A. M. Residency
by ALFA MANA REALTORS PVT LTD · Next To Diamond Jubilee School, MumbaiAlso near Mazgaon, Chinchbunder, Sewri
Possession date of A. M. Residency: 31 December 2026, moved from 29 September 2020 (75 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900000070, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about A. M. Residency?
How the possession date of A. M. Residency has moved
29 September 2020
Completion date given when the project was registered
31 March 2022
Extended at the builder's request (MahaRERA application EXT51900009298)
Reason the builder gave MahaRERA:
“DUE TO COVID 19, LOCKDOWN SITUATION 18TH MARCH TO 31ST JULY 2020, WE WERE UNABLE TO COMPLETE THE PROJECT AND FINAL IOD SUBMITTED ON 17TH NOVEMBER 2020, BUT ISSUE OF THE SAME IS AWAITED (THE POLICY FOR PREMIUM REDUCTION IS FINALIZED. NOW VID…” Read the full reason
“DUE TO COVID 19, LOCKDOWN SITUATION 18TH MARCH TO 31ST JULY 2020, WE WERE UNABLE TO COMPLETE THE PROJECT AND FINAL IOD SUBMITTED ON 17TH NOVEMBER 2020, BUT ISSUE OF THE SAME IS AWAITED (THE POLICY FOR PREMIUM REDUCTION IS FINALIZED. NOW VIDE NOTIFICATION NO. TPS-1820/ANO.27/PR.NO. 80/20/NOV 13 DATED 14.01.2021. WE MADE OUR PAYMENT ON 5TH MARCH 2021. THE IOD IS EXPECTED TO BE ISSUED ON 12TH MARCH 2021 AND FURTHER CC IS YET AWAITED, HENCE EXTENSION IS REQUIRED.”31 December 2023
Extended at the builder's request (MahaRERA application EXT51900012563)
Reason the builder gave MahaRERA:
“DUE TO COVID 19, LOCKDOWN SITUATION 18TH MARCH TO 31ST JULY 2020, WE WERE UNABLE TO COMPLETE THE PROJECT AND FINAL IOD SUBMITTED ON 17TH NOVEMBER 2020, BUT ISSUE OF THE SAME IS AWAITED (THE POLICY FOR PREMIUM REDUCTION IS FINALIZED. NOW VID…” Read the full reason
“DUE TO COVID 19, LOCKDOWN SITUATION 18TH MARCH TO 31ST JULY 2020, WE WERE UNABLE TO COMPLETE THE PROJECT AND FINAL IOD SUBMITTED ON 17TH NOVEMBER 2020, BUT ISSUE OF THE SAME IS AWAITED (THE POLICY FOR PREMIUM REDUCTION IS FINALIZED. NOW VIDE NOTIFICATION NO. TPS-1820/ANO.27/PR.NO. 80/20/NOV 13 DATED 14.01.2021. WE MADE OUR PAYMENT ON 5TH MARCH 2021. THE IOD IS EXPECTED TO BE ISSUED ON 12TH MARCH 2021 AND FURTHER CC IS YET AWAITED, HENCE EXTENSION IS REQUIRED.”31 December 2024
Extended at the builder's request (MahaRERA application EXT51900018793)
Reason the builder gave MahaRERA:
“The Approval i.e. BMC IOD & CC which was issued till that level the project is completed & Occupation Certificate is obtained & handed over Flats to all buyers , old Rehab tenants & Government reserve Flats to Government. the balance approv…” Read the full reason
“The Approval i.e. BMC IOD & CC which was issued till that level the project is completed & Occupation Certificate is obtained & handed over Flats to all buyers , old Rehab tenants & Government reserve Flats to Government. the balance approval IOD is issued CC is awaited and same is expected to be issued in January 2024 hence the delay is due to delay in approval.”31 December 2025
Extended at the builder's request (MahaRERA application EXT51900025937)
Reason the builder gave MahaRERA:
“The Approval i.e. BMC IOD & CC which was issued till that level the project is completed & Occupation Certificate is obtained & handed over Flats to all buyers, old Rehab tenants & Government reserve Flats to Government the further balance…” Read the full reason
“The Approval i.e. BMC IOD & CC which was issued till that level the project is completed & Occupation Certificate is obtained & handed over Flats to all buyers, old Rehab tenants & Government reserve Flats to Government the further balance approval IOD and CC is issued on 4th March 2024 , work is completed 80%. RCC + Bandkaam +Plaster etc only finishing work is in progress expected to be completed by February 2025 and the sale of flat will be done alongwith it.The delay is due to delay in approval by MCGM.”31 December 2026
Extended at the builder's request (MahaRERA application EA07012619342)
Reason the builder gave MahaRERA: “IOD AMENDED AND CC ISSUED IN MAR 24 WORK IS IN PROGRESS EXPECTED TO BE COMPLETED BY JUNE 26 AND THE SALE OF FLAT WILL BE DONE ALONG WITH IT. THE DELAYED IN APPROVAL FROM MOEF FINAL NOC SO WE NEED AN EXTENSION.”
Source: A. M. Residency’s extension records on MahaRERA (P51900000070), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on A. M. Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 14 court cases, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900000070
- Status
- Registered and active
- Builder
- ALFA MANA REALTORS PVT LTD
- Location
- Next To Diamond Jubilee School, Mumbai · 400010
- Project type
- Mixed
- Registered on
- 22 Jun 2017
- Completion date at registration
- September 2020
- Latest completion date
- December 2026
- Delay so far
- 75 months
- Homes
- 340
- Sold or booked
- 57%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 14
- Title report on file
- Not found
Construction progress of A. M. Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 1 | 100% | 100% | 95% | 100% |
| BUILDING NO 2 | 100% | 100% | 95% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 1: covers 9 floors
- BUILDING NO 2: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on A. M. Residency every month.
A. M. Residency: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 352 – 489 | 224 |
| 2 BHK | 608 – 713 | 81 |
| 3 BHK | 713 – 716 | 24 |
| Other | 352 – 713 | 13 |
| Shops | 186 – 753 | 2 |
| 5 BHK | 713 | 1 |
- Buildings: BUILDING NO 1 (9 floors, 237 units) · BUILDING NO 2 (9 floors, 108 units)
- Car parking: 81 open
- Land: 3,654 sq m (about 0.9 acres) · sanctioned built-up 13,052 sq m · recreational space 3,654 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Alfa Mana Realtors (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 37 months late). No complaints on MahaRERA.
Read Google reviews of A. M. Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
A. M. Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about A. M. Residency
What is the possession date of A. M. Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for A. M. Residency in Next To Diamond Jubilee School, Mumbai is 31 December 2026 — 75 months later than 29 September 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for A. M. Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date A. M. Residency's builder has filed on MahaRERA, the official one, is 31 December 2026, already 75 months later than the 29 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of A. M. Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), A. M. Residency's builder applied to MahaRERA to extend the completion date 5 times: to 31 March 2022, giving the reason "DUE TO COVID 19, LOCKDOWN SITUATION 18TH MARCH TO 31ST JULY 2020, WE WERE UNABLE TO COMPLETE THE PROJECT AND FINAL IOD SUBMITTED ON 17TH NOVEMBER 2020, BUT ISSUE OF THE SAME IS AWAITED (THE POLICY FOR PREMIUM REDUCTION IS FINALIZED. NOW VIDE NOTIFICATION NO. TPS-1820/ANO.27/PR.NO. 80/20/NOV 13 DATED 14.01.2021. WE MADE OUR PAYMENT ON 5TH MARCH 2021. THE IOD IS EXPECTED TO BE ISSUED ON 12TH MARCH 2021 AND FURTHER CC IS YET AWAITED, HENCE EXTENSION IS REQUIRED."; to 31 December 2023, giving the reason "DUE TO COVID 19, LOCKDOWN SITUATION 18TH MARCH TO 31ST JULY 2020, WE WERE UNABLE TO COMPLETE THE PROJECT AND FINAL IOD SUBMITTED ON 17TH NOVEMBER 2020, BUT ISSUE OF THE SAME IS AWAITED (THE POLICY FOR PREMIUM REDUCTION IS FINALIZED. NOW VIDE NOTIFICATION NO. TPS-1820/ANO.27/PR.NO. 80/20/NOV 13 DATED 14.01.2021. WE MADE OUR PAYMENT ON 5TH MARCH 2021. THE IOD IS EXPECTED TO BE ISSUED ON 12TH MARCH 2021 AND FURTHER CC IS YET AWAITED, HENCE EXTENSION IS REQUIRED."; to 31 December 2024, giving the reason "The Approval i.e. BMC IOD & CC which was issued till that level the project is completed & Occupation Certificate is obtained & handed over Flats to all buyers , old Rehab tenants & Government reserve Flats to Government. the balance approval IOD is issued CC is awaited and same is expected to be issued in January 2024 hence the delay is due to delay in approval."; to 31 December 2025, giving the reason "The Approval i.e. BMC IOD & CC which was issued till that level the project is completed & Occupation Certificate is obtained & handed over Flats to all buyers, old Rehab tenants & Government reserve Flats to Government the further balance approval IOD and CC is issued on 4th March 2024 , work is completed 80%. RCC + Bandkaam +Plaster etc only finishing work is in progress expected to be completed by February 2025 and the sale of flat will be done alongwith it.The delay is due to delay in approval by MCGM."; to 31 December 2026, giving the reason "IOD AMENDED AND CC ISSUED IN MAR 24 WORK IS IN PROGRESS EXPECTED TO BE COMPLETED BY JUNE 26 AND THE SALE OF FLAT WILL BE DONE ALONG WITH IT. THE DELAYED IN APPROVAL FROM MOEF FINAL NOC SO WE NEED AN EXTENSION.".
What is the RERA number of A. M. Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of A. M. Residency in Next To Diamond Jubilee School, Mumbai is P51900000070.
Is A. M. Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), A. M. Residency is registered as P51900000070 and its status is "Registered and active".
What is the construction status of A. M. Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), A. M. Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does A. M. Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is A. M. Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), A. M. Residency is registered on MahaRERA as P51900000070, its completion date has moved 75 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if A. M. Residency's possession date changes?
The latest dates are on A. M. Residency's MahaRERA page (P51900000070). GharKundli's Kundli Watch sends a free WhatsApp update on A. M. Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does A. M. Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), A. M. Residency has 2 buildings filed: BUILDING NO 1 with 9 floors and 237 units; BUILDING NO 2 with 9 floors and 108 units.
What are the flat sizes (carpet area) in A. M. Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for A. M. Residency: 1 BHK: 352 to 489 sq ft carpet (224 homes); 2 BHK: 608 to 713 sq ft carpet (81 homes); 3 BHK: 713 to 716 sq ft carpet (24 homes); 5 BHK: 713 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does A. M. Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 81 open car parking spaces for A. M. Residency.
How big is the land of A. M. Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), A. M. Residency stands on 3,654 sq m of land (about 0.9 acres), with 13,052 sq m of sanctioned built-up area and 3,654 sq m of recreational open space.
What is the track record of A. M. Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Alfa Mana Realtors (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 37 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of A. M. Residency?
Google Maps has reviews of A. M. Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is A. M. Residency?
A. M. Residency by ALFA MANA REALTORS PVT LTD is in Next To Diamond Jubilee School, Mumbai (pincode 400010), near Mazgaon, Chinchbunder, Sewri, Maharashtra, and is registered on MahaRERA as P51900000070, per GharKundli's check of MahaRERA records.
How many homes are in A. M. Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), A. M. Residency has 340 homes in 2 towers registered on MahaRERA, and 57% of them are sold or booked.
When was A. M. Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), A. M. Residency was registered on MahaRERA on 22 June 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on A. M. Residency?
14 court cases are listed for A. M. Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of A. M. Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ALFA MANA REALTORS PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of A. M. Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Ward E
- IBRAHIM RESIDENCY
- BISMILLAH ARCADE 2
- Presidence Eternia
- CHAITYA 777
- RAHEJA MODERN VIVAREA NORTH TOWER
- PARSHWA LOTUS & RANGARI HEIGHTS
- 52 Avenue
- MONTESOUTH-6
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.