One India Tower

by One India Constructions Private Limited · Mazgaon, MumbaiAlso near Byculla East, Chinchbunder, Tank Road

Possession date of One India Tower: 30 April 2029, moved from 30 June 2021 (90 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900008466, and currently active. Its completion date has moved from June 2021 to April 2029: 90 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about One India Tower?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of One India Tower has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51900010436)

    Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS”
  3. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT51900013933)

    Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30/12/2024”
  4. 30 December 2028

    Extended at the builder's request (MahaRERA application EA25072502200)

    Reason the builder gave MahaRERA:
    “This letter is to formally request an extension of the project registration for our real estate project. One India Tower, registered under RERA registration number P51900008466, which is due to expire on 31-12-2024 Reason for Extension Requ…” Read the full reason“This letter is to formally request an extension of the project registration for our real estate project. One India Tower, registered under RERA registration number P51900008466, which is due to expire on 31-12-2024 Reason for Extension Request: However, the overall completion has been delayed due to challenges such as delayed approvals, shortage of skilled labor at various stages, and interruptions in the finishing work supply chain These factors have impacted the final handover schedule. We are now fully equipped to proceed with the remaining internal and external development work. Therefo…”
  5. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: One India Tower’s extension records on MahaRERA (P51900008466), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on One India Tower

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900008466
Status
Registered and active
Builder
One India Constructions Private Limited
Location
Mazgaon, Mumbai · 400010
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
June 2021
Latest completion date
April 2029
Delay so far
90 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
209
Sold or booked
73%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of One India Tower, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
One India Tower100%82%72%85%

Commencement certificate (CC), as filed on MahaRERA

  • One India Tower: covers 16th to 23rd fLOOR LEVEL

Want to know when this changes? Kundli Watch sends a free WhatsApp update on One India Tower every month.

One India Tower: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK190 – 472171
2 BHK559 – 71736
Shops100 – 1,1987
1 Room Kitchen182 – 2402
Office Space2,1391
  • Buildings: One India Tower (31 floors, 217 units)
  • Land: 1,314 sq m (about 0.3 acres) · sanctioned built-up 8,055 sq m
  • Boundaries filed include: Shivdas Chapsi Marg, J J Hospital
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of One India Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

One India Tower: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about One India Tower

What is the possession date of One India Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for One India Tower in Mazgaon, Mumbai is 30 April 2029 — 90 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for One India Tower?

Builders and listing sites often quote an earlier "target" date for handover. The completion date One India Tower's builder has filed on MahaRERA, the official one, is 30 April 2029, already 90 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of One India Tower extended?

According to GharKundli's check of MahaRERA records (updated October 2026), One India Tower's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS"; to 30 December 2024, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30/12/2024"; to 30 December 2028, giving the reason "This letter is to formally request an extension of the project registration for our real estate project. One India Tower, registered under RERA registration number P51900008466, which is due to expire on 31-12-2024 Reason for Extension Request: However, the overall completion has been delayed due to challenges such as delayed approvals, shortage of skilled labor at various stages, and interruptions in the finishing work supply chain These factors have impacted the final handover schedule. We are now fully equipped to proceed with the remaining internal and external development work. Therefo…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of One India Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of One India Tower in Mazgaon, Mumbai is P51900008466.

Is One India Tower registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), One India Tower is registered as P51900008466 and its status is "Registered and active".

What is the construction status of One India Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), One India Tower's status on MahaRERA is "Registered and active". As filed by the builder, slab work on One India Tower is 82% done and internal work 72%. GharKundli's full report compares construction progress with the deadline.

Does One India Tower have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is One India Tower safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), One India Tower is registered on MahaRERA as P51900008466, its completion date has moved 90 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if One India Tower's possession date changes?

The latest dates are on One India Tower's MahaRERA page (P51900008466). GharKundli's Kundli Watch sends a free WhatsApp update on One India Tower every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does One India Tower have?

According to GharKundli's check of MahaRERA records (updated October 2026), One India Tower has one building filed: One India Tower with 31 floors and 217 units.

What are the flat sizes (carpet area) in One India Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for One India Tower: 1 BHK: 190 to 472 sq ft carpet (171 homes); 2 BHK: 559 to 717 sq ft carpet (36 homes); 1 Room Kitchen: 182 to 240 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of One India Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), One India Tower stands on 1,314 sq m of land (about 0.3 acres), with 8,055 sq m of sanctioned built-up area.

Where can I read reviews of One India Tower?

Google Maps has reviews of One India Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is One India Tower?

One India Tower by One India Constructions Private Limited is in Mazgaon, Mumbai (pincode 400010), near Byculla East, Chinchbunder, Tank Road, Maharashtra, and is registered on MahaRERA as P51900008466, per GharKundli's check of MahaRERA records. Its boundaries filed there include Shivdas Chapsi Marg, J J Hospital.

How many homes are in One India Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), One India Tower has 209 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.

When was One India Tower registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), One India Tower was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on One India Tower?

No court cases are listed for One India Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of One India Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is One India Constructions Private Limited.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in pincode 400010

All 47 projects in Mazgaon (400010) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.