Four Seasons Private Residences Phase - 2
by Provenance Land Private Limited · Worli, MumbaiAlso near Lower Parel, Kalanagar, Bandra East, Delisle Road
Possession date of Four Seasons Private Residences Phase - 2: 31 December 2025, moved from 30 December 2023 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900022056. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Four Seasons Private Residences Phase - 2?
How the possession date of Four Seasons Private Residences Phase - 2 has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51900018506)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”31 December 2025
Extended at the builder's request (MahaRERA application EXT51900027603)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen procurement issues, site conditions, coordination challenges. Despite these setbacks, we are working di…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen procurement issues, site conditions, coordination challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-12-2025 to complete the project and fulfil all reg…”
Source: Four Seasons Private Residences Phase - 2’s extension records on MahaRERA (P51900022056), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Four Seasons Private Residences Phase - 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Four Seasons Private Residences Phase - 1P51900002789 · possession 30 Dec 2022
- MahaRERA registration
- P51900022056
- Status
- Lapsed (registration period ended)
- Builder
- Provenance Land Private Limited
- Location
- Worli, Mumbai · 400018
- Project type
- Residential / Group Housing
- Registered on
- 25 Aug 2019
- Completion date at registration
- December 2023
- Latest completion date
- December 2025
- Delay so far
- 24 months
- Homes
- 10
- Sold or booked
- 78%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Four Seasons Private Residences Phase - 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Four Seasons Private Residences | 100% | 100% | 100% | 60% |
Commencement certificate (CC), as filed on MahaRERA
- Four Seasons Private Residences: covers 17 (45th to 61st Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Four Seasons Private Residences Phase - 2 every month.
Four Seasons Private Residences Phase - 2: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 2,860 | 5 |
| Other | 4,979 – 5,065 | 3 |
| Duplex | 4,892 – 5,208 | 2 |
- Buildings: Four Seasons Private Residences (63 floors, 10 units)
- Land: 4,069 sq m (about 1.0 acres) · sanctioned built-up 3,686 sq m · recreational space 610 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Provenance Land has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 18 months); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Four Seasons Private Residences Phase - 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Four Seasons Private Residences Phase - 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Four Seasons Private Residences Phase - 2
What is the possession date of Four Seasons Private Residences Phase - 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Four Seasons Private Residences Phase - 2 in Worli, Mumbai is 31 December 2025 — 24 months later than 30 December 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Four Seasons Private Residences Phase - 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Four Seasons Private Residences Phase - 2's builder has filed on MahaRERA, the official one, is 31 December 2025, already 24 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Four Seasons Private Residences Phase - 2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Four Seasons Private Residences Phase - 2's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 31 December 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen procurement issues, site conditions, coordination challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-12-2025 to complete the project and fulfil all reg…".
What is the RERA number of Four Seasons Private Residences Phase - 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Four Seasons Private Residences Phase - 2 in Worli, Mumbai is P51900022056.
Is Four Seasons Private Residences Phase - 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Four Seasons Private Residences Phase - 2 is registered as P51900022056 and its status is "Lapsed (registration period ended)".
What is the construction status of Four Seasons Private Residences Phase - 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Four Seasons Private Residences Phase - 2's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Four Seasons Private Residences is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Four Seasons Private Residences Phase - 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Four Seasons Private Residences Phase - 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Four Seasons Private Residences Phase - 2 is registered on MahaRERA as P51900022056, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Four Seasons Private Residences Phase - 2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Four Seasons Private Residences Phase - 1 (P51900002789, possession 30 Dec 2022). Check that your agreement names the registration of your own wing.
How can I get updates if Four Seasons Private Residences Phase - 2's possession date changes?
The latest dates are on Four Seasons Private Residences Phase - 2's MahaRERA page (P51900022056). GharKundli's Kundli Watch sends a free WhatsApp update on Four Seasons Private Residences Phase - 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Four Seasons Private Residences Phase - 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Four Seasons Private Residences Phase - 2 has one building filed: Four Seasons Private Residences with 63 floors and 10 units.
What are the flat sizes (carpet area) in Four Seasons Private Residences Phase - 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Four Seasons Private Residences Phase - 2: 3 BHK: 2860 sq ft carpet (5 homes); Other: 4979 to 5065 sq ft carpet (3 homes); Duplex: 4892 to 5208 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Four Seasons Private Residences Phase - 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Four Seasons Private Residences Phase - 2 stands on 4,069 sq m of land (about 1.0 acres), with 3,686 sq m of sanctioned built-up area and 610 sq m of recreational open space.
What is the track record of Four Seasons Private Residences Phase - 2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Provenance Land has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 18 months); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Four Seasons Private Residences Phase - 2?
Google Maps has reviews of Four Seasons Private Residences Phase - 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Four Seasons Private Residences Phase - 2?
Four Seasons Private Residences Phase - 2 by Provenance Land Private Limited is in Worli, Mumbai (pincode 400018), near Lower Parel, Kalanagar, Bandra East, Delisle Road, Maharashtra, and is registered on MahaRERA as P51900022056, per GharKundli's check of MahaRERA records.
How many homes are in Four Seasons Private Residences Phase - 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Four Seasons Private Residences Phase - 2 has 10 homes in 1 tower registered on MahaRERA, and 78% of them are sold or booked.
When was Four Seasons Private Residences Phase - 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Four Seasons Private Residences Phase - 2 was registered on MahaRERA on 25 August 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Four Seasons Private Residences Phase - 2?
No court cases are listed for Four Seasons Private Residences Phase - 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Four Seasons Private Residences Phase - 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Provenance Land Private Limited, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Four Seasons Private Residences Phase - 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400018
- Naman Xana
- WORLI HOUSE
- Sea Face
- Kalpataru One - Wing A
- SEA FACE HOUSE, WORLI
- Godrej Trilogy Seaturf
- Godrej Trilogy Seafront
- EMBASSY CITADEL
Other projects by Provenance Land Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.