Madhoor Aurum
by MADHOOR BUILDWELL PRIVATE LIMITED · Dadar, Mumbai 400019Also near Matunga, Wadala West, Hindu Colony
What’s in the report? →Possession date of Madhoor Aurum (MahaRERA P51900077613): 30 October 2029. It has 26 homes (2 BHK, 3 BHK and 4 BHK, 585–1731 sq ft carpet), 27% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900077613, and currently active. Its completion date is now October 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51900077613, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Madhoor Aurum?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Madhoor Aurum has moved
30 June 2029
Completion date given when the project was registered
30 October 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Madhoor Aurum’s extension records on MahaRERA (P51900077613), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Madhoor Aurum
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900077613
- Status
- Registered and active
- Builder
- MADHOOR BUILDWELL PRIVATE LIMITED
- Location
- Dadar, Mumbai · 400019
- Project type
- Residential / Group Housing
- Registered on
- 15 Oct 2024
- Completion date at registration
- June 2029
- Latest completion date
- October 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 26
- Sold or booked
- 27%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Madhoor Aurum, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MADHOOR AURM | 100% | 15% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- MADHOOR AURM: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Madhoor Aurum every 1–2 months.
Madhoor Aurum: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 585 – 962 | 20 |
| 3 BHK | 891 – 1,100 | 3 |
| 4 BHK | 1,487 – 1,530 | 2 |
| 6 BHK | 1,731 | 1 |
- Buildings: MADHOOR AURM (22 floors, 26 units)
- Land: 528 sq m (about 0.1 acres) · sanctioned built-up 2,465 sq m
- Boundaries filed include: Sir Bhalchandra Road
- Land, as filed: 248/10
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Madhoor Buildwell (a group of 2 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 19 months); 3 still being built, 2 past the promised date (typically 32 months late). 3 complaints on MahaRERA across 1 project.
Read Google reviews of Madhoor Aurum →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Madhoor Aurum: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Madhoor Aurum
What is the possession date of Madhoor Aurum?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Madhoor Aurum in Dadar, Mumbai is 30 October 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Madhoor Aurum?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Madhoor Aurum's builder has filed on MahaRERA, the official one, is 30 October 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Madhoor Aurum?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Madhoor Aurum in Dadar, Mumbai is P51900077613.
Is Madhoor Aurum registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhoor Aurum is registered as P51900077613 and its status is "Registered and active".
What is the current construction status of Madhoor Aurum? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhoor Aurum's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MADHOOR AURM is 15% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Madhoor Aurum have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Madhoor Aurum safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhoor Aurum is registered on MahaRERA as P51900077613, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Madhoor Aurum?
Madhoor Aurum is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Madhoor Aurum are 585 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Madhoor Aurum?
For a flat in Madhoor Aurum (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Madhoor Aurum received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Madhoor Aurum is still under construction, with 30 October 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Madhoor Aurum a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhoor Aurum is a redevelopment: 15 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Madhoor Aurum uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Madhoor Aurum was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Madhoor Aurum's possession date changes?
The latest dates are on Madhoor Aurum's MahaRERA page (P51900077613). GharKundli's Kundli Watch sends a free WhatsApp update on Madhoor Aurum every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Madhoor Aurum have?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhoor Aurum has one building filed: MADHOOR AURM with 22 floors and 26 units.
What are the flat sizes (carpet area) in Madhoor Aurum?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Madhoor Aurum: 2 BHK: 585 to 962 sq ft carpet (20 homes); 3 BHK: 891 to 1100 sq ft carpet (3 homes); 4 BHK: 1487 to 1530 sq ft carpet (2 homes); 6 BHK: 1731 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Madhoor Aurum?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhoor Aurum stands on 528 sq m of land (about 0.1 acres), with 2,465 sq m of sanctioned built-up area.
What is the track record of Madhoor Aurum's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhoor Buildwell (a group of 2 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 19 months); 3 still being built, 2 past the promised date (typically 32 months late). 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Madhoor Aurum?
Google Maps has reviews of Madhoor Aurum written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Madhoor Aurum?
Madhoor Aurum by MADHOOR BUILDWELL PRIVATE LIMITED is in Dadar, Mumbai, pincode 400019 (near Matunga, Wadala West, Hindu Colony), Maharashtra, and is registered on MahaRERA as P51900077613, per GharKundli's check of MahaRERA records. Its boundaries filed there include Sir Bhalchandra Road. Its land is filed as 248/10. GharKundli lists all 104 MahaRERA projects in Matunga (400019).
How many flats are in Madhoor Aurum, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhoor Aurum has 26 homes in 1 tower registered on MahaRERA, and 27% of them are sold or booked.
When was Madhoor Aurum registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhoor Aurum was registered on MahaRERA on 15 October 2024. GharKundli did not find a title report on the land on file there.
Does Madhoor Aurum have any legal issues or court cases?
No court cases are listed for Madhoor Aurum on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Madhoor Aurum?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MADHOOR BUILDWELL PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of Madhoor Aurum
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai City →
Other projects in Matunga (400019)
All 104 projects in Matunga (400019) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.