by Neev Infrastructure Pvt. Ltd. · Mazgaon, Mumbai 400097Also near malad east, Kurar Village, Dindoshi
What’s in the report? →Possession date of Neev Galaxy (MahaRERA P51800003057): 30 September 2025, moved from 31 December 2018 (81 months later), and it has already passed. It has 34 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800003057. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800003057, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (September 2025) has passed.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about Neev Galaxy?
MahaRERA ki red-flag list mein hai. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Neev Galaxy has moved
31 December 2018
Completion date given when the project was registered
31 December 2019
Extended at the builder's request (MahaRERA application EXT51800001236)
Reason the builder gave MahaRERA:
“With regards to above mentioned project there is an illegal structure on DP Road and for the removal of that illegal structure a Suit was filed by the MCGM in the Hon’ble Bombay High Court. Hence, there is delay in completion of the said pr…” Read the full reason
“With regards to above mentioned project there is an illegal structure on DP Road and for the removal of that illegal structure a Suit was filed by the MCGM in the Hon’ble Bombay High Court. Hence, there is delay in completion of the said project. We are awaiting orders from the Hon’ble High Court and once the orders are received we shall continue with the completion of the said project. The project completion may require a period of more than one year. However, the extension period permitted vide the MahaRERA website is not beyond 1 year. Vide the present letter we are applying for an exten…”31 December 2021
Extended at the builder's request (MahaRERA application EXT51800006318)
Reason the builder gave MahaRERA: “Due to litigation the project is delayed.”
30 June 2024
Extended at the builder's request (MahaRERA application EXT51800011241)
Reason the builder gave MahaRERA: “Delayed due to Coronavirus”
30 September 2025
Extended at the builder's request (MahaRERA application EXT51800025118)
Reason the builder gave MahaRERA:
“The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, cau…” Read the full reason
“The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 30-09-2025. We hereby submit this application seeking an extension of the project under section 7 (3) of Maharera”
Source: Neev Galaxy’s extension records on MahaRERA (P51800003057), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Neev Galaxy
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the September 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800003057
- Status
- Lapsed (registration period ended)
- Builder
- Neev Infrastructure Pvt. Ltd.
- Location
- Mazgaon, Mumbai · 400097
- Project type
- Residential / Group Housing
- Registered on
- 4 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- September 2025
- Delay so far
- 81 months
- Homes
- 34
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Neev Galaxy, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NEEV GALAXY | 100% | 100% | 100% | 60% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Neev Galaxy every 1–2 months.
Neev Galaxy: buildings, flats and land, as filed on MahaRERA
- Buildings: NEEV GALAXY (13 floors)
- Land: 704 sq m (about 0.2 acres) · sanctioned built-up 996 sq m
- Land, as filed: 49/E
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Neev Infrastructure has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. 9 complaints on MahaRERA across 1 project.
Read Google reviews of Neev Galaxy →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Neev Galaxy: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Neev Galaxy
What is the possession date of Neev Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Neev Galaxy in Mazgaon, Mumbai is 30 September 2025 — 81 months later than 31 December 2018, the date given at registration. That date has already passed.
The date has already moved 81 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Neev Galaxy?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Neev Galaxy's builder has filed on MahaRERA, the official one, is 30 September 2025, already 81 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Neev Galaxy extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Neev Galaxy's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2019, giving the reason "With regards to above mentioned project there is an illegal structure on DP Road and for the removal of that illegal structure a Suit was filed by the MCGM in the Hon’ble Bombay High Court. Hence, there is delay in completion of the said project. We are awaiting orders from the Hon’ble High Court and once the orders are received we shall continue with the completion of the said project. The project completion may require a period of more than one year. However, the extension period permitted vide the MahaRERA website is not beyond 1 year. Vide the present letter we are applying for an exten…"; to 31 December 2021, giving the reason "Due to litigation the project is delayed."; to 30 June 2024, giving the reason "Delayed due to Coronavirus"; to 30 September 2025, giving the reason "The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 30-09-2025. We hereby submit this application seeking an extension of the project under section 7 (3) of Maharera".
What is the RERA number of Neev Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Neev Galaxy in Mazgaon, Mumbai is P51800003057.
Is Neev Galaxy registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neev Galaxy is registered as P51800003057 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the current construction status of Neev Galaxy? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Neev Galaxy's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NEEV GALAXY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Neev Galaxy have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Neev Galaxy safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Neev Galaxy is registered on MahaRERA as P51800003057, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 81 months since registration, no complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Neev Galaxy?
Neev Galaxy isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Neev Galaxy?
For a flat in Neev Galaxy (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Neev Galaxy received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Neev Galaxy isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Neev Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), Neev Galaxy's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Neev Galaxy uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Neev Galaxy was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Neev Galaxy's possession date changes?
The latest dates are on Neev Galaxy's MahaRERA page (P51800003057). GharKundli's Kundli Watch sends a free WhatsApp update on Neev Galaxy every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Neev Galaxy have?
According to GharKundli's check of MahaRERA records (updated October 2026), Neev Galaxy has one building filed: NEEV GALAXY with 13 floors.
How big is the land of Neev Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), Neev Galaxy stands on 704 sq m of land (about 0.2 acres), with 996 sq m of sanctioned built-up area.
What is the track record of Neev Galaxy's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Neev Infrastructure has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. 9 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Neev Galaxy?
Google Maps has reviews of Neev Galaxy written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Neev Galaxy?
Neev Galaxy by Neev Infrastructure Pvt. Ltd. is in Mazgaon, Mumbai, pincode 400097 (near malad east, Kurar Village, Dindoshi), Maharashtra, and is registered on MahaRERA as P51800003057, per GharKundli's check of MahaRERA records. Its land is filed as 49/E. GharKundli lists all 195 MahaRERA projects in Malad East (400097).
How many flats are in Neev Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), Neev Galaxy has 34 homes in 1 tower registered on MahaRERA.
When was Neev Galaxy registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neev Galaxy was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.
Does Neev Galaxy have any legal issues or court cases?
1 court case is listed for Neev Galaxy on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Neev Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Neev Infrastructure Pvt. Ltd..
Check it yourself on MahaRERA
- How to check the possession date of Neev Galaxy
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Malad East (400097)
- Maaria Annexe
- Hussaini Park
- Tarabaug
- Halima Residency
- 10 Harbour Estates
- Hamilton Mansion
- Continental Heights
- White House
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.