated November 2026), Casa Bella has one building filed: CASA BELLA with 7 floors.
How big is the land of Casa Bella?
According to GharKundli's check of MahaRERA records (updated November 2026), Casa Bella stands on 341 sq m of land (about 0.1 acres), with 679 sq m of sanctioned built-up area.
What is the track record of Casa Bella's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Vikram Pundalik Gadade has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, all within the promised date. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Casa Bella?
Google Maps has reviews of Casa Bella written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Casa Bella?
Casa Bella by VIKRAM PUNDALIK GADADE is in Pragati Coloy, Sangli, pincode 416416 (near Vishrambag, Dattanagar, South Shivaji Nagar), Maharashtra, and is registered on MahaRERA as P53100029466, per GharKundli's check of MahaRERA records. Its land is filed as S NO 72 1 PLOT NO 20. GharKundli lists all 368 MahaRERA projects in Sangli (416416).
How many flats are in Casa Bella?
According to GharKundli's check of MahaRERA records (updated November 2026), Casa Bella has 10 homes in 1 tower registered on MahaRERA.
When was Casa Bella registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Casa Bella was registered on MahaRERA on 29 May 2021. GharKundli did not find a title report on the land on file there.
Does Casa Bella have any legal issues or court cases?
No court cases are listed for Casa Bella on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Casa Bella?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VIKRAM PUNDALIK GADADE, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Casa Bella
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Miraj
- Vishnu Hari Regency
- Nakshtra
- Platinum Plaza
- Aranya
- Elite Prime
- Irish Orison
- Sriram Vasant
- Shivnandini Complex
Other projects by VIKRAM PUNDALIK GADADE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.