Ratan Address

by Shri Nakoda Enterprises · Dadar West, MumbaiAlso near Prabhadevi, Shivaji Park, Mahim

Possession date of Ratan Address: 30 January 2027, moved from 30 April 2024 (29 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900032985, and currently active. Its completion date has moved from April 2024 to January 2027: 29 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Ratan Address?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Ratan Address has moved

  1. 30 April 2024

    Completion date given when the project was registered

  2. 30 April 2025

    Extended at the builder's request (MahaRERA application EXT51900018501)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”
  3. 31 October 2025

    Extended at the builder's request (MahaRERA application EXT51900027833)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 54.55% allottees for purpose of extension of RERA registration period of the said project.”
  4. 31 March 2026

    Extended at the builder's request (MahaRERA application EA31102518208)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.”
  5. 30 September 2026

    Extended at the builder's request (MahaRERA application EA04062621229)

    Reason the builder gave MahaRERA:
    “Due to unforeseen site conditions and coordination challenges, the progress of internal plastering work across multiple units has been delayed. The completion of internal plumbing work was also affected due to material supply disruptions an…” Read the full reason“Due to unforeseen site conditions and coordination challenges, the progress of internal plastering work across multiple units has been delayed. The completion of internal plumbing work was also affected due to material supply disruptions and workforce constraints, which consequently impacted the finishing stages of the project. Further, the process of obtaining the Occupancy Certificate (OC) has been prolonged due to pending inspections and approvals from the concerned authorities. In view of the above, we kindly request an extension for project completion until 30-09-2026.”
  6. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ratan Address’s extension records on MahaRERA (P51900032985), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ratan Address

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900032985
Status
Registered and active
Builder
Shri Nakoda Enterprises
Location
Dadar West, Mumbai · 400028
Project type
Others
Registered on
2 Feb 2022
Completion date at registration
April 2024
Latest completion date
January 2027
Delay so far
29 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
125
Sold or booked
56%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Ratan Address, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A Wing and B Wing100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • A Wing and B Wing: covers 23 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ratan Address every month.

Ratan Address: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK395 – 77959
1 BHK316 – 75537
3 BHK471 – 99529
Shops158 – 44612
Office Space169 – 4596
  • Buildings: A Wing and B Wing (23 floors, 143 units)
  • Land: 1,656 sq m (about 0.4 acres) · sanctioned built-up 6,584 sq m · recreational space 127 sq m
  • Boundaries filed include: S K Bole Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Shri Nakoda Enterprises (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 2 past the promised date (typically 52 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Ratan Address →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ratan Address: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Ratan Address

What is the possession date of Ratan Address?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ratan Address in Dadar West, Mumbai is 30 January 2027 — 29 months later than 30 April 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Ratan Address?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ratan Address's builder has filed on MahaRERA, the official one, is 30 January 2027, already 29 months later than the 30 April 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ratan Address extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Ratan Address's builder applied to MahaRERA to extend the completion date 4 times: to 30 April 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 31 October 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 54.55% allottees for purpose of extension of RERA registration period of the said project."; to 31 March 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work."; to 30 September 2026, giving the reason "Due to unforeseen site conditions and coordination challenges, the progress of internal plastering work across multiple units has been delayed. The completion of internal plumbing work was also affected due to material supply disruptions and workforce constraints, which consequently impacted the finishing stages of the project. Further, the process of obtaining the Occupancy Certificate (OC) has been prolonged due to pending inspections and approvals from the concerned authorities. In view of the above, we kindly request an extension for project completion until 30-09-2026.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Ratan Address?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ratan Address in Dadar West, Mumbai is P51900032985.

Is Ratan Address registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ratan Address is registered as P51900032985 and its status is "Registered and active".

What is the construction status of Ratan Address?

According to GharKundli's check of MahaRERA records (updated October 2026), Ratan Address's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A Wing and B Wing is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Ratan Address have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Ratan Address safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ratan Address is registered on MahaRERA as P51900032985, its completion date has moved 29 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Ratan Address's possession date changes?

The latest dates are on Ratan Address's MahaRERA page (P51900032985). GharKundli's Kundli Watch sends a free WhatsApp update on Ratan Address every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ratan Address have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ratan Address has one building filed: A Wing and B Wing with 23 floors and 143 units.

What are the flat sizes (carpet area) in Ratan Address?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ratan Address: 2 BHK: 395 to 779 sq ft carpet (59 homes); 1 BHK: 316 to 755 sq ft carpet (37 homes); 3 BHK: 471 to 995 sq ft carpet (29 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Ratan Address?

According to GharKundli's check of MahaRERA records (updated October 2026), Ratan Address stands on 1,656 sq m of land (about 0.4 acres), with 6,584 sq m of sanctioned built-up area and 127 sq m of recreational open space.

What is the track record of Ratan Address's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Nakoda Enterprises (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 2 past the promised date (typically 52 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Ratan Address?

Google Maps has reviews of Ratan Address written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Ratan Address?

Ratan Address by Shri Nakoda Enterprises is in Dadar West, Mumbai (pincode 400028), near Prabhadevi, Shivaji Park, Mahim, Maharashtra, and is registered on MahaRERA as P51900032985, per GharKundli's check of MahaRERA records. Its boundaries filed there include S K Bole Road.

How many homes are in Ratan Address?

According to GharKundli's check of MahaRERA records (updated October 2026), Ratan Address has 125 homes in 1 tower registered on MahaRERA, and 56% of them are sold or booked.

When was Ratan Address registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ratan Address was registered on MahaRERA on 2 February 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Ratan Address?

No court cases are listed for Ratan Address on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Ratan Address?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shri Nakoda Enterprises, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai City →

Other projects in Dadar West

All 148 projects in Dadar West (400028) →

Other projects by Shri Nakoda Enterprises

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.