by PHOENIX BUILDCON JOINT VENTURE AOP · Near Altekar Hall, SangliAlso near Miraj, District Court Sangli

Possession date of NAKSHATRA: 31 July 2026. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P53100046403. Status: Lapsed (registration period ended). Its completion date is now July 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (July 2026) has passed.

What do you want to know about NAKSHATRA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NAKSHATRA has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 July 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: NAKSHATRA’s extension records on MahaRERA (P53100046403), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NAKSHATRA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53100046403
Status
Lapsed (registration period ended)
Builder
PHOENIX BUILDCON JOINT VENTURE AOP
Location
Near Altekar Hall, Sangli · 416410
Project type
Others
Registered on
22 Jun 2022
Completion date at registration
March 2026
Latest completion date
July 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
42
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of NAKSHATRA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NAKSHATRA100%100%80%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NAKSHATRA every month.

NAKSHATRA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of NAKSHATRA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NAKSHATRA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NAKSHATRA

What is the possession date of NAKSHATRA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NAKSHATRA in Near Altekar Hall, Sangli is 31 July 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for NAKSHATRA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NAKSHATRA's builder has filed on MahaRERA, the official one, is 31 July 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of NAKSHATRA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NAKSHATRA in Near Altekar Hall, Sangli is P53100046403.

Is NAKSHATRA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA is registered as P53100046403 and its status is "Lapsed (registration period ended)".

What is the construction status of NAKSHATRA?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NAKSHATRA is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does NAKSHATRA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is NAKSHATRA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA is registered on MahaRERA as P53100046403, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NAKSHATRA's possession date changes?

The latest dates are on NAKSHATRA's MahaRERA page (P53100046403). GharKundli's Kundli Watch sends a free WhatsApp update on NAKSHATRA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NAKSHATRA have?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA has one building filed: NAKSHATRA with 7 floors.

How big is the land of NAKSHATRA?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA stands on 923 sq m of land (about 0.2 acres), with 2,065 sq m of sanctioned built-up area.

Where can I read reviews of NAKSHATRA?

Google Maps has reviews of NAKSHATRA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NAKSHATRA?

NAKSHATRA by PHOENIX BUILDCON JOINT VENTURE AOP is in Near Altekar Hall, Sangli (pincode 416410), near Miraj, District Court Sangli, Maharashtra, and is registered on MahaRERA as P53100046403, per GharKundli's check of MahaRERA records.

How many homes are in NAKSHATRA?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA has 42 homes in 1 tower registered on MahaRERA.

When was NAKSHATRA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA was registered on MahaRERA on 22 June 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on NAKSHATRA?

No court cases are listed for NAKSHATRA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of NAKSHATRA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PHOENIX BUILDCON JOINT VENTURE AOP.

All projects with possession due in 2026 in Sangli →

Other projects in Miraj

All 37 projects in Miraj (416410) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.