CHAITYA 777

by M/s. CHAITYA DEVELOPERS · Chinchpokli, MumbaiAlso near Mazgaon, Byculla, Lower Parel

Possession date of CHAITYA 777: 30 April 2032, moved from 30 December 2025 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900022725, and currently active. Its completion date has moved from December 2025 to April 2032: 72 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about CHAITYA 777?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of CHAITYA 777 has moved

  1. 30 December 2025

    Completion date given when the project was registered

  2. 31 December 2031

    Extended at the builder's request (MahaRERA application EA24022619983)

    Reason the builder gave MahaRERA:
    “We, M/s. Chaitya Developers, Promoter of the above-mentioned project, respectfully submit that the project was originally registered with MahaRERA based on the IOD sanction up to 28 floors. Subsequently, pursuant to revised planning permiss…” Read the full reason“We, M/s. Chaitya Developers, Promoter of the above-mentioned project, respectfully submit that the project was originally registered with MahaRERA based on the IOD sanction up to 28 floors. Subsequently, pursuant to revised planning permissions and enhanced development potential, we have obtained revised sanction up to 46 floors. The revised scope includes vertical expansion along with the addition of Wings B & C and extension of A Wing. Necessary regulatory approvals have been obtained, and construction will proceed as per the revised sanctioned plans. The declaration for correction reflec…”
  3. 30 April 2032

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: CHAITYA 777’s extension records on MahaRERA (P51900022725), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on CHAITYA 777

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2032 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900022725
Status
Registered and active
Builder
M/s. CHAITYA DEVELOPERS
Location
Chinchpokli, Mumbai · 400012
Project type
Residential / Group Housing
Registered on
16 Oct 2019
Completion date at registration
December 2025
Latest completion date
April 2032
Delay so far
72 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
156
Sold or booked
90%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of CHAITYA 777, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
CHAITYA 777100%100%90%90%

Commencement certificate (CC), as filed on MahaRERA

  • CHAITYA 777: covers Ground + 35 Upper Floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on CHAITYA 777 every month.

CHAITYA 777: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK669 – 967105
3 BHK703 – 96751

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of CHAITYA 777 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

CHAITYA 777: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about CHAITYA 777

What is the possession date of CHAITYA 777?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for CHAITYA 777 in Chinchpokli, Mumbai is 30 April 2032 — 72 months later than 30 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for CHAITYA 777?

Builders and listing sites often quote an earlier "target" date for handover. The completion date CHAITYA 777's builder has filed on MahaRERA, the official one, is 30 April 2032, already 72 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of CHAITYA 777 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), CHAITYA 777's builder applied to MahaRERA to extend the completion date once: to 31 December 2031, giving the reason "We, M/s. Chaitya Developers, Promoter of the above-mentioned project, respectfully submit that the project was originally registered with MahaRERA based on the IOD sanction up to 28 floors. Subsequently, pursuant to revised planning permissions and enhanced development potential, we have obtained revised sanction up to 46 floors. The revised scope includes vertical expansion along with the addition of Wings B & C and extension of A Wing. Necessary regulatory approvals have been obtained, and construction will proceed as per the revised sanctioned plans. The declaration for correction reflec…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of CHAITYA 777?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of CHAITYA 777 in Chinchpokli, Mumbai is P51900022725.

Is CHAITYA 777 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), CHAITYA 777 is registered as P51900022725 and its status is "Registered and active".

What is the construction status of CHAITYA 777?

According to GharKundli's check of MahaRERA records (updated October 2026), CHAITYA 777's status on MahaRERA is "Registered and active". As filed by the builder, slab work on CHAITYA 777 is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does CHAITYA 777 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is CHAITYA 777 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), CHAITYA 777 is registered on MahaRERA as P51900022725, its completion date has moved 72 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if CHAITYA 777's possession date changes?

The latest dates are on CHAITYA 777's MahaRERA page (P51900022725). GharKundli's Kundli Watch sends a free WhatsApp update on CHAITYA 777 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does CHAITYA 777 have?

According to GharKundli's check of MahaRERA records (updated October 2026), CHAITYA 777 has one building filed: CHAITYA 777 with 28 floors and 156 units.

What are the flat sizes (carpet area) in CHAITYA 777?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for CHAITYA 777: 2 BHK: 669 to 967 sq ft carpet (105 homes); 3 BHK: 703 to 967 sq ft carpet (51 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of CHAITYA 777?

According to GharKundli's check of MahaRERA records (updated October 2026), CHAITYA 777 stands on 5,229 sq m of land (about 1.3 acres), with 20,607 sq m of sanctioned built-up area and 593 sq m of recreational open space.

Where can I read reviews of CHAITYA 777?

Google Maps has reviews of CHAITYA 777 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is CHAITYA 777?

CHAITYA 777 by M/s. CHAITYA DEVELOPERS is in Chinchpokli, Mumbai (pincode 400012), near Mazgaon, Byculla, Lower Parel, Maharashtra, and is registered on MahaRERA as P51900022725, per GharKundli's check of MahaRERA records.

How many homes are in CHAITYA 777?

According to GharKundli's check of MahaRERA records (updated October 2026), CHAITYA 777 has 156 homes in 1 tower registered on MahaRERA, and 90% of them are sold or booked.

When was CHAITYA 777 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), CHAITYA 777 was registered on MahaRERA on 16 October 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on CHAITYA 777?

No court cases are listed for CHAITYA 777 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of CHAITYA 777?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. CHAITYA DEVELOPERS.