Harsh Crown
by HARSH DEVELOPERS & INFRASTRUCTURE LLP · Dadar West, Mumbai
Registered on MahaRERA under PR1170002502982, and currently active. Its completion date has moved from May 2029 to September 2029, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
- MahaRERA registration
- PR1170002502982
- Status
- Registered and active
- Builder
- HARSH DEVELOPERS & INFRASTRUCTURE LLP
- Location
- Dadar West, Mumbai · 400028
- Project type
- Residential / Group Housing
- Registered on
- 18 Mar 2026
- Completion date at registration
- May 2029
- Latest completion date
- September 2029
- Delay so far
- 4 months
- Homes
- 24
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
GharKundli’s full report on Harsh Crown
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Kundli Watch
Harsh Crown: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Harsh Crown
Is Harsh Crown registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Harsh Crown is registered as PR1170002502982 and its status is "Registered and active".
Where is Harsh Crown?
Harsh Crown by HARSH DEVELOPERS & INFRASTRUCTURE LLP is in Dadar West, Mumbai (pincode 400028), Maharashtra, and is registered on MahaRERA as PR1170002502982, per GharKundli's check of MahaRERA records.
When is possession of Harsh Crown due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Harsh Crown in Dadar West, Mumbai is 30 September 2029 — 4 months later than 31 May 2029, the date given at registration.
Does Harsh Crown have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Harsh Crown?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HARSH DEVELOPERS & INFRASTRUCTURE LLP, which has 4 other projects registered on MahaRERA.
Other projects in pincode 400028
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.