NIDHI RESIDENCY
by ADITYA YASH BUILDERS · Chikhloli, Thane
Possession date of NIDHI RESIDENCY: 31 July 2027, moved from 31 March 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700045522, and currently active. Its completion date has moved from March 2026 to July 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about NIDHI RESIDENCY?
How the possession date of NIDHI RESIDENCY has moved
31 March 2026
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA08042620585)
Reason the builder gave MahaRERA:
“The project has reached 95% completion. The remaining scope of work primarily includes select internal finishing works, installation of lifts, water pumps, firefighting fittings and equipment in compliance with CFO NOC requirements, and ele…” Read the full reason
“The project has reached 95% completion. The remaining scope of work primarily includes select internal finishing works, installation of lifts, water pumps, firefighting fittings and equipment in compliance with CFO NOC requirements, and electrical fittings in the common areas. Statutory NOCs and related approvals are currently under process with the respective authorities. We request Authority to Grant us extension till 31-03-2027. We remain committed to timely completion in the interest of all stakeholder”31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: NIDHI RESIDENCY’s extension records on MahaRERA (P51700045522), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NIDHI RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700045522
- Status
- Registered and active
- Builder
- ADITYA YASH BUILDERS
- Location
- Chikhloli, Thane · 421505
- Project type
- Residential / Group Housing
- Registered on
- 24 May 2022
- Completion date at registration
- March 2026
- Latest completion date
- July 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 279
- Sold or booked
- 55%
- Towers
- 10
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of NIDHI RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A WING | 100% | 100% | 90% | 0% |
| B WING | 100% | 100% | 70% | 0% |
| C WING | 100% | 100% | 70% | 0% |
| D WING | 100% | 0% | 0% | 0% |
| E WING | 100% | 40% | 10% | 0% |
| G WING | 100% | 100% | 50% | 0% |
| I WING | 100% | 100% | 90% | 0% |
| F WING | 100% | 40% | 10% | 0% |
| H WING | 100% | 100% | 80% | 0% |
| J WING | 100% | 100% | 90% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- A WING: covers 8 floors
- B WING: covers 8 floors
- C WING: covers 8 floors
- D WING: covers 8 floors
- E WING: covers 8 floors
- G WING: covers 8 floors
- I WING: covers 5 floors
- F WING: covers 8 floors
- H WING: covers 8 floors
- J WING: covers 5 floors
Latest CC order on MahaRERA: dated 26/02/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIDHI RESIDENCY every month.
NIDHI RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: A WING (8 floors, 34 units) · B WING (8 floors, 54 units) · C WING (8 floors, 40 units) · D WING (8 floors, 28 units) · E WING (8 floors, 28 units) · G WING (8 floors, 49 units) · I WING (5 floors, 10 units) · F WING (8 floors, 28 units) · and 2 more
- Car parking: 138 covered
- Land: 5,200 sq m (about 1.3 acres) · sanctioned built-up 9,118 sq m · recreational space 520 sq m
- Boundaries filed include: KRUSHNA KUNJ COMPLEX
The builder’s record and reviews
Aditya Aanandi Associates (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 3 months late). No complaints on MahaRERA.
Read Google reviews of NIDHI RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NIDHI RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NIDHI RESIDENCY
What is the possession date of NIDHI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NIDHI RESIDENCY in Chikhloli, Thane is 31 July 2027 — 12 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for NIDHI RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NIDHI RESIDENCY's builder has filed on MahaRERA, the official one, is 31 July 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of NIDHI RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), NIDHI RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The project has reached 95% completion. The remaining scope of work primarily includes select internal finishing works, installation of lifts, water pumps, firefighting fittings and equipment in compliance with CFO NOC requirements, and electrical fittings in the common areas. Statutory NOCs and related approvals are currently under process with the respective authorities. We request Authority to Grant us extension till 31-03-2027. We remain committed to timely completion in the interest of all stakeholder". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of NIDHI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NIDHI RESIDENCY in Chikhloli, Thane is P51700045522.
Is NIDHI RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NIDHI RESIDENCY is registered as P51700045522 and its status is "Registered and active".
What is the construction status of NIDHI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), NIDHI RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 10 towers. GharKundli's full report compares construction progress with the deadline.
Does NIDHI RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is NIDHI RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), NIDHI RESIDENCY is registered on MahaRERA as P51700045522, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NIDHI RESIDENCY's possession date changes?
The latest dates are on NIDHI RESIDENCY's MahaRERA page (P51700045522). GharKundli's Kundli Watch sends a free WhatsApp update on NIDHI RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NIDHI RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), NIDHI RESIDENCY has 10 buildings filed: A WING with 8 floors and 34 units; B WING with 8 floors and 54 units; C WING with 8 floors and 40 units; D WING with 8 floors and 28 units; E WING with 8 floors and 28 units; G WING with 8 floors and 49 units; and 4 more.
How much parking does NIDHI RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 138 covered car parking spaces for NIDHI RESIDENCY.
How big is the land of NIDHI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), NIDHI RESIDENCY stands on 5,200 sq m of land (about 1.3 acres), with 9,118 sq m of sanctioned built-up area and 520 sq m of recreational open space.
What is the track record of NIDHI RESIDENCY's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Aanandi Associates (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 3 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of NIDHI RESIDENCY?
Google Maps has reviews of NIDHI RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NIDHI RESIDENCY?
NIDHI RESIDENCY by ADITYA YASH BUILDERS is in Chikhloli, Thane (pincode 421505), Maharashtra, and is registered on MahaRERA as P51700045522, per GharKundli's check of MahaRERA records. Its boundaries filed there include KRUSHNA KUNJ COMPLEX.
How many homes are in NIDHI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), NIDHI RESIDENCY has 279 homes in 10 towers registered on MahaRERA, and 55% of them are sold or booked.
When was NIDHI RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NIDHI RESIDENCY was registered on MahaRERA on 24 May 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on NIDHI RESIDENCY?
No court cases are listed for NIDHI RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of NIDHI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ADITYA YASH BUILDERS.
Check it yourself on MahaRERA
- How to check the possession date of NIDHI RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Chikhloli
- MIDTOWN B AND C WING
- NEELKANTH ROYALE PALMS - F WING PHASE II
- RUGI COLONIA
- MID-TOWN
- VASTU SIDDHI , PHASE II
- SARVODAY SQUARE PHASE 1 BLDG. NO. 3,4 AND 7
- SATYAM ELEGANZA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.