Skip to content
GharKundli

52 Avenue

by HEKS REALTY (Rubberwala) · Mazgaon, MumbaiAlso near Byculla, Lower Parel, Saatraasta

Possession date of 52 Avenue: 31 December 2028, moved from 30 December 2024 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900020639, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about 52 Avenue?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of 52 Avenue has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EA14082622135)

    Reason the builder gave MahaRERA:
    “Background of the Project The above-mentioned project was duly registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA). The Promoter has consistently endeavoured to execute and complete the project in accordance with the…” Read the full reason“Background of the Project The above-mentioned project was duly registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA). The Promoter has consistently endeavoured to execute and complete the project in accordance with the approved plans and statutory requirements. However, owing to several unforeseen and unavoidable circumstances beyond the reasonable control of the Promoter, the project could not be completed within the originally stipulated registration period. Reasons for Seeking Extension The progress of the project has been adversely impacted due to a combination of…”

Source: 52 Avenue’s extension records on MahaRERA (P51900020639), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on 52 Avenue

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 court cases, and how it ended
  • Construction pace against the December 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900020639
Status
Registered and active
Builder
HEKS REALTY
Location
Mazgaon, Mumbai · 400010
Project type
Residential / Group Housing
Registered on
30 Apr 2019
Completion date at registration
December 2024
Latest completion date
December 2028
Delay so far
48 months
Homes
51
Sold or booked
73%
Towers
1
Complaints on MahaRERA
0
Court cases listed
2
Title report on file
Not found

Construction progress of 52 Avenue, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
52 Avenue33%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • 52 Avenue: covers 24 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 52 Avenue every month.

52 Avenue: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK750 – 1,12526
3 BHK944 – 1,43018
1 BHK566 – 7506
4 BHK1,3521
  • Buildings: 52 Avenue (21 floors, 51 units)
  • Land: 629 sq m (about 0.2 acres) · sanctioned built-up 3,075 sq m
  • Boundaries filed include: Cork Road, Dadaji Kondeo Marg
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Rubberwala Housing & Infrastructure (a group of 10 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 61 months); 7 still being built, 3 past the promised date (typically 30 months late); 1 lapsed. 13 complaints on MahaRERA across 2 projects.

Read Google reviews of 52 Avenue →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

52 Avenue: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 52 Avenue

What is the possession date of 52 Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 52 Avenue in Mazgaon, Mumbai is 31 December 2028 — 48 months later than 30 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for 52 Avenue?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 52 Avenue's builder has filed on MahaRERA, the official one, is 31 December 2028, already 48 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of 52 Avenue extended?

According to GharKundli's check of MahaRERA records (updated October 2026), 52 Avenue's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "Background of the Project The above-mentioned project was duly registered with the Maharashtra Real Estate Regulatory Authority (MahaRERA). The Promoter has consistently endeavoured to execute and complete the project in accordance with the approved plans and statutory requirements. However, owing to several unforeseen and unavoidable circumstances beyond the reasonable control of the Promoter, the project could not be completed within the originally stipulated registration period. Reasons for Seeking Extension The progress of the project has been adversely impacted due to a combination of…".

What is the RERA number of 52 Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 52 Avenue in Mazgaon, Mumbai is P51900020639.

Is 52 Avenue registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 52 Avenue is registered as P51900020639 and its status is "Registered and active". On MahaRERA's own list: Sales frozen by MahaRERA: completion date lapsed. MahaRERA has put this project in abeyance because its completion date has lapsed. Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.

What is the construction status of 52 Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), 52 Avenue's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 52 Avenue is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does 52 Avenue have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is 52 Avenue safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), 52 Avenue is registered on MahaRERA as P51900020639, its completion date has moved 48 months since registration, no complaints are listed against it and it is on MahaRERA's list "Sales frozen by MahaRERA: completion date lapsed". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 52 Avenue's possession date changes?

The latest dates are on 52 Avenue's MahaRERA page (P51900020639). GharKundli's Kundli Watch sends a free WhatsApp update on 52 Avenue every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 52 Avenue have?

According to GharKundli's check of MahaRERA records (updated October 2026), 52 Avenue has one building filed: 52 Avenue with 21 floors and 51 units.

What are the flat sizes (carpet area) in 52 Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for 52 Avenue: 2 BHK: 750 to 1125 sq ft carpet (26 homes); 3 BHK: 944 to 1430 sq ft carpet (18 homes); 1 BHK: 566 to 750 sq ft carpet (6 homes); 4 BHK: 1352 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of 52 Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), 52 Avenue stands on 629 sq m of land (about 0.2 acres), with 3,075 sq m of sanctioned built-up area.

What is the track record of 52 Avenue's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Rubberwala Housing & Infrastructure (a group of 10 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 61 months); 7 still being built, 3 past the promised date (typically 30 months late); 1 lapsed. 13 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of 52 Avenue?

Google Maps has reviews of 52 Avenue written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 52 Avenue?

52 Avenue by HEKS REALTY (Rubberwala) is in Mazgaon, Mumbai (pincode 400010), near Byculla, Lower Parel, Saatraasta, Maharashtra, and is registered on MahaRERA as P51900020639, per GharKundli's check of MahaRERA records. Its boundaries filed there include Cork Road, Dadaji Kondeo Marg.

How many homes are in 52 Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), 52 Avenue has 51 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.

When was 52 Avenue registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 52 Avenue was registered on MahaRERA on 30 April 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on 52 Avenue?

2 court cases are listed for 52 Avenue on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of 52 Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HEKS REALTY, the company Rubberwala files this project under.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in pincode 400010

All 47 projects in Mazgaon (400010) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.