by A.PATNI REALTY PRIVATE LIMITED · Mohammed Ali Road, MumbaiAlso near Bhuleshwar, Girgaon, Masjid Bunder

Possession date of NATHANI SQUARE: 30 April 2027, moved from 30 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900010462, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about NATHANI SQUARE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NATHANI SQUARE has moved

  1. 30 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA11032620180)

    Reason the builder gave MahaRERA: “MHADA NOC TO O.C IS NOT YET GRANTED DUE TO WHICH BMC HAS NOT ISSUED O.C. FOR THE PROJECT”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: NATHANI SQUARE’s extension records on MahaRERA (P51900010462), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NATHANI SQUARE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900010462
Status
Registered and active
Builder
A.PATNI REALTY PRIVATE LIMITED
Location
Mohammed Ali Road, Mumbai · 400003
Project type
Others
Registered on
27 Aug 2017
Completion date at registration
December 2025
Latest completion date
April 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
163
Sold or booked
93%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of NATHANI SQUARE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NATHANI SQUARE100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • NATHANI SQUARE: covers 25 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NATHANI SQUARE every month.

NATHANI SQUARE: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK302 – 593138
2 BHK491 – 59325

The builder’s record and reviews

Nathani Parekh Constructions (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 42 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of NATHANI SQUARE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NATHANI SQUARE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NATHANI SQUARE

What is the possession date of NATHANI SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NATHANI SQUARE in Mohammed Ali Road, Mumbai is 30 April 2027 — 12 months later than 30 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for NATHANI SQUARE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NATHANI SQUARE's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NATHANI SQUARE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI SQUARE's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "MHADA NOC TO O.C IS NOT YET GRANTED DUE TO WHICH BMC HAS NOT ISSUED O.C. FOR THE PROJECT". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of NATHANI SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NATHANI SQUARE in Mohammed Ali Road, Mumbai is P51900010462.

Is NATHANI SQUARE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI SQUARE is registered as P51900010462 and its status is "Registered and active".

What is the construction status of NATHANI SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI SQUARE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NATHANI SQUARE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does NATHANI SQUARE have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is NATHANI SQUARE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI SQUARE is registered on MahaRERA as P51900010462, its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NATHANI SQUARE's possession date changes?

The latest dates are on NATHANI SQUARE's MahaRERA page (P51900010462). GharKundli's Kundli Watch sends a free WhatsApp update on NATHANI SQUARE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NATHANI SQUARE have?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI SQUARE has one building filed: NATHANI SQUARE with 27 floors and 163 units.

What are the flat sizes (carpet area) in NATHANI SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for NATHANI SQUARE: 1 BHK: 302 to 593 sq ft carpet (138 homes); 2 BHK: 491 to 593 sq ft carpet (25 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of NATHANI SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI SQUARE stands on 1,291 sq m of land (about 0.3 acres), with 10,428 sq m of sanctioned built-up area and 103 sq m of recreational open space.

What is the track record of NATHANI SQUARE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Nathani Parekh Constructions (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 42 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NATHANI SQUARE?

Google Maps has reviews of NATHANI SQUARE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NATHANI SQUARE?

NATHANI SQUARE by A.PATNI REALTY PRIVATE LIMITED is in Mohammed Ali Road, Mumbai (pincode 400003), near Bhuleshwar, Girgaon, Masjid Bunder, Maharashtra, and is registered on MahaRERA as P51900010462, per GharKundli's check of MahaRERA records.

How many homes are in NATHANI SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI SQUARE has 163 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.

When was NATHANI SQUARE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NATHANI SQUARE was registered on MahaRERA on 27 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on NATHANI SQUARE?

No court cases are listed for NATHANI SQUARE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of NATHANI SQUARE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is A.PATNI REALTY PRIVATE LIMITED.

All projects with possession due in 2027 in Mumbai City →

Other projects in Mumbai City

All 20 projects in Mandvi (400003) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.