Savaliya Residency
by Shree Savaliya Housing LLP · Mira Road East, Thane 401107Also near Bhayander, Mira Bhayandar, Pleasant Park
What’s in the report? →Possession date of Savaliya Residency (MahaRERA P51700027312): 31 July 2026, moved from 30 June 2025 (13 months later), and it has already passed. It has 39 homes, 84% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700027312. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51700027312, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about Savaliya Residency?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Savaliya Residency has moved
30 June 2025
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EA09072502009)
Reason the builder gave MahaRERA:
“This is to inform that the revised timeline for the completion of the project Shree Krishna Bhoomi by Shree Krishna Buildcon has been determined after evaluating the current progress and remaining scope of work, as reflected in the submitte…” Read the full reason
“This is to inform that the revised timeline for the completion of the project Shree Krishna Bhoomi by Shree Krishna Buildcon has been determined after evaluating the current progress and remaining scope of work, as reflected in the submitted PERT Chart. The structural activities including slabs of the superstructure, internal walls, and internal plastering—originally scheduled for completion by mid-2025—faced delays due to challenges in contractor coordination, material supply disruptions, and labor resource availability. These delays cascaded into the finishing and internal works like floo…”31 July 2026
Extended at the builder's request (MahaRERA application EA04022619710)
Reason the builder gave MahaRERA:
“The Promoter respectfully submits that the construction of the project is substantially completed and approximately 95% of the work is finished. All major civil, structural, masonry, plastering, flooring, doors and windows, and finishing wo…” Read the full reason
“The Promoter respectfully submits that the construction of the project is substantially completed and approximately 95% of the work is finished. All major civil, structural, masonry, plastering, flooring, doors and windows, and finishing works have been completed and the building is fully ready for occupation in all respects, except for a few statutory and service-related approvals. The balance works presently pending are limited to installation of electrical meters by MSEDCL, completion and certification of the fire-fighting system, commissioning of municipal water supply connection, and c…”
Source: Savaliya Residency’s extension records on MahaRERA (P51700027312), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Savaliya Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700027312
- Status
- Lapsed (registration period ended)
- Builder
- Shree Savaliya Housing LLP
- Location
- Mira Road East, Thane · 401107
- Project type
- Residential / Group Housing
- Registered on
- 1 Dec 2020
- Completion date at registration
- June 2025
- Latest completion date
- July 2026
- Delay so far
- 13 months
- Homes
- 39
- Sold or booked
- 84%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Savaliya Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAVALIYA RESIDENCY | 100% | 100% | 100% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- SAVALIYA RESIDENCY: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Savaliya Residency every 1–2 months.
Savaliya Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: SAVALIYA RESIDENCY (17 floors, 49 units)
- Land: 1,250 sq m (about 0.3 acres) · sanctioned built-up 911 sq m · recreational space 271 sq m
- Boundaries filed include: SANGHVI COMPLEX
- Land, as filed: /OLD SURVEY NO 475/, NEW SURVEY NO 118/2
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Shree Savaliya Housing (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 58 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Savaliya Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Savaliya Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Savaliya Residency
What is the possession date of Savaliya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Savaliya Residency in Mira Road East, Thane is 31 July 2026 — 13 months later than 30 June 2025, the date given at registration. That date has already passed.
The date has already moved 13 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Savaliya Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Savaliya Residency's builder has filed on MahaRERA, the official one, is 31 July 2026, already 13 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Savaliya Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Savaliya Residency's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "This is to inform that the revised timeline for the completion of the project Shree Krishna Bhoomi by Shree Krishna Buildcon has been determined after evaluating the current progress and remaining scope of work, as reflected in the submitted PERT Chart. The structural activities including slabs of the superstructure, internal walls, and internal plastering—originally scheduled for completion by mid-2025—faced delays due to challenges in contractor coordination, material supply disruptions, and labor resource availability. These delays cascaded into the finishing and internal works like floo…"; to 31 July 2026, giving the reason "The Promoter respectfully submits that the construction of the project is substantially completed and approximately 95% of the work is finished. All major civil, structural, masonry, plastering, flooring, doors and windows, and finishing works have been completed and the building is fully ready for occupation in all respects, except for a few statutory and service-related approvals. The balance works presently pending are limited to installation of electrical meters by MSEDCL, completion and certification of the fire-fighting system, commissioning of municipal water supply connection, and c…".
What is the RERA number of Savaliya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Savaliya Residency in Mira Road East, Thane is P51700027312.
Is Savaliya Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Savaliya Residency is registered as P51700027312 and its status is "Lapsed (registration period ended)".
What is the current construction status of Savaliya Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Savaliya Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAVALIYA RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Savaliya Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Savaliya Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Savaliya Residency is registered on MahaRERA as P51700027312, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 13 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Savaliya Residency?
Savaliya Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Savaliya Residency?
For a flat in Savaliya Residency (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Savaliya Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Savaliya Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Savaliya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Savaliya Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Savaliya Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Savaliya Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Savaliya Residency's possession date changes?
The latest dates are on Savaliya Residency's MahaRERA page (P51700027312). GharKundli's Kundli Watch sends a free WhatsApp update on Savaliya Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Savaliya Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Savaliya Residency has one building filed: SAVALIYA RESIDENCY with 17 floors and 49 units.
How big is the land of Savaliya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Savaliya Residency stands on 1,250 sq m of land (about 0.3 acres), with 911 sq m of sanctioned built-up area and 271 sq m of recreational open space.
What is the track record of Savaliya Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Savaliya Housing (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 58 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Savaliya Residency?
Google Maps has reviews of Savaliya Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Savaliya Residency?
Savaliya Residency by Shree Savaliya Housing LLP is in Mira Road East, Thane, pincode 401107 (near Bhayander, Mira Bhayandar, Pleasant Park), Maharashtra, and is registered on MahaRERA as P51700027312, per GharKundli's check of MahaRERA records. Its boundaries filed there include SANGHVI COMPLEX. Its land is filed as /OLD SURVEY NO 475/, NEW SURVEY NO 118/2. GharKundli lists all 323 MahaRERA projects in Mira Road East (401107).
How many flats are in Savaliya Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Savaliya Residency has 39 homes in 1 tower registered on MahaRERA, and 84% of them are sold or booked.
When was Savaliya Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Savaliya Residency was registered on MahaRERA on 1 December 2020. GharKundli did not find a title report on the land on file there.
Does Savaliya Residency have any legal issues or court cases?
No court cases are listed for Savaliya Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Savaliya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree Savaliya Housing LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Savaliya Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Mira Road East (401107)
- Shanti Signature by Ashit Shah
- Lotus
- Sheetal Utsav
- JP Connect-miraroad
- Chandresh Terrace
- Urban Reserve Wing B
- Palm Lands
- Raj Crest
Other projects by Shree Savaliya Housing LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.