Infinity Residences
by Infinity Associates · Kala Chowky, MumbaiAlso near Parel, Lalbaug, Kalanagar, Bandra East
Possession date of Infinity Residences: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900030602, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Infinity Residences?
How the possession date of Infinity Residences has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Infinity Residences’s extension records on MahaRERA (P51900030602), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Infinity Residences
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 2 court cases, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900030602
- Status
- Registered and active
- Builder
- Infinity Associates
- Location
- Kala Chowky, Mumbai · 400033
- Project type
- Residential / Group Housing
- Registered on
- 1 Sep 2021
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 213
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Infinity Residences, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Infinity Residences | 100% | 71% | 30% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Infinity Residences every month.
Infinity Residences: buildings, flats and land, as filed on MahaRERA
- Buildings: Infinity Residences (40 floors)
- Land: 6,440 sq m (about 1.6 acres) · sanctioned built-up 24,831 sq m · recreational space 243 sq m
- Boundaries filed include: G D Ambedkar Marg
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Infinity Associates (a group of 2 linked companies) has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 6 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Infinity Residences →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Infinity Residences: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Infinity Residences
What is the possession date of Infinity Residences?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Infinity Residences in Kala Chowky, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Infinity Residences?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Infinity Residences's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Infinity Residences?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Infinity Residences in Kala Chowky, Mumbai is P51900030602.
Is Infinity Residences registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Infinity Residences is registered as P51900030602 and its status is "Registered and active".
What is the construction status of Infinity Residences?
According to GharKundli's check of MahaRERA records (updated October 2026), Infinity Residences's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Infinity Residences is 71% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.
Does Infinity Residences have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Infinity Residences safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Infinity Residences is registered on MahaRERA as P51900030602, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Infinity Residences's possession date changes?
The latest dates are on Infinity Residences's MahaRERA page (P51900030602). GharKundli's Kundli Watch sends a free WhatsApp update on Infinity Residences every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Infinity Residences have?
According to GharKundli's check of MahaRERA records (updated October 2026), Infinity Residences has one building filed: Infinity Residences with 40 floors.
How big is the land of Infinity Residences?
According to GharKundli's check of MahaRERA records (updated October 2026), Infinity Residences stands on 6,440 sq m of land (about 1.6 acres), with 24,831 sq m of sanctioned built-up area and 243 sq m of recreational open space.
What is the track record of Infinity Residences's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Infinity Associates (a group of 2 linked companies) has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 6 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Infinity Residences?
Google Maps has reviews of Infinity Residences written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Infinity Residences?
Infinity Residences by Infinity Associates is in Kala Chowky, Mumbai (pincode 400033), near Parel, Lalbaug, Kalanagar, Bandra East, Maharashtra, and is registered on MahaRERA as P51900030602, per GharKundli's check of MahaRERA records. Its boundaries filed there include G D Ambedkar Marg.
How many homes are in Infinity Residences?
According to GharKundli's check of MahaRERA records (updated October 2026), Infinity Residences has 213 homes in 1 tower registered on MahaRERA.
When was Infinity Residences registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Infinity Residences was registered on MahaRERA on 1 September 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Infinity Residences?
2 court cases are listed for Infinity Residences on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Infinity Residences?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Infinity Associates, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Infinity Residences
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai City →
Other projects in pincode 400033
All 17 projects in Mazgaon (400033) →Other projects by Infinity Associates
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.