Possession date of SAMARTH GIRNAR HEIGHTS: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P53100048691, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SAMARTH GIRNAR HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAMARTH GIRNAR HEIGHTS has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SAMARTH GIRNAR HEIGHTS’s extension records on MahaRERA (P53100048691), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAMARTH GIRNAR HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53100048691
Status
Registered and active
Builder
samarth associates
Location
Vishrambag, Sangli · 416416
Project type
Residential / Group Housing
Registered on
12 Jan 2023
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
20
Sold or booked
58%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of SAMARTH GIRNAR HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAMARTH GIRNAR HEIGHTS100%100%100%80%

Commencement certificate (CC), as filed on MahaRERA

  • SAMARTH GIRNAR HEIGHTS: covers PARKING+6

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAMARTH GIRNAR HEIGHTS every month.

SAMARTH GIRNAR HEIGHTS: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Samarth Associates (a group of 2 linked companies) has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of SAMARTH GIRNAR HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAMARTH GIRNAR HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAMARTH GIRNAR HEIGHTS

What is the possession date of SAMARTH GIRNAR HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAMARTH GIRNAR HEIGHTS in Vishrambag, Sangli is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SAMARTH GIRNAR HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAMARTH GIRNAR HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SAMARTH GIRNAR HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAMARTH GIRNAR HEIGHTS in Vishrambag, Sangli is P53100048691.

Is SAMARTH GIRNAR HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH GIRNAR HEIGHTS is registered as P53100048691 and its status is "Registered and active".

What is the construction status of SAMARTH GIRNAR HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH GIRNAR HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAMARTH GIRNAR HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SAMARTH GIRNAR HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SAMARTH GIRNAR HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH GIRNAR HEIGHTS is registered on MahaRERA as P53100048691, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAMARTH GIRNAR HEIGHTS's possession date changes?

The latest dates are on SAMARTH GIRNAR HEIGHTS's MahaRERA page (P53100048691). GharKundli's Kundli Watch sends a free WhatsApp update on SAMARTH GIRNAR HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAMARTH GIRNAR HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH GIRNAR HEIGHTS has one building filed: SAMARTH GIRNAR HEIGHTS with 7 floors and 20 units.

How big is the land of SAMARTH GIRNAR HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH GIRNAR HEIGHTS stands on 446 sq m of land (about 0.1 acres), with 1,370 sq m of sanctioned built-up area.

What is the track record of SAMARTH GIRNAR HEIGHTS's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Samarth Associates (a group of 2 linked companies) has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAMARTH GIRNAR HEIGHTS?

Google Maps has reviews of SAMARTH GIRNAR HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAMARTH GIRNAR HEIGHTS?

SAMARTH GIRNAR HEIGHTS by samarth associates is in Vishrambag, Sangli (pincode 416416), near Hasara chowk, Maharashtra, and is registered on MahaRERA as P53100048691, per GharKundli's check of MahaRERA records.

How many homes are in SAMARTH GIRNAR HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH GIRNAR HEIGHTS has 20 homes in 1 tower registered on MahaRERA, and 58% of them are sold or booked.

When was SAMARTH GIRNAR HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH GIRNAR HEIGHTS was registered on MahaRERA on 12 January 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on SAMARTH GIRNAR HEIGHTS?

No court cases are listed for SAMARTH GIRNAR HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAMARTH GIRNAR HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is samarth associates, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2027 in Sangli →

Other projects in Vishrambag

All 149 projects in Sangli (416416) →

Other projects by samarth associates

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.