Possession due in 2029 · Mumbai City
According to GharKundli's check of MahaRERA records, 92 housing projects in Mumbai City have a MahaRERA completion date in 2029, out of 634 Mumbai City projects GharKundli has read in detail so far.
The date is the latest completion date the builder has filed on MahaRERA, including MahaRERA’s automatic 4-month extension of August 2026 where it applies. “First promised” is the date given at registration. Completed projects are not listed. Open a project for its full MahaRERA record.
| Project | Where | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| Avyukta Imperial ROOPVENTURES LLP | Matunga | 30 Jan 2029 | 30 Sep 2028 | 0 |
| EVANA HEIGHTS GBD INFRA PROJECT LLP | Parel | 30 Jan 2029 | 30 Sep 2028 | 0 |
| RAHEJA AMALTIS - WING A K RAHEJA CORP REAL ESTATE PRIVATE LIMITED | Sion West | 30 Jan 2029 | 30 Sep 2028 | 0 |
| RAHEJA AMALTIS - WING B K RAHEJA CORP REAL ESTATE PRIVATE LIMITED | Sion West | 30 Jan 2029 | 30 Sep 2028 | 0 |
| RAHEJA MODERN VIVAREA SOUTH TOWER K RAHEJA CORP REAL ESTATE PRIVATE LIMITED | Mahalaxmi | 30 Jan 2029 | 30 Sep 2028 | 1 |
| RUNWAL TIMELESS RUNWAL DEVELOPERS LIMITED | Sion East | 30 Jan 2029 | 30 Sep 2026 | 10 |
| The Gateway LH Residential Housing Private Limited | Parel Sewree | 30 Jan 2029 | 30 Sep 2028 | 1 |
| THE PINNACLE RATNARAJ BLESSING MILESTONE LLP | Currey Road | 30 Jan 2029 | 30 Sep 2028 | 0 |
| TULSI HERITAGE BLUE STONE DEVELOPERS LLP | Dadar Mumbai | 30 Jan 2029 | 30 Sep 2028 | 0 |
| La Belleza Qaswa Enterprises | Bhuleshwar Division | 28 Feb 2029 | 28 Oct 2028 | 0 |
| REHMAT PARK Oriental Contractors Private Limited | Bhuleshwar C Ward | 28 Feb 2029 | 31 Oct 2028 | 0 |
| Shree Krishnakunj Sugee Developers Private Limited | Shivaji Park | 30 Mar 2029 | 30 Nov 2028 | 1 |
| Matunga Wing B Lodha Developers Limited | Sion | 31 Mar 2029 | same | 0 |
| Queen’s Corner Prathmeshwara Lifespaces LLP | Mahim | 15 Apr 2029 | 15 Dec 2028 | 0 |
| Greenstone Heritage - Wing - I Beauty Lifestyles and Homes Pvt. Ltd. | Near Crawford Market | 28 Apr 2029 | 28 Dec 2028 | 0 |
| Anzar Residency MITHILA DEVELOPERS | Mumbai Central | 30 Apr 2029 | 30 Dec 2021 | 1 |
| Aplite Sapphire Aplite Developers LLP | Tardeo | 30 Apr 2029 | 31 Dec 2028 | 0 |
| AQUA BAY CHAMUNDA INFRASTRUCTURE LIMITED | Near Metropolitan Magistrate Court Sewri | 30 Apr 2029 | 31 Dec 2028 | 0 |
| Arihant Amara Sky Arihant Infrastructure Company | Sion-Chunabhatti | 30 Apr 2029 | 31 Dec 2028 | 0 |
| Atlas Residency A and B Atlas Infratech Pvt.Ltd | Lower Parel,Chinchpokhli West | 30 Apr 2029 | 31 Dec 2028 | 0 |
| AVENUE 18 Shree Divyakirti Constructions LLP | Dadar Naigaon Division | 30 Apr 2029 | 31 Dec 2028 | 0 |
| CHHADVA IRIS SHEELA KHERAJ CHHADVA | Dadar West | 30 Apr 2029 | 31 Dec 2028 | 0 |
| Classic Heights Classic Enterprises | E Ward | 30 Apr 2029 | 31 Dec 2028 | 0 |
| DARSHAN AURA DARSHAN SKY HIGH CONSTRUCTIONS LLP | Ghodapdeo | 30 Apr 2029 | 31 Dec 2028 | 0 |
| Darshan Inara Darshan Legacy Builders LLP | Prabhadevi | 30 Apr 2029 | 31 Dec 2028 | 0 |
| DNS PRASHAM DNS Constructions Private Limited | Sion | 30 Apr 2029 | 31 Dec 2028 | 0 |
| DREAM RESIDENCY CINE PROPERTIES & FINANCE PVT LTD. | Girgaum Mumbai | 30 Apr 2029 | 31 Dec 2028 | 0 |
| EKTA VISTABELLA EKTA SHELTERS PRIVATE LIMITED | Dadar Matunga | 30 Apr 2029 | 31 Dec 2028 | 0 |
| GANESH NIKETAN AMEYA MADHU DEVELOPERS | Shivaji Park Dadar West | 30 Apr 2029 | 31 Dec 2028 | 0 |
| Hira House Goshar Alliance LLP | Matunga East | 30 Apr 2029 | 31 Dec 2028 | 0 |
| Infinity Residences Infinity Associates | Kala Chowky | 30 Apr 2029 | 31 Dec 2028 | 1 |
| Island Cove LH Residential Housing Private Limited | Mahim | 30 Apr 2029 | 31 Aug 2028 | 2 |
| KGN RESIDENCY KGN DEVELOPERS | Mumbai Central | 30 Apr 2029 | 31 Dec 2028 | 0 |
| MARIANA HEIGHTS K SABA BUILDERS & DEVELOPERS | Wadala East | 30 Apr 2029 | 23 Feb 2023 | 0 |
| NAJAMAI MANSION NAVROZE ENTERPRISES | Dadar East | 30 Apr 2029 | 31 Dec 2028 | 0 |
| NIRBAN AVENUE 1 NIRBAN HOUSING AND DEVELOPMENT LLP | Parel | 30 Apr 2029 | 31 Dec 2028 | 0 |
| OLYMPIA TOWER OLYMPIA ENTERPRISES | Byculla | 30 Apr 2029 | 31 Dec 2025 | 0 |
| ONE INDIA HEIGHTS ONEINDIA CONSTRUCTION LLP | Madanpura | 30 Apr 2029 | 30 Apr 2024 | 0 |
| One Marina VALENCIA AND MISHAL VENTURES PVT LTD | Chira Bazar Chandanwadi | 30 Apr 2029 | 30 Dec 2028 | 1 |
| Opulence by Neo Neo Builders and Developers | Girgaon | 30 Apr 2029 | 31 Dec 2028 | 0 |
| PARK VIEW RESIDENCY SHAGUN INFRASTRUCTURE | Shivaji Park, Dadar | 30 Apr 2029 | 31 Dec 2028 | 0 |
| Pearl Elegance Pearl Concept Realty LLP | Mahim | 30 Apr 2029 | 31 Dec 2028 | 0 |
| PROMONT Sheth Smarthomes LLP | Chunabhatti East | 30 Apr 2029 | 31 Dec 2028 | 3 |
| QAMAR E BANI HASHIM COMMERCIAL DEVELOPERS | B Ward | 30 Apr 2029 | 31 Dec 2028 | 0 |
| Ram Setu Bhavan GBD INFRACON LLP | Matunga Division,Dadar East | 30 Apr 2029 | 31 Dec 2028 | 0 |
| RAUNAK CENTRUM - A Raunak Jigna Associates | Rahul Nagar, Everald Nagar, Sion | 30 Apr 2029 | 31 Dec 2028 | 5 |
| S3 Epitome S3 Smart Spaces Private Limited | Lower Parel | 30 Apr 2029 | 31 Dec 2028 | 0 |
| SAFFRON BUILDARCH - GP | Dadar West | 30 Apr 2029 | 31 Dec 2028 | 0 |
| SANGHVI PARSSSVA ETERNITY SANGHVI PARSSSVA ENTERPRISE LLP | Girgaon | 30 Apr 2029 | 30 Jun 2026 | 0 |
| Shakuntala Sadan D R Developers | Bhuleshwar | 30 Apr 2029 | 31 Dec 2028 | 0 |
| SIDDHGIRI BAF NA PROPERTIES LLP | Matunga, Dadar | 30 Apr 2029 | 31 Dec 2028 | 0 |
| SUNSTONE EPITOME SUNSTONE CONSTRUCTIONS | Sion | 30 Apr 2029 | 31 Dec 2028 | 0 |
| VARDHMAN ALTURA VARDHMAN GROUP REALBUILD LLP | Girgaon | 30 Apr 2029 | 31 Dec 2028 | 0 |
| WORLI HOUSE HARBOUR FRONT PROPERTIES PRIVATE LIMITED | Worli | 30 Apr 2029 | 31 Dec 2028 | 0 |
| ZEN 16 GOODWILL INFRASTRUCTURE LLP | Mahim West | 30 Apr 2029 | 31 Dec 2028 | 0 |
| SHREEJI ONE DIVINE DIVINE GANESHA ESTATE LLP | Mahim | 17 Jun 2029 | 17 Feb 2029 | 0 |
| Sea Face Lodha Developers Limited | Worli | 28 Jun 2029 | 28 Feb 2029 | 0 |
| AURUM GIRNAR Aurum Girnar Private Limited | Malabar Hill Cumbala Hill Division | 30 Jun 2029 | same | 0 |
| Godrej Horizon Phase II Godrej Projects Development Ltd | Wadala | 30 Jun 2029 | same | 2 |
| Aakasa Shivaji Park GFT Realtors LLP | G North Ward | 31 Jul 2029 | 31 Mar 2029 | 0 |
| AL-MADINA CHS AR GROUP REALTY | Byculla | 31 Jul 2029 | 31 Mar 2029 | 0 |
| AMARIS SUITES C.M.GANDHI VENTURES | Matunga | 31 Jul 2029 | 31 Mar 2029 | 0 |
| Birla Anayu Birla Estates Private Limited | Malabar Hill | 31 Jul 2029 | 31 Mar 2029 | 0 |
| Birla Niyaara Phase-2 Aditya Birla Real Estate Limited | Worli | 31 Jul 2029 | 31 Mar 2029 | 0 |
| MANIKYA ARYAMAN ENTERPRISES | Mahim West | 31 Jul 2029 | 31 Mar 2029 | 0 |
| Ratan Elite Shri Nakoda Enterprises | Sion East | 31 Jul 2029 | 31 Mar 2029 | 0 |
| The Altitude VDV Infrastructures LLP | Tardeo | 31 Jul 2029 | 31 Mar 2029 | 2 |
| Veer Square Dadar P D Associates | Dadar West | 31 Jul 2029 | 31 Mar 2029 | 0 |
| THE REDEVELOPMENT OF KIRTI MANDIR CHSL PRANAV CONSTRUCTIONS LIMITED | Goregaon West | 3 Aug 2029 | 3 Apr 2029 | 0 |
| Harsh Aurum HARSH DEVELOPERS & INFRASTRUCTURE LLP | Dadar West | 30 Aug 2029 | 30 Apr 2029 | 0 |
| RAJKAMAL JEWEL SUBHAM COMMERCIAL ENTERPRISES PVT LTD | Mumbai Central | 1 Sep 2029 | same | 0 |
| Amaresha Inconel Developers & Builders Private Limited | Shivaji Park | 30 Sep 2029 | 31 May 2026 | 0 |
| Aurum Endeavour Ashok Johaan Realty LLP | Wadala West | 30 Sep 2029 | 31 May 2029 | 0 |
| Harsh Crown HARSH DEVELOPERS & INFRASTRUCTURE LLP | Dadar West | 30 Sep 2029 | 31 May 2029 | 0 |
| Sky 9 Mitani Realtors LLP | Girgaon | 30 Sep 2029 | 31 May 2029 | 0 |
| 41 GRANDSTAND RAMESH BUILDERS | Matunga | 30 Oct 2029 | 30 Jun 2029 | 0 |
| CODE 137 PRAMEYA DEVELOPERS | Mahim West | 30 Oct 2029 | 30 Jun 2029 | 1 |
| Kinjal Legacy Hi Rock Construction Private Limited | Tardeo-Malabar Hill | 30 Oct 2029 | 30 Jun 2029 | 0 |
| MADHOOR AURUM MADHOOR BUILDWELL PRIVATE LIMITED | Dadar | 30 Oct 2029 | 30 Jun 2029 | 0 |
| RUSTOMJEE 180 BAYVIEW MATUNGA W - WING B RAJ DOSHI EXPORTS PRIVATE LIMITED | Matunga West | 30 Oct 2029 | 30 Jun 2029 | 0 |
| Shree Niwas Endemic Properties LLP | Matunga | 30 Oct 2029 | 30 Jun 2029 | 0 |
| AJMAL-235 AWFI REAL ESTATE PRIVATE LIMITED | Nagpada | 30 Nov 2029 | 31 Jul 2029 | 0 |
| Harsh Oasis HARSH DEVELOPERS & INFRASTRUCTURE LLP | Mahim West | 30 Nov 2029 | 31 Jul 2029 | 0 |
| OM BUILDING CO-OPERATIVE HOUSING SOCIETY LIMITED AANSH BUILDCON | Brahmanwada | 30 Nov 2029 | same | 0 |
| Prodigy One PRODIGY REALTY LLP | Matunga | 30 Nov 2029 | 31 Jul 2029 | 0 |
| BELLWETHER CASCADE BELLWETHER REALTY LLP | Matunga | 31 Dec 2029 | same | 0 |
| DIPTI OPAL BAY DIPTI ASSOCIATES | Dadar West | 31 Dec 2029 | same | 1 |
| Godrej Avenue Eleven - Tower B GODREJ RESIDENCY PRIVATE LIMITED | Mumbai Central | 31 Dec 2029 | 30 Dec 2023 | 6 |
| KINGS HILL VIEW KINGS BUILDERS AND DEVELOPERS (I) PRIVATE LIMITED | Sion | 31 Dec 2029 | same | 0 |
| MAARIA ANNEXE LAKADAWALA DEVELOPERS PVT LTD | Mazgaon | 31 Dec 2029 | 31 Jan 2021 | 1 |
| MORAJ OPULENCE MORAJ AHN DEVELOPERS LLP | Mahim | 31 Dec 2029 | 28 Dec 2026 | 1 |
| Sugee Vrundavan Sugee Developers Private Limited | Mahim | 31 Dec 2029 | same | 0 |
Other years in Mumbai City: 2026 (43) · 2027 (136) · 2028 (87) · 2030 (64) · 2031 (45)
Source: GharKundli’s check of MahaRERA records. More projects appear as GharKundli reads them.