Kohinoor Square Phase 1
by Kohinoor CTNL Infrastructure Company Private Limited · Dadar West, MumbaiAlso near Shivaji Park, Mahim, Matunga
Possession date of Kohinoor Square Phase 1: 31 December 2025, moved from 30 December 2022 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900004769. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Kohinoor Square Phase 1?
How the possession date of Kohinoor Square Phase 1 has moved
30 December 2022
Completion date given when the project was registered
10 September 2023
Extended at the builder's request (MahaRERA application EXT51900013029)
Reason the builder gave MahaRERA:
“(1) While developing the Project Kohinoor Square Phase 1 consist of Wing A, Wing B and Basement (“said Project”), the Corporate Insolvency Resolution Process (CIRP) was initiated by the secured creditors against the Promoter before the Nati…” Read the full reason
“(1) While developing the Project Kohinoor Square Phase 1 consist of Wing A, Wing B and Basement (“said Project”), the Corporate Insolvency Resolution Process (CIRP) was initiated by the secured creditors against the Promoter before the National Company Law Tribunal, Mumbai Bench (NCLT); (2) The NCLT by its Order dated 21/02/2018 approved the resolution plan in respect of the Promoter and the said Project was restarted. In view of the said CIRP process, the said Project was delayed, however, the Promoter completed construction of the buildings before Project completion date; (3) The Promoter…”31 December 2025
Extended at the builder's request (MahaRERA application EXT51900025428)
Reason the builder gave MahaRERA:
“Full occupation certificate for 3 basements, A- Wing and C – Wing and full occupation certificate upto 47th floor and part 48th floor is obtained for Wing B. The possession of all the units/ flats is already handed over to the respective pu…” Read the full reason
“Full occupation certificate for 3 basements, A- Wing and C – Wing and full occupation certificate upto 47th floor and part 48th floor is obtained for Wing B. The possession of all the units/ flats is already handed over to the respective purchasers. The 48th floor is purchased by Kohinoor Elite Hotels Pvt. Ltd. and the possession of part 48th floor for which occupation certificate is obtained is handed over to Kohinoor Elite Hotels Pvt. Ltd. The construction of the balance part of 48th floor only is under progress as per the requirements of the purchaser and approval of the competent author…”
Source: Kohinoor Square Phase 1’s extension records on MahaRERA (P51900004769), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kohinoor Square Phase 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 7 court cases, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Kohinoor Square Phase 2P51900012308 · possession 30 Dec 2023
- MahaRERA registration
- P51900004769
- Status
- Lapsed (registration period ended)
- Builder
- Kohinoor CTNL Infrastructure Company Private Limited
- Location
- Dadar West, Mumbai · 400028
- Project type
- Commercial
- Registered on
- 9 Aug 2017
- Completion date at registration
- December 2022
- Latest completion date
- December 2025
- Delay so far
- 36 months
- Homes
- 0
- Sold or booked
- 100%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 7
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Kohinoor Square Phase 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A Comprising of Offices, IT, ITES, Shops and PPL in Basement | 100% | 98% | 100% | 99% |
| Wing B Comprising of Offices, IT, ITES, Hotel,Shops and PPL in Basement | 100% | 98% | 100% | 99% |
Commencement certificate (CC), as filed on MahaRERA
- Wing A Comprising of Offices, IT, ITES, Shops and PPL in Basement: covers 9 floors
- Wing B Comprising of Offices, IT, ITES, Hotel,Shops and PPL in Basement: covers 53 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kohinoor Square Phase 1 every month.
Kohinoor Square Phase 1: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 759 – 17,239 | 183 |
| Other | 152 – 18,061 | 16 |
- Buildings: Wing A Comprising of Offices, IT, ITES, Shops and PPL in Basement (11 floors, 18 units) · Wing B Comprising of Offices, IT, ITES, Hotel,Shops and PPL in Basement (53 floors, 181 units)
- Land: 11,718 sq m (about 2.9 acres) · sanctioned built-up 58,483 sq m · recreational space 2,536 sq m
- Boundaries filed include: Padmabai Thakkar Road, N C Kelkar Marg, Lady Jamshedji Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Kohinoor Ctnl Infrastructure has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, all within the promised date. 3 complaints on MahaRERA across 2 projects.
Read Google reviews of Kohinoor Square Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kohinoor Square Phase 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Kohinoor Square Phase 1
What is the possession date of Kohinoor Square Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kohinoor Square Phase 1 in Dadar West, Mumbai is 31 December 2025 — 36 months later than 30 December 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Kohinoor Square Phase 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kohinoor Square Phase 1's builder has filed on MahaRERA, the official one, is 31 December 2025, already 36 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kohinoor Square Phase 1 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Kohinoor Square Phase 1's builder applied to MahaRERA to extend the completion date 2 times: to 10 September 2023, giving the reason "(1) While developing the Project Kohinoor Square Phase 1 consist of Wing A, Wing B and Basement (“said Project”), the Corporate Insolvency Resolution Process (CIRP) was initiated by the secured creditors against the Promoter before the National Company Law Tribunal, Mumbai Bench (NCLT); (2) The NCLT by its Order dated 21/02/2018 approved the resolution plan in respect of the Promoter and the said Project was restarted. In view of the said CIRP process, the said Project was delayed, however, the Promoter completed construction of the buildings before Project completion date; (3) The Promoter…"; to 31 December 2025, giving the reason "Full occupation certificate for 3 basements, A- Wing and C – Wing and full occupation certificate upto 47th floor and part 48th floor is obtained for Wing B. The possession of all the units/ flats is already handed over to the respective purchasers. The 48th floor is purchased by Kohinoor Elite Hotels Pvt. Ltd. and the possession of part 48th floor for which occupation certificate is obtained is handed over to Kohinoor Elite Hotels Pvt. Ltd. The construction of the balance part of 48th floor only is under progress as per the requirements of the purchaser and approval of the competent author…".
What is the RERA number of Kohinoor Square Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kohinoor Square Phase 1 in Dadar West, Mumbai is P51900004769.
Is Kohinoor Square Phase 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kohinoor Square Phase 1 is registered as P51900004769 and its status is "Lapsed (registration period ended)".
What is the construction status of Kohinoor Square Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Kohinoor Square Phase 1's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 98% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Kohinoor Square Phase 1 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Kohinoor Square Phase 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kohinoor Square Phase 1 is registered on MahaRERA as P51900004769, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Kohinoor Square Phase 1 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Kohinoor Square Phase 2 (P51900012308, possession 30 Dec 2023). Check that your agreement names the registration of your own wing.
How can I get updates if Kohinoor Square Phase 1's possession date changes?
The latest dates are on Kohinoor Square Phase 1's MahaRERA page (P51900004769). GharKundli's Kundli Watch sends a free WhatsApp update on Kohinoor Square Phase 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kohinoor Square Phase 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kohinoor Square Phase 1 has 2 buildings filed: Wing A Comprising of Offices, IT, ITES, Shops and PPL in Basement with 11 floors and 18 units; Wing B Comprising of Offices, IT, ITES, Hotel,Shops and PPL in Basement with 53 floors and 181 units.
How big is the land of Kohinoor Square Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Kohinoor Square Phase 1 stands on 11,718 sq m of land (about 2.9 acres), with 58,483 sq m of sanctioned built-up area and 2,536 sq m of recreational open space.
What is the track record of Kohinoor Square Phase 1's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Kohinoor Ctnl Infrastructure has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, all within the promised date. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Kohinoor Square Phase 1?
Google Maps has reviews of Kohinoor Square Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Kohinoor Square Phase 1?
Kohinoor Square Phase 1 by Kohinoor CTNL Infrastructure Company Private Limited is in Dadar West, Mumbai (pincode 400028), near Shivaji Park, Mahim, Matunga, Maharashtra, and is registered on MahaRERA as P51900004769, per GharKundli's check of MahaRERA records. Its boundaries filed there include Padmabai Thakkar Road, N C Kelkar Marg, Lady Jamshedji Road.
How many homes are in Kohinoor Square Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Kohinoor Square Phase 1 has 0 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.
When was Kohinoor Square Phase 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kohinoor Square Phase 1 was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Kohinoor Square Phase 1?
7 court cases are listed for Kohinoor Square Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Kohinoor Square Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kohinoor CTNL Infrastructure Company Private Limited, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Kohinoor Square Phase 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Dadar West
- Ratan Address
- Adityaraj Midtown
- Emmanuel
- Avhad Oasis
- OCEANA
- San Petros Residency
- Harsh Crown
- Yashwant Heights
Other projects by Kohinoor CTNL Infrastructure Company Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.