Lotus
by Shreem Reality · Mandvi, MumbaiAlso near Masjid Bunder, Dongri, Chinch Bunder
Possession date of Lotus: 14 June 2030, moved from 7 February 2028 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900077966, and currently active. Its completion date has moved from February 2028 to June 2030: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Lotus?
How the possession date of Lotus has moved
7 February 2028
Completion date given when the project was registered
14 February 2030
Extended at the builder's request (MahaRERA application EA17062621412)
Reason the builder gave MahaRERA:
“The delay in the completion of the project has occurred due to procurement issues, financial constraints, and various site-related challenges that have impacted the planned construction schedule. Delays in the procurement of materials and r…” Read the full reason
“The delay in the completion of the project has occurred due to procurement issues, financial constraints, and various site-related challenges that have impacted the planned construction schedule. Delays in the procurement of materials and resources, coupled with financial limitations, affected the timely execution of construction activities. Additionally, site-specific challenges and operational constraints resulted in slower progress of the ongoing works, thereby extending the overall project timeline. Despite these difficulties, the promoter has taken necessary measures to address the cha…”14 June 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Lotus’s extension records on MahaRERA (P51900077966), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Lotus
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900077966
- Status
- Registered and active
- Builder
- Shreem Reality
- Location
- Mandvi, Mumbai · 400003
- Project type
- Others
- Registered on
- 14 Nov 2024
- Completion date at registration
- February 2028
- Latest completion date
- June 2030
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 5
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Lotus, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Lotus | 90% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Lotus: covers 32 floors
Latest CC order on MahaRERA: dated 31/10/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lotus every month.
Lotus: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Shops | 53 – 2,105 | 113 |
| Office Space | 71 – 1,972 | 52 |
| Multi Purpose Room | 140 – 1,496 | 3 |
| 2 BHK | 613 – 834 | 2 |
| 1 BHK | 448 | 1 |
| 1 Room Kitchen | 301 | 1 |
- Buildings: Lotus (42 floors, 172 units)
- Car parking: 153 covered
- Land: 797 sq m (about 0.2 acres) · sanctioned built-up 9,618 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Lotus →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Lotus: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Lotus
What is the possession date of Lotus?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lotus in Mandvi, Mumbai is 14 June 2030 — 24 months later than 7 February 2028, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Lotus?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Lotus's builder has filed on MahaRERA, the official one, is 14 June 2030, already 24 months later than the 7 February 2028 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Lotus extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Lotus's builder applied to MahaRERA to extend the completion date once: to 14 February 2030, giving the reason "The delay in the completion of the project has occurred due to procurement issues, financial constraints, and various site-related challenges that have impacted the planned construction schedule. Delays in the procurement of materials and resources, coupled with financial limitations, affected the timely execution of construction activities. Additionally, site-specific challenges and operational constraints resulted in slower progress of the ongoing works, thereby extending the overall project timeline. Despite these difficulties, the promoter has taken necessary measures to address the cha…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Lotus?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lotus in Mandvi, Mumbai is P51900077966.
Is Lotus registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lotus is registered as P51900077966 and its status is "Registered and active".
What is the construction status of Lotus?
According to GharKundli's check of MahaRERA records (updated October 2026), Lotus's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Lotus is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Lotus have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Lotus safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Lotus is registered on MahaRERA as P51900077966, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Lotus's possession date changes?
The latest dates are on Lotus's MahaRERA page (P51900077966). GharKundli's Kundli Watch sends a free WhatsApp update on Lotus every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Lotus have?
According to GharKundli's check of MahaRERA records (updated October 2026), Lotus has one building filed: Lotus with 42 floors and 172 units.
What are the flat sizes (carpet area) in Lotus?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Lotus: 2 BHK: 613 to 834 sq ft carpet (2 homes); 1 BHK: 448 sq ft carpet (1 homes); 1 Room Kitchen: 301 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Lotus have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 153 covered car parking spaces for Lotus.
How big is the land of Lotus?
According to GharKundli's check of MahaRERA records (updated October 2026), Lotus stands on 797 sq m of land (about 0.2 acres), with 9,618 sq m of sanctioned built-up area.
Where can I read reviews of Lotus?
Google Maps has reviews of Lotus written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Lotus?
Lotus by Shreem Reality is in Mandvi, Mumbai (pincode 400003), near Masjid Bunder, Dongri, Chinch Bunder, Maharashtra, and is registered on MahaRERA as P51900077966, per GharKundli's check of MahaRERA records.
How many homes are in Lotus?
According to GharKundli's check of MahaRERA records (updated October 2026), Lotus has 5 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Lotus registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Lotus was registered on MahaRERA on 14 November 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on Lotus?
No court cases are listed for Lotus on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Lotus?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shreem Reality.
Check it yourself on MahaRERA
- How to check the possession date of Lotus
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai City →
Other projects in pincode 400003
- BURJ ASHRAFI
- NATHANI SQUARE
- Safiya Heights
- Nikhil Heights
- ESTA RANJIT HOUSE
- DULDUL HEIGHTS
- Ayesha Residency
- QAMAR E BANI HASHIM
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.