Kalpataru One - Wing A
by Kalpataru Properties Limited (Agile) · Worli Naka, MumbaiAlso near Worli Colony, Delisle Road, Prabhadevi
Possession date of Kalpataru One - Wing A: 31 July 2032. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900055246, and currently active. Its completion date is now July 2032, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Kalpataru One - Wing A?
How the possession date of Kalpataru One - Wing A has moved
31 March 2032
Completion date given when the project was registered
31 July 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Kalpataru One - Wing A’s extension records on MahaRERA (P51900055246), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kalpataru One - Wing A
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 court cases, and how it ended
- Construction pace against the July 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Kalpataru One - Wing BP51900079410 · possession 31 Jul 2032
- MahaRERA registration
- P51900055246
- Status
- Registered and active
- Builder
- Kalpataru Properties Limited
- Location
- Worli Naka, Mumbai · 400018
- Project type
- Residential / Group Housing
- Registered on
- 14 Mar 2024
- Completion date at registration
- March 2032
- Latest completion date
- July 2032
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 111
- Sold or booked
- 33%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Kalpataru One - Wing A, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Wing A: covers 76 floors
Latest CC order on MahaRERA: dated 10/04/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kalpataru One - Wing A every month.
Kalpataru One - Wing A: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 5 BHK | 4,411 – 4,434 | 102 |
| Other | 6,227 – 7,382 | 9 |
- Buildings: Wing A (76 floors, 111 units)
- Car parking: 223 covered
- Land: 1,350 sq m (about 0.3 acres) · sanctioned built-up 54,337 sq m
The builder’s record and reviews
Kalpataru (a group of 21 linked companies) has 96 projects on MahaRERA since 2017, this one included. Of the 92 GharKundli has checked: 57 finished, 53 within the promised date and 4 needed more time (typically 5 months); 33 still being built, 2 past the promised date (typically 5 months late); 2 lapsed. 386 complaints on MahaRERA across 57 projects.
Read Google reviews of Kalpataru One - Wing A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kalpataru One - Wing A: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Kalpataru One - Wing A
What is the possession date of Kalpataru One - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kalpataru One - Wing A in Worli Naka, Mumbai is 31 July 2032, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Kalpataru One - Wing A?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kalpataru One - Wing A's builder has filed on MahaRERA, the official one, is 31 July 2032, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Kalpataru One - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kalpataru One - Wing A in Worli Naka, Mumbai is P51900055246.
Is Kalpataru One - Wing A registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru One - Wing A is registered as P51900055246 and its status is "Registered and active".
What is the construction status of Kalpataru One - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru One - Wing A's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing A is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Kalpataru One - Wing A have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Kalpataru One - Wing A safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru One - Wing A is registered on MahaRERA as P51900055246, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Kalpataru One - Wing A have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Kalpataru One - Wing B (P51900079410, possession 31 Jul 2032). Check that your agreement names the registration of your own wing.
How can I get updates if Kalpataru One - Wing A's possession date changes?
The latest dates are on Kalpataru One - Wing A's MahaRERA page (P51900055246). GharKundli's Kundli Watch sends a free WhatsApp update on Kalpataru One - Wing A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kalpataru One - Wing A have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru One - Wing A has one building filed: Wing A with 76 floors and 111 units.
What are the flat sizes (carpet area) in Kalpataru One - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Kalpataru One - Wing A: 5 BHK: 4411 to 4434 sq ft carpet (102 homes); Other: 6227 to 7382 sq ft carpet (9 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Kalpataru One - Wing A have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 223 covered car parking spaces for Kalpataru One - Wing A.
How big is the land of Kalpataru One - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru One - Wing A stands on 1,350 sq m of land (about 0.3 acres), with 54,337 sq m of sanctioned built-up area.
What is the track record of Kalpataru One - Wing A's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru (a group of 21 linked companies) has 96 projects on MahaRERA since 2017, this one included. Of the 92 GharKundli has checked: 57 finished, 53 within the promised date and 4 needed more time (typically 5 months); 33 still being built, 2 past the promised date (typically 5 months late); 2 lapsed. 386 complaints on MahaRERA across 57 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Kalpataru One - Wing A?
Google Maps has reviews of Kalpataru One - Wing A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Kalpataru One - Wing A?
Kalpataru One - Wing A by Kalpataru Properties Limited (Agile) is in Worli Naka, Mumbai (pincode 400018), near Worli Colony, Delisle Road, Prabhadevi, Maharashtra, and is registered on MahaRERA as P51900055246, per GharKundli's check of MahaRERA records.
How many homes are in Kalpataru One - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru One - Wing A has 111 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.
When was Kalpataru One - Wing A registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru One - Wing A was registered on MahaRERA on 14 March 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on Kalpataru One - Wing A?
3 court cases are listed for Kalpataru One - Wing A on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Kalpataru One - Wing A?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kalpataru Properties Limited, the company Agile files this project under, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Kalpataru One - Wing A
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400018
- Naman Xana
- Four Seasons Private Residences Phase - 2
- WORLI HOUSE
- Sea Face
- SEA FACE HOUSE, WORLI
- Godrej Trilogy Seaturf
- Godrej Trilogy Seafront
- EMBASSY CITADEL
Other projects by Kalpataru Properties Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.