Nascon Inspire
by VIGHNAHARTA DEVELOPERS · Dombivli West, Thane
Registered on MahaRERA under P51700034385. Status: Lapsed (registration period ended). Its completion date has moved from December 2024 to December 2025, 12 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
GharKundli’s full report on Nascon Inspire
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700034385
- Status
- Lapsed (registration period ended)
- Builder
- VIGHNAHARTA DEVELOPERS
- Location
- Dombivli West, Thane · 421202
- Project type
- Others
- Registered on
- 5 Apr 2022
- Completion date at registration
- December 2024
- Latest completion date
- December 2025
- Delay so far
- 12 months
- Homes
- 15
- Sold or booked
- 64%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Kundli Watch
Nascon Inspire: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Nascon Inspire
Is Nascon Inspire registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nascon Inspire is registered as P51700034385 and its status is "Lapsed (registration period ended)".
Where is Nascon Inspire?
Nascon Inspire by VIGHNAHARTA DEVELOPERS is in Dombivli West, Thane (pincode 421202), Maharashtra, and is registered on MahaRERA as P51700034385, per GharKundli's check of MahaRERA records.
When is possession of Nascon Inspire due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nascon Inspire in Dombivli West, Thane is 31 December 2025 — 12 months later than 31 December 2024, the date given at registration. That date has already passed.
Does Nascon Inspire have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Nascon Inspire?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIGHNAHARTA DEVELOPERS, which has 7 other projects registered on MahaRERA.
Other projects in pincode 421202
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.