Riverwood Park Building No -1
by Shree Khidkaleshwar Property Developers Pvt. Ltd. · Sagarli , Dombivali East, Thane
Possession date of Riverwood Park Building No -1: 31 July 2027, moved from 31 December 2025 (15 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700032548, and currently active. Its completion date has moved from December 2025 to July 2027: 15 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Riverwood Park Building No -1?
GharKundli’s full report on Riverwood Park Building No -1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Riverwood Park Building No. 2P51700004997 · possession 30 Sep 2023
- Riverwood Park Building No -3P51700030195 · possession 30 Oct 2027
- Riverwood Park Building No. 4P51700004003 · possession 30 Oct 2023
- Riverwood Park Building No. 5P51700010819 · possession 6 Feb 2025
- MahaRERA registration
- P51700032548
- Status
- Registered and active
- Builder
- Shree Khidkaleshwar Property Developers Pvt. Ltd.
- Location
- Sagarli , Dombivali East, Thane · 421204
- Project type
- Residential / Group Housing
- Registered on
- 10 Jan 2022
- Completion date at registration
- December 2025
- Latest completion date
- July 2027
- Delay so far
- 15 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 170
- Sold or booked
- 82%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of Riverwood Park Building No -1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No - 1 | 100% | 81% | 45% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Building No - 1: covers 23 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Riverwood Park Building No -1 every month.
Riverwood Park Building No -1: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No - 1 (23 floors, 170 units)
- Land: 2,275 sq m (about 0.6 acres) · sanctioned built-up 10,830 sq m
The builder’s record and reviews
Shree Khidkaleshwar Property Developers has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 8 months); 2 still being built, 1 past the promised date (typically 6 months late). 2 complaints on MahaRERA across 2 projects.
Read Google reviews of Riverwood Park Building No -1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Riverwood Park Building No -1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Riverwood Park Building No -1
What is the possession date of Riverwood Park Building No -1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Riverwood Park Building No -1 in Sagarli , Dombivali East, Thane is 31 July 2027 — 15 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Riverwood Park Building No -1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Riverwood Park Building No -1's builder has filed on MahaRERA, the official one, is 31 July 2027, already 15 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Riverwood Park Building No -1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Riverwood Park Building No -1 in Sagarli , Dombivali East, Thane is P51700032548.
Is Riverwood Park Building No -1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Riverwood Park Building No -1 is registered as P51700032548 and its status is "Registered and active".
What is the construction status of Riverwood Park Building No -1?
According to GharKundli's check of MahaRERA records (updated October 2026), Riverwood Park Building No -1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building No - 1 is 81% done and internal work 45%. GharKundli's full report compares construction progress with the deadline.
Does Riverwood Park Building No -1 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Riverwood Park Building No -1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Riverwood Park Building No -1 is registered on MahaRERA as P51700032548, its completion date has moved 15 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Riverwood Park Building No -1 have other wings or phases?
Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: Riverwood Park Building No. 2 (P51700004997, possession 30 Sep 2023); Riverwood Park Building No -3 (P51700030195, possession 30 Oct 2027); Riverwood Park Building No. 4 (P51700004003, possession 30 Oct 2023); Riverwood Park Building No. 5 (P51700010819, possession 6 Feb 2025). Check that your agreement names the registration of your own wing.
How can I get updates if Riverwood Park Building No -1's possession date changes?
The latest dates are on Riverwood Park Building No -1's MahaRERA page (P51700032548). GharKundli's Kundli Watch sends a free WhatsApp update on Riverwood Park Building No -1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Riverwood Park Building No -1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Riverwood Park Building No -1 has one building filed: Building No - 1 with 23 floors and 170 units.
How big is the land of Riverwood Park Building No -1?
According to GharKundli's check of MahaRERA records (updated October 2026), Riverwood Park Building No -1 stands on 2,275 sq m of land (about 0.6 acres), with 10,830 sq m of sanctioned built-up area.
What is the track record of Riverwood Park Building No -1's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Khidkaleshwar Property Developers has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 8 months); 2 still being built, 1 past the promised date (typically 6 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Riverwood Park Building No -1?
Google Maps has reviews of Riverwood Park Building No -1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Riverwood Park Building No -1?
Riverwood Park Building No -1 by Shree Khidkaleshwar Property Developers Pvt. Ltd. is in Sagarli , Dombivali East, Thane (pincode 421204), Maharashtra, and is registered on MahaRERA as P51700032548, per GharKundli's check of MahaRERA records.
How many homes are in Riverwood Park Building No -1?
According to GharKundli's check of MahaRERA records (updated October 2026), Riverwood Park Building No -1 has 170 homes in 1 tower registered on MahaRERA, and 82% of them are sold or booked.
When was Riverwood Park Building No -1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Riverwood Park Building No -1 was registered on MahaRERA on 10 January 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Riverwood Park Building No -1?
No court cases are listed for Riverwood Park Building No -1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Riverwood Park Building No -1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree Khidkaleshwar Property Developers Pvt. Ltd., which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Riverwood Park Building No -1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
All projects in Manpada (421204) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.