Possession date of Harsh Oasis (MahaRERA PR1170002503005): 30 November 2029. It has 57 homes (1 BHK, 2 BHK and 3 BHK, 162–814 sq ft carpet), 7% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1170002503005, and currently active. Its completion date is now November 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1170002503005, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Harsh Oasis?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Harsh Oasis has moved

  1. 31 July 2029

    Completion date given when the project was registered

  2. 30 November 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Harsh Oasis’s extension records on MahaRERA (PR1170002503005), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Harsh Oasis

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1170002503005
Status
Registered and active
Builder
HARSH DEVELOPERS & INFRASTRUCTURE LLP
Location
Mahim West, Mumbai · 400016
Project type
Residential / Group Housing
Registered on
18 Mar 2026
Completion date at registration
July 2029
Latest completion date
November 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
57
Sold or booked
7%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Harsh Oasis, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Harsh Oasis60%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Harsh Oasis: covers Plinth

Latest CC order on MahaRERA: dated 20/01/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Harsh Oasis every 1–2 months.

Harsh Oasis: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK162 – 48231
2 BHK636 – 68020
3 BHK8146

The builder’s record and reviews

Harsh Developers & Infrastructure (a group of 2 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, all within the promised date; 3 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Harsh Oasis →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Harsh Oasis: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Harsh Oasis

What is the possession date of Harsh Oasis?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Harsh Oasis in Mahim West, Mumbai is 30 November 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Harsh Oasis?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Harsh Oasis's builder has filed on MahaRERA, the official one, is 30 November 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Harsh Oasis?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Harsh Oasis in Mahim West, Mumbai is PR1170002503005.

Is Harsh Oasis registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Harsh Oasis is registered as PR1170002503005 and its status is "Registered and active".

What is the current construction status of Harsh Oasis? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Harsh Oasis's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Harsh Oasis is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Harsh Oasis have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Harsh Oasis safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Harsh Oasis is registered on MahaRERA as PR1170002503005, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Harsh Oasis?

Harsh Oasis is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Harsh Oasis are 162 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Harsh Oasis?

For a flat in Harsh Oasis (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Harsh Oasis received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Harsh Oasis is still under construction, with 30 November 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Harsh Oasis a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Harsh Oasis is a redevelopment: 29 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Harsh Oasis uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Harsh Oasis was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Harsh Oasis's possession date changes?

The latest dates are on Harsh Oasis's MahaRERA page (PR1170002503005). GharKundli's Kundli Watch sends a free WhatsApp update on Harsh Oasis every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Harsh Oasis have?

According to GharKundli's check of MahaRERA records (updated October 2026), Harsh Oasis has one building filed: Harsh Oasis with 21 floors and 57 units.

What are the flat sizes (carpet area) in Harsh Oasis?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Harsh Oasis: 1 BHK: 162 to 482 sq ft carpet (31 homes); 2 BHK: 636 to 680 sq ft carpet (20 homes); 3 BHK: 814 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Harsh Oasis have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 65 covered car parking spaces for Harsh Oasis.

How big is the land of Harsh Oasis?

According to GharKundli's check of MahaRERA records (updated October 2026), Harsh Oasis stands on 607 sq m of land (about 0.2 acres), with 3,210 sq m of sanctioned built-up area.

What is the track record of Harsh Oasis's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Harsh Developers & Infrastructure (a group of 2 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, all within the promised date; 3 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Harsh Oasis?

Google Maps has reviews of Harsh Oasis written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Harsh Oasis?

Harsh Oasis by HARSH DEVELOPERS & INFRASTRUCTURE LLP is in Mahim West, Mumbai, pincode 400016 (near Dadar West, Shivaji Park, Matunga West), Maharashtra, and is registered on MahaRERA as PR1170002503005, per GharKundli's check of MahaRERA records. GharKundli lists all 84 MahaRERA projects in Mahim (400016).

How many flats are in Harsh Oasis, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Harsh Oasis has 57 homes in 1 tower registered on MahaRERA, and 7% of them are sold or booked.

When was Harsh Oasis registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Harsh Oasis was registered on MahaRERA on 18 March 2026. GharKundli did not find a title report on the land on file there.

Does Harsh Oasis have any legal issues or court cases?

No court cases are listed for Harsh Oasis on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Harsh Oasis?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HARSH DEVELOPERS & INFRASTRUCTURE LLP, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2029 in Mumbai City →

Other projects in Mahim (400016)

All 84 projects in Mahim (400016) →

Other projects by HARSH DEVELOPERS & INFRASTRUCTURE LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.