VISION CITY
by VISION GROUP · Hasara Chowk, SangliAlso near Vishrambag, Willingdon College Sangli
Possession date of VISION CITY: 30 January 2028, moved from 31 March 2026 (18 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P53100045960, and currently active. Its completion date has moved from March 2026 to January 2028: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VISION CITY?
How the possession date of VISION CITY has moved
31 March 2026
Completion date given when the project was registered
30 September 2027
Extended at the builder's request (MahaRERA application EA14032620225)
Reason the builder gave MahaRERA:
“Market Conditions & Customer Response: The slowdown in market demand and lower-than-expected customer response has directly impacted the pace of sales and subsequent cash flow, thereby affecting project timelines. Government Authority Appro…” Read the full reason
“Market Conditions & Customer Response: The slowdown in market demand and lower-than-expected customer response has directly impacted the pace of sales and subsequent cash flow, thereby affecting project timelines. Government Authority Approvals: Certain statutory approvals and No Objection Certificates (NOCs) from relevant government authorities have taken longer than anticipated, which has further contributed to the delay. We wish to emphasize that the delay is not due to any negligence or lack of effort on our part, but purely on account of external factors as mentioned above. We remain c…”30 January 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: VISION CITY’s extension records on MahaRERA (P53100045960), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VISION CITY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53100045960
- Status
- Registered and active
- Builder
- VISION GROUP
- Location
- Hasara Chowk, Sangli · 416416
- Project type
- Others
- Registered on
- 15 Jun 2022
- Completion date at registration
- March 2026
- Latest completion date
- January 2028
- Delay so far
- 18 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 103
- Sold or booked
- 78%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of VISION CITY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING C | 90% | 100% | 70% | 60% |
| BUNGALOW UNIT 1 TO 7 | 100% | 100% | 85% | 0% |
| WING D | 100% | 100% | 90% | 70% |
Commencement certificate (CC), as filed on MahaRERA
- WING C: covers 12 floors
- BUNGALOW UNIT 1 TO 7: covers 2 floors
- WING D: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VISION CITY every month.
VISION CITY: buildings, flats and land, as filed on MahaRERA
- Buildings: WING C (15 floors, 60 units) · BUNGALOW UNIT 1 TO 7 (2 floors, 7 units) · WING D (15 floors, 70 units)
- Car parking: 96 covered, 7 open
- Land: 3,851 sq m (about 1.0 acres) · sanctioned built-up 11,707 sq m
- Boundaries filed include: COLONY ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Vision Realities (a group of 2 linked companies) has 4 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 3 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of VISION CITY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VISION CITY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VISION CITY
What is the possession date of VISION CITY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VISION CITY in Hasara Chowk, Sangli is 30 January 2028 — 18 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for VISION CITY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VISION CITY's builder has filed on MahaRERA, the official one, is 30 January 2028, already 18 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VISION CITY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), VISION CITY's builder applied to MahaRERA to extend the completion date once: to 30 September 2027, giving the reason "Market Conditions & Customer Response: The slowdown in market demand and lower-than-expected customer response has directly impacted the pace of sales and subsequent cash flow, thereby affecting project timelines. Government Authority Approvals: Certain statutory approvals and No Objection Certificates (NOCs) from relevant government authorities have taken longer than anticipated, which has further contributed to the delay. We wish to emphasize that the delay is not due to any negligence or lack of effort on our part, but purely on account of external factors as mentioned above. We remain c…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of VISION CITY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VISION CITY in Hasara Chowk, Sangli is P53100045960.
Is VISION CITY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VISION CITY is registered as P53100045960 and its status is "Registered and active".
What is the construction status of VISION CITY?
According to GharKundli's check of MahaRERA records (updated October 2026), VISION CITY's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does VISION CITY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is VISION CITY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VISION CITY is registered on MahaRERA as P53100045960, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VISION CITY's possession date changes?
The latest dates are on VISION CITY's MahaRERA page (P53100045960). GharKundli's Kundli Watch sends a free WhatsApp update on VISION CITY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VISION CITY have?
According to GharKundli's check of MahaRERA records (updated October 2026), VISION CITY has 3 buildings filed: WING C with 15 floors and 60 units; BUNGALOW UNIT 1 TO 7 with 2 floors and 7 units; WING D with 15 floors and 70 units.
How much parking does VISION CITY have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 96 covered and 7 open car parking spaces for VISION CITY.
How big is the land of VISION CITY?
According to GharKundli's check of MahaRERA records (updated October 2026), VISION CITY stands on 3,851 sq m of land (about 1.0 acres), with 11,707 sq m of sanctioned built-up area.
What is the track record of VISION CITY's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vision Realities (a group of 2 linked companies) has 4 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 3 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of VISION CITY?
Google Maps has reviews of VISION CITY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VISION CITY?
VISION CITY by VISION GROUP is in Hasara Chowk, Sangli (pincode 416416), near Vishrambag, Willingdon College Sangli, Maharashtra, and is registered on MahaRERA as P53100045960, per GharKundli's check of MahaRERA records. Its boundaries filed there include COLONY ROAD.
How many homes are in VISION CITY?
According to GharKundli's check of MahaRERA records (updated October 2026), VISION CITY has 103 homes in 3 towers registered on MahaRERA, and 78% of them are sold or booked.
When was VISION CITY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VISION CITY was registered on MahaRERA on 15 June 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on VISION CITY?
No court cases are listed for VISION CITY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VISION CITY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VISION GROUP, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of VISION CITY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Sangli →
Other projects in Miraj
- VISHNU HARI REGENCY
- NAKSHTRA
- PLATINUM PLAZA
- ARANYA
- ELITE PRIME
- IRISH ORISON
- SRIRAM VASANT
- SHIVNANDINI COMPLEX
Other projects by VISION GROUP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.