WHITE HOUSE

by RUBBERWALA HOUSING & INFRASTRUCTURE LTD. (Heks) · Mazgaon, MumbaiAlso near Byculla East, Lower Parel, Jacob Circle

Possession date of WHITE HOUSE: 30 June 2025, moved from 31 December 2018 (78 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51900003831. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (June 2025) has passed.

What do you want to know about WHITE HOUSE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of WHITE HOUSE has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51900011010)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 52.63% allottees for purpose of extension of RERA registration period of the said project.”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51900025627)

    Reason the builder gave MahaRERA: “We are already updated Part OC & Society Registration Certificate and also applied for Full OC. this is for request to Grant Extension upto 30.6.2025”

Source: WHITE HOUSE’s extension records on MahaRERA (P51900003831), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on WHITE HOUSE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900003831
Status
Lapsed (registration period ended)
Builder
RUBBERWALA HOUSING & INFRASTRUCTURE LTD.
Location
Mazgaon, Mumbai · 400033
Project type
Residential / Group Housing
Registered on
6 Aug 2017
Completion date at registration
December 2018
Latest completion date
June 2025
Delay so far
78 months
Homes
21
Sold or booked
100%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of WHITE HOUSE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WHITE HOUSE100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • WHITE HOUSE: covers 20 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on WHITE HOUSE every month.

WHITE HOUSE: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK778 – 81820
1 BHK3891

The builder’s record and reviews

Rubberwala Housing & Infrastructure (a group of 10 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 61 months); 7 still being built, 3 past the promised date (typically 30 months late); 1 lapsed. 13 complaints on MahaRERA across 2 projects.

Read Google reviews of WHITE HOUSE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

WHITE HOUSE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about WHITE HOUSE

What is the possession date of WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for WHITE HOUSE in Mazgaon, Mumbai is 30 June 2025 — 78 months later than 31 December 2018, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for WHITE HOUSE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date WHITE HOUSE's builder has filed on MahaRERA, the official one, is 30 June 2025, already 78 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of WHITE HOUSE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), WHITE HOUSE's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 52.63% allottees for purpose of extension of RERA registration period of the said project."; to 30 June 2025, giving the reason "We are already updated Part OC & Society Registration Certificate and also applied for Full OC. this is for request to Grant Extension upto 30.6.2025".

What is the RERA number of WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of WHITE HOUSE in Mazgaon, Mumbai is P51900003831.

Is WHITE HOUSE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), WHITE HOUSE is registered as P51900003831 and its status is "Lapsed (registration period ended)".

What is the construction status of WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated October 2026), WHITE HOUSE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on WHITE HOUSE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does WHITE HOUSE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is WHITE HOUSE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), WHITE HOUSE is registered on MahaRERA as P51900003831, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 78 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if WHITE HOUSE's possession date changes?

The latest dates are on WHITE HOUSE's MahaRERA page (P51900003831). GharKundli's Kundli Watch sends a free WhatsApp update on WHITE HOUSE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does WHITE HOUSE have?

According to GharKundli's check of MahaRERA records (updated October 2026), WHITE HOUSE has one building filed: WHITE HOUSE with 22 floors and 21 units.

What are the flat sizes (carpet area) in WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for WHITE HOUSE: 3 BHK: 778 to 818 sq ft carpet (20 homes); 1 BHK: 389 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated October 2026), WHITE HOUSE stands on 838 sq m of land (about 0.2 acres), with 3,529 sq m of sanctioned built-up area.

What is the track record of WHITE HOUSE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Rubberwala Housing & Infrastructure (a group of 10 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 61 months); 7 still being built, 3 past the promised date (typically 30 months late); 1 lapsed. 13 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of WHITE HOUSE?

Google Maps has reviews of WHITE HOUSE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is WHITE HOUSE?

WHITE HOUSE by RUBBERWALA HOUSING & INFRASTRUCTURE LTD. (Heks) is in Mazgaon, Mumbai (pincode 400033), near Byculla East, Lower Parel, Jacob Circle, Maharashtra, and is registered on MahaRERA as P51900003831, per GharKundli's check of MahaRERA records. Its boundaries filed there include TUKARAM BHISAJI KADAM MARG.

How many homes are in WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated October 2026), WHITE HOUSE has 21 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was WHITE HOUSE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), WHITE HOUSE was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on WHITE HOUSE?

No court cases are listed for WHITE HOUSE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of WHITE HOUSE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RUBBERWALA HOUSING & INFRASTRUCTURE LTD., the company Heks files this project under, which has 1 other project registered on MahaRERA.

Other projects in Mazgaon

All 17 projects in Mazgaon (400033) →

Other projects by RUBBERWALA HOUSING & INFRASTRUCTURE LTD.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.