Possession date of Raheja Solaris-1: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700030509, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Raheja Solaris-1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Raheja Solaris-1 has moved

  1. 30 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Raheja Solaris-1’s extension records on MahaRERA (P51700030509), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Raheja Solaris-1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700030509
Status
Registered and active
Builder
Raheja Universal (Pvt.) Ltd.
Location
TTC Industrial Area, Thane · 400705
Project type
Residential / Group Housing
Registered on
30 Aug 2021
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
432
Sold or booked
100%
Towers
2
Complaints on MahaRERA
4
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
17

Construction progress of Raheja Solaris-1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Raheja Solaris-1A100%100%90%40%
Raheja Solaris-1B100%100%60%10%

Commencement certificate (CC), as filed on MahaRERA

  • Raheja Solaris-1A: covers 30 floors
  • Raheja Solaris-1B: covers 31 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Raheja Solaris-1 every month.

Raheja Solaris-1: buildings, flats and land, as filed on MahaRERA

  • Buildings: Raheja Solaris-1A (30 floors, 196 units) · Raheja Solaris-1B (31 floors, 245 units)
  • Land: 2,23,309 sq m (about 55.2 acres) · sanctioned built-up 20,814 sq m

The builder’s record and reviews

Raheja Universal (a group of 2 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 2 finished, all within the promised date; 17 still being built, none past the promised date yet. 18 complaints on MahaRERA across 7 projects.

Read Google reviews of Raheja Solaris-1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Raheja Solaris-1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Raheja Solaris-1

What is the possession date of Raheja Solaris-1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Raheja Solaris-1 in TTC Industrial Area, Thane is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Raheja Solaris-1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Raheja Solaris-1's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Raheja Solaris-1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Raheja Solaris-1 in TTC Industrial Area, Thane is P51700030509.

Is Raheja Solaris-1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja Solaris-1 is registered as P51700030509 and its status is "Registered and active".

What is the construction status of Raheja Solaris-1?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja Solaris-1's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Raheja Solaris-1 have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Raheja Solaris-1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja Solaris-1 is registered on MahaRERA as P51700030509, its completion date has not been moved by the builder and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Raheja Solaris-1 have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Raheja Solaris-2 (P51700046184, possession 30 Apr 2028); Raheja Solaris-3 (P51700053551, possession 30 Apr 2029). Check that your agreement names the registration of your own wing.

How can I get updates if Raheja Solaris-1's possession date changes?

The latest dates are on Raheja Solaris-1's MahaRERA page (P51700030509). GharKundli's Kundli Watch sends a free WhatsApp update on Raheja Solaris-1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Raheja Solaris-1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja Solaris-1 has 2 buildings filed: Raheja Solaris-1A with 30 floors and 196 units; Raheja Solaris-1B with 31 floors and 245 units.

How big is the land of Raheja Solaris-1?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja Solaris-1 stands on 2,23,309 sq m of land (about 55.2 acres), with 20,814 sq m of sanctioned built-up area.

What is the track record of Raheja Solaris-1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja Universal (a group of 2 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 2 finished, all within the promised date; 17 still being built, none past the promised date yet. 18 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Raheja Solaris-1?

Google Maps has reviews of Raheja Solaris-1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Raheja Solaris-1?

Raheja Solaris-1 by Raheja Universal (Pvt.) Ltd. is in TTC Industrial Area, Thane (pincode 400705), near Sanpada, Maharashtra, and is registered on MahaRERA as P51700030509, per GharKundli's check of MahaRERA records.

How many homes are in Raheja Solaris-1?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja Solaris-1 has 432 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.

When was Raheja Solaris-1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja Solaris-1 was registered on MahaRERA on 30 August 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on Raheja Solaris-1?

No court cases are listed for Raheja Solaris-1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Raheja Solaris-1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Raheja Universal (Pvt.) Ltd., which has 17 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in TTC Industrial Area

All 61 projects in Sanpada (400705) →

Other projects by Raheja Universal (Pvt.) Ltd.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.