Dhunjibhoy Halima Residency

by DHUNJIBHOY ICE FACTORY PVT. LTD. · Mazgaon, Mumbai 400010Also near Dongri, Byculla, ChinchbunderRegistered on MahaRERA as “Halima Residency”

What’s in the report? →

Possession date of Dhunjibhoy Halima Residency (MahaRERA P51900006273): 30 April 2028, moved from 31 July 2023 (53 months later). It has 35 homes (1 BHK and 2 BHK, 370–827 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900006273, and currently active. Its completion date has moved from July 2023 to April 2028: 53 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51900006273, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Dhunjibhoy Halima Residency?

Possession date khiski: ab Apr 2028. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Dhunjibhoy Halima Residency has moved

  1. 31 July 2023

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA21072502115)

    Reason the builder gave MahaRERA: “Disruptions caused by the COVID-19 pandemic & tenant litigation in the High court but now its resolved. We appreciate your understanding and continued support. please allow Extension will do the needful.”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Dhunjibhoy Halima Residency’s extension records on MahaRERA (P51900006273), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Dhunjibhoy Halima Residency

Ready · October 2026 · 27 filings read

Risk & trust score locked/100
  • Risk & trust score, every point explained
  • What the title report on MahaRERA says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900006273
Status
Registered and active
Builder
DHUNJIBHOY ICE FACTORY PVT. LTD.
Location
Mazgaon, Mumbai · 400010
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
July 2023
Latest completion date
April 2028
Delay so far
53 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
35
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Yes
Latest construction certificate
13 Jul 2026

Construction progress of Dhunjibhoy Halima Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DHUNJIBHOY0%73%75%65%

Commencement certificate (CC), as filed on MahaRERA

  • DHUNJIBHOY: covers 7 floors

Latest CC order on MahaRERA: dated 07/07/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Dhunjibhoy Halima Residency every 1–2 months.

Dhunjibhoy Halima Residency: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Other515 – 60914
2 BHK802 – 82712
1 BHK370 – 6229

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Dhunjibhoy Halima Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Dhunjibhoy Halima Residency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Dhunjibhoy Halima Residency

What is the possession date of Dhunjibhoy Halima Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Dhunjibhoy Halima Residency in Mazgaon, Mumbai is 30 April 2028 — 53 months later than 31 July 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 53 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Dhunjibhoy Halima Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Dhunjibhoy Halima Residency's builder has filed on MahaRERA, the official one, is 30 April 2028, already 53 months later than the 31 July 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Dhunjibhoy Halima Residency extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Dhunjibhoy Halima Residency's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Disruptions caused by the COVID-19 pandemic & tenant litigation in the High court but now its resolved. We appreciate your understanding and continued support. please allow Extension will do the needful.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Dhunjibhoy Halima Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Dhunjibhoy Halima Residency in Mazgaon, Mumbai is P51900006273.

Is Dhunjibhoy Halima Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Dhunjibhoy Halima Residency is registered as P51900006273 and its status is "Registered and active".

What is the current construction status of Dhunjibhoy Halima Residency? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Dhunjibhoy Halima Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on DHUNJIBHOY is 73% done and internal work 75%. The latest construction certificate the builder filed there is dated 13 July 2026. GharKundli's full report compares construction progress with the deadline.

Does Dhunjibhoy Halima Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Dhunjibhoy Halima Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Dhunjibhoy Halima Residency is registered on MahaRERA as P51900006273, its completion date has moved 53 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Dhunjibhoy Halima Residency?

Dhunjibhoy Halima Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Dhunjibhoy Halima Residency are 370 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Dhunjibhoy Halima Residency?

For a flat in Dhunjibhoy Halima Residency (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Dhunjibhoy Halima Residency received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Dhunjibhoy Halima Residency is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Dhunjibhoy Halima Residency uploaded its title report on MahaRERA?

Yes. According to GharKundli's check of MahaRERA records (updated October 2026), an advocate's title report for Dhunjibhoy Halima Residency is uploaded on MahaRERA. It says who owns the land and whether there's any loan, case or claim on it. GharKundli's full report reads it and lists anything that needs a written answer from the builder.

A loan or claim on the land can hold up your flat or your home loan. See what the title report says →

How can I get updates if Dhunjibhoy Halima Residency's possession date changes?

The latest dates are on Dhunjibhoy Halima Residency's MahaRERA page (P51900006273). GharKundli's Kundli Watch sends a free WhatsApp update on Dhunjibhoy Halima Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Dhunjibhoy Halima Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), Dhunjibhoy Halima Residency has one building filed: DHUNJIBHOY with 8 floors and 35 units.

What are the flat sizes (carpet area) in Dhunjibhoy Halima Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Dhunjibhoy Halima Residency: Other: 515 to 609 sq ft carpet (14 homes); 2 BHK: 802 to 827 sq ft carpet (12 homes); 1 BHK: 370 to 622 sq ft carpet (9 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Dhunjibhoy Halima Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 24 covered car parking spaces for Dhunjibhoy Halima Residency.

How big is the land of Dhunjibhoy Halima Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Dhunjibhoy Halima Residency stands on 1,075 sq m of land (about 0.3 acres), with 4,051 sq m of sanctioned built-up area.

What are the reviews of Dhunjibhoy Halima Residency?

Google Maps has reviews of Dhunjibhoy Halima Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Dhunjibhoy Halima Residency?

Dhunjibhoy Halima Residency by DHUNJIBHOY ICE FACTORY PVT. LTD. is in Mazgaon, Mumbai, pincode 400010 (near Dongri, Byculla, Chinchbunder), Maharashtra, and is registered on MahaRERA as P51900006273, per GharKundli's check of MahaRERA records. Its boundaries filed there include NESBIT ROAD. Its land is filed as 6124. GharKundli lists all 47 MahaRERA projects in Mazgaon (400010).

How many flats are in Dhunjibhoy Halima Residency, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Dhunjibhoy Halima Residency has 35 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Dhunjibhoy Halima Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Dhunjibhoy Halima Residency was registered on MahaRERA on 14 August 2017. A title report on the land is on file there.

Does Dhunjibhoy Halima Residency have any legal issues or court cases?

No court cases are listed for Dhunjibhoy Halima Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Dhunjibhoy Halima Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DHUNJIBHOY ICE FACTORY PVT. LTD..

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Mazgaon (400010)

All 47 projects in Mazgaon (400010) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.